County of Modoc9 audit years11 findings9 repeat
9
Audit Years
11
Total Findings
9
Repeat Findings
$6.1M
Federal Awards Expended (FY 2024)

FY 2024-06-30

$6,135,457 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on August 1, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by February 1, 2026 (215 days ago).

What is a management decision? →
2024-002
Procurement & Suspension/Debarment
MATERIAL WEAKNESSREPEAT OF 2023-001

During our testing, we noted that management’s review of contracts did not include a review to ensure that the party was not debarred, suspended or otherwise excluded. Questioned costs: None. Context: Audit procedures included a review of the three agreements during the year ended June 30, 2024, which represented the entire population. For all of the items reviewed management did not obtain verification that the party was not debarred, suspended or otherwise excluded, prior to entering into the transactions. However, upon subsequent review, no parties were determined the be debarred, suspended or otherwise excluded. Cause: The County’s procurement process did not include a requirement that required a verification of debarred or suspended status. Effect: Amounts could be paid to parties that are debarred, suspended or otherwise excluded. Repeat Finding: Yes Recommendation: We recommend that management enhance the procurement controls to ensure that all required parties are reviewed for suspension and debarment prior to entering the transaction. Views of responsible officials: The County agrees with the findings. Corrective action plan: The County has developed a formal policy, which has been distributed to all departments. The policy is scheduled to take effect in Fiscal Year 2024–2025.

Show full finding ▾
Full finding narrative

Criteria or specific requirement: Per 2 CFR 200 Appendix II (H) Debarment and Suspension (Executive Orders 12549 and 12689)—A contract award (see 2 CFR 180.220) must not be made to parties listed on the governmentwide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. Condition: During our testing, we noted that management’s review of contracts did not include a review to ensure that the party was not debarred, suspended or otherwise excluded. Questioned costs: None. Context: Audit procedures included a review of the three agreements during the year ended June 30, 2024, which represented the entire population. For all of the items reviewed management did not obtain verification that the party was not debarred, suspended or otherwise excluded, prior to entering into the transactions. However, upon subsequent review, no parties were determined the be debarred, suspended or otherwise excluded. Cause: The County’s procurement process did not include a requirement that required a verification of debarred or suspended status. Effect: Amounts could be paid to parties that are debarred, suspended or otherwise excluded. Repeat Finding: Yes Recommendation: We recommend that management enhance the procurement controls to ensure that all required parties are reviewed for suspension and debarment prior to entering the transaction. Views of responsible officials: The County agrees with the findings. Corrective action plan: The County has developed a formal policy, which has been distributed to all departments. The policy is scheduled to take effect in Fiscal Year 2024–2025.

Corrective Action Plan

Suspension & Debarment Recommendation: As part of its procurement process, the County should obtain verification that the vendor or subrecipient is not suspended or debarred. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action planned in response to finding: While several departments at the County have been checking this internally, we will work on a more formal procedure that will require the departments to show proof of verification that the vendor or subrecipient is not suspended or debarred prior to release of payment. Name(s) of the contact person(s) responsible for corrective action: Stephanie Wellemeyer, Auditor/Clerk Planned completion date for corrective action plan: During fiscal year 2024/2025.

Prior Finding References

2023-001

About Procurement and Suspension and Debarment →

FY 2023-06-30

$6,137,114 federal awards expended

FAC accepted this audit on October 25, 2024 — management decision was due April 25, 2025.

2023-001
Procurement & Suspension/Debarment
MATERIAL WEAKNESS

During our testing, we noted that management’s review of contracts did not include a review to ensure that the party was not debarred, suspended or otherwise excluded. Questioned costs: None. Context: Audit procedures included a review of the five agreements during the year ended June 30, 2023, which represented the entire population. For all of the items reviewed management did not obtain verification that the party was not debarred, suspended or otherwise excluded, prior to entering into the transactions. However, upon subsequent review, no parties were determined the be debarred, suspended or otherwise excluded. Cause: The County’s procurement process did not include a requirement that required a verification of debarred or suspended status. Effect: Amounts could be paid to parties that are debarred, suspended or otherwise excluded. Repeat Finding: No Recommendation: We recommend that management enhance the procurement controls to ensure that all required parties are reviewed for suspension and debarment prior to entering the transaction. Views of responsible officials: The County agrees with the findings. Corrective action plan: While several departments at the County have been checking this internally, we will work on a more formal procedure that will require the departments to show proof of verification that the vendor or subrecipient is not suspended or debarred prior to release of payment.

