EIN: 910727652
UEI: TWG2J3J9GQN1
Audited by: Clark Nuber P.S.
Oversight agency: 11 [Department of Commerce]
View federal awards & risk assessment →
Data as of September 2, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on January 8, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by July 8, 2025 (421 days ago).
What is a management decision? →FAC accepted this audit on February 12, 2024 — management decision was due August 12, 2024.
Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-002 • Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Criteria • 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation • IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 nonpayroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs • $2,674 Cause • IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect • As a result, charges were made to Federal awards that were not allowable. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. o Allowability 200.403, 200.404, 200.405 o Allowable budget period – 200.403 (h) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: We acknowledge that the deficiencies identified, while minor in dollar value to the grant, represent areas for improvement. The specific issues identified were: 1. Field office rental: A field office rental statement was partially charged to the incorrect fiscal year. Reason: The landlord submitted the invoice for payment after the year-end close (FY2022) and was subsequently fully charged to FY2023, instead of being split across fiscal years. 2. Postage (2 elements): The IPHC loads postage stamps on a stamps.com account to process missing logbook notices to vessel owners, a function that pertains to a grant. Clear delineation of the cost of the stamps allocated to the grant and the stamps allocated to activities that do not qualify under the grant were not enumerated. The employee that requested the stamps in the procurement software did so because the lead team member was not available. When procuring the stamps the face-value of a stamp was used at $0.60 instead of $0.57, a discount the organization receives due to bulk purchase and stamp.com membership. The cost of this error was $9.96. At the start of FY2023, we used a single operating Fund (Fund 30 – Statistics) to record income and expenses for data related activities that included some grant funds. During the course of the year, we commenced the development of the new 5-year grant application with NOAA Fisheries to cover IPHC’s Directed Commercial Catch Sampling of Pacific halibut in Alaska (IPHC Grant 802) (Grant Number: NOAA-NMFS-AK-2023-2007663) from FY2022-FY2026. During this grant renewal/development process, a decision was taken to split Fund 30 – Statistics into two, with Fund 35 AK Cost-Recovery being created. This new Fund 35 was developed to contain only those expenses and income that were deemed as eligible under the grant rules. Over the course of the year, the Secretariat categorized income and expenses between the two Funds, which involved recoding some transactions coded to Fund 30 at the start of the fiscal year, to Fund 35 later in the year. For FY2024, we will continue to undertake monthly reconciliation and month-end close processes to ensure charges are appropriately coded and attributed. In addition, the year-end reconciliation and close processes will support the attestation of funds spent under the grant within one month of the fiscal year ending. This proactive approach aims to ensure timely completion for the single audit, allowing for comprehensive scrutiny of costs assigned to the grant before incorporating financial statements for review during the single audit process. Further, we will ensure preliminary scrutiny and month-end close of financial reports pertaining to grant funds before loading them to the auditors for review. Finally, our procedures have already been improved to ensure that costs charged to the federal awards are charged to the appropriate activity code and are allowable under federal cost principles. Anticipated completion date: Completed - 1 December 2023, and annually by year-end closeout.
Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-002 • Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Criteria • 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation • IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 nonpayroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs • $2,674 Cause • IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect • As a result, charges were made to Federal awards that were not allowable. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. o Allowability 200.403, 200.404, 200.405 o Allowable budget period – 200.403 (h) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: We acknowledge that the deficiencies identified, while minor in dollar value to the grant, represent areas for improvement. The specific issues identified were: 1. Field office rental: A field office rental statement was partially charged to the incorrect fiscal year. Reason: The landlord submitted the invoice for payment after the year-end close (FY2022) and was subsequently fully charged to FY2023, instead of being split across fiscal years. 2. Postage (2 elements): The IPHC loads postage stamps on a stamps.com account to process missing logbook notices to vessel owners, a function that pertains to a grant. Clear delineation of the cost of the stamps allocated to the grant and the stamps allocated to activities that do not qualify under the grant were not enumerated. The employee that requested the stamps in the procurement software did so because the lead team member was not available. When procuring the stamps the face-value of a stamp was used at $0.60 instead of $0.57, a discount the organization receives due to bulk purchase and stamp.com membership. The cost of this error was $9.96. At the start of FY2023, we used a single operating Fund (Fund 30 – Statistics) to record income and expenses for data related activities that included some grant funds. During the course of the year, we commenced the development of the new 5-year grant application with NOAA Fisheries to cover IPHC’s Directed Commercial Catch Sampling of Pacific halibut in Alaska (IPHC Grant 802) (Grant Number: NOAA-NMFS-AK-2023-2007663) from FY2022-FY2026. During this grant renewal/development process, a decision was taken to split Fund 30 – Statistics into two, with Fund 35 AK Cost-Recovery being created. This new Fund 35 was developed to contain only those expenses and income that were deemed as eligible under the grant rules. Over the course of the year, the Secretariat categorized income and expenses between the two Funds, which involved recoding some transactions coded to Fund 30 at the start of the fiscal year, to Fund 35 later in the year. For FY2024, we will continue to undertake monthly reconciliation and month-end close processes to ensure charges are appropriately coded and attributed. In addition, the year-end reconciliation and close processes will support the attestation of funds spent under the grant within one month of the fiscal year ending. This proactive approach aims to ensure timely completion for the single audit, allowing for comprehensive scrutiny of costs assigned to the grant before incorporating financial statements for review during the single audit process. Further, we will ensure preliminary scrutiny and month-end close of financial reports pertaining to grant funds before loading them to the auditors for review. Finally, our procedures have already been improved to ensure that costs charged to the federal awards are charged to the appropriate activity code and are allowable under federal cost principles. Anticipated completion date: Completed - 1 December 2023, and annually by year-end closeout.
Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-003 • Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria • 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation • IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200. Questioned Costs • Not applicable. Cause • IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Procurement Standards. Effect or Potential Effect • As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Procurement Standards. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200. - Procurement standards 2 CFR 200 Subpart D or 200.318-200.327 - Requirement for documented policies consistent with standards 200.318(a) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: As this was the IPHC’s first full GAAP Audit, Single