Show full finding ▾
Full finding narrative

Federal Agency: Department of Health and Human Services Federal Program Title: COVID-19 Epidemiology and Laboratory for Capacity Testing ALN: 93.323 Pass-Through Agency: State of California Department of Health and Human Services Pass-Through Number(s): N/A Award Number and Period: N/A Type of Finding: Material Weakness in Internal Control over Compliance and Noncompliance Criteria or specific requirement: Per 2 CFR 200 Appendix II (H) Debarment and Suspension (Executive Orders 12549 and 12689)—A contract award (see 2 CFR 180.220) must not be made to parties listed on the governmentwide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. Condition: During our testing, we noted that management’s review of contracts did not include a review to ensure that the party was not debarred, suspended or otherwise excluded. Questioned costs: None. Context: Audit procedures included a review of the five agreements during the year ended June 30, 2023, which represented the entire population. For all of the items reviewed management did not obtain verification that the party was not debarred, suspended or otherwise excluded, prior to entering into the transactions. However, upon subsequent review, no parties were determined the be debarred, suspended or otherwise excluded. Cause: The County’s procurement process did not include a requirement that required a verification of debarred or suspended status. Effect: Amounts could be paid to parties that are debarred, suspended or otherwise excluded. Repeat Finding: No Recommendation: We recommend that management enhance the procurement controls to ensure that all required parties are reviewed for suspension and debarment prior to entering the transaction. Views of responsible officials: The County agrees with the findings. Corrective action plan: While several departments at the County have been checking this internally, we will work on a more formal procedure that will require the departments to show proof of verification that the vendor or subrecipient is not suspended or debarred prior to release of payment.

Corrective Action Plan

Federal Agency: Department of Health and Human Services Federal Program Title: COVID-19 Epidemiology and Laboratory for Capacity Testing ALN: 93.323 Pass-Through Agency: State of California Department of Health and Human Services Pass-Through Number(s): N/A Award Number and Period: N/A Type of Finding: Material Weakness in Internal Control over Compliance and Noncompliance Criteria or specific requirement: Per 2 CFR 200 Appendix II (H) Debarment and Suspension (Executive Orders 12549 and 12689)—A contract award (see 2 CFR 180.220) must not be made to parties listed on the governmentwide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. Condition: During our testing, we noted that management’s review of contracts did not include a review to ensure that the party was not debarred, suspended or otherwise excluded. Questioned costs: None. Context: Audit procedures included a review of the five agreements during the year ended June 30, 2023, which represented the entire population. For all of the items reviewed management did not obtain verification that the party was not debarred, suspended or otherwise excluded, prior to entering into the transactions. However, upon subsequent review, no parties were determined the be debarred, suspended or otherwise excluded. Cause: The County’s procurement process did not include a requirement that required a verification of debarred or suspended status. Effect: Amounts could be paid to parties that are debarred, suspended or otherwise excluded. Repeat Finding: No Recommendation: We recommend that management enhance the procurement controls to ensure that all required parties are reviewed for suspension and debarment prior to entering the transaction. Views of responsible officials: The County agrees with the findings. Corrective action plan: While several departments at the County have been checking this internally, we will work on a more formal procedure that will require the departments to show proof of verification that the vendor or subrecipient is not suspended or debarred prior to release of payment.

About Procurement and Suspension and Debarment →

FY 2022-06-30

$5,432,832 federal awards expendedNo findings recorded this year

FAC accepted this audit on January 29, 2024 — management decision was due July 29, 2024.

FY 2021-06-30

$6,515,427 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 29, 2022 — management decision was due March 29, 2023.

FY 2020-06-30

$7,717,240 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 7, 2021 — management decision was due June 7, 2022.

FY 2019-06-30

$5,147,964 federal awards expendedNo findings recorded this year

FAC accepted this audit on July 19, 2021 — management decision was due January 19, 2022.

FY 2018-06-30

$5,048,711 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 8, 2020 — management decision was due April 8, 2021.

FY 2017-06-30

MATERIAL NONCOMPLIANCE DISCLOSED$10,464,953 federal awards expended

FAC accepted this audit on February 24, 2020 — management decision was due August 24, 2020.

2017-003
Other
MATERIAL WEAKNESSREPEAT OF 2016-005OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2016-005

About Other →
2017-004
Activities Allowed or Unallowed / Cost Allowability / Reporting
MATERIAL WEAKNESSREPEAT OF 2016-006

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2016-006

About Activities Allowed or Unallowed, Allowable Costs / Cost Principles, Reporting →
2017-005
Cost Allowability / Reporting
MATERIAL WEAKNESSREPEAT OF 2016-007

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2016-007

About Allowable Costs / Cost Principles, Reporting →
2017-006
Activities Allowed or Unallowed / Special Tests & Provisions
MATERIAL WEAKNESSREPEAT OF 2016-008OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2016-008

About Activities Allowed or Unallowed, Special Tests and Provisions →
2017-007
Procurement & Suspension/Debarment
MATERIAL WEAKNESSOTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Procurement and Suspension and Debarment →

FY 2016-06-30

MATERIAL NONCOMPLIANCE DISCLOSED$8,375,109 federal awards expended

FAC accepted this audit on July 29, 2019 — management decision was due January 29, 2020.

2016-005
Other
MATERIAL WEAKNESSREPEAT OF 2015-005OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-005

About Other →
2016-006
Other
MATERIAL WEAKNESSREPEAT OF 2015-006

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-006

About Other →
2016-007
Reporting
MATERIAL WEAKNESSREPEAT OF 2015-007

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-007

About Reporting →
2016-008
Activities Allowed or Unallowed
MATERIAL WEAKNESSREPEAT OF 2015-009

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-009

About Activities Allowed or Unallowed →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in California

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.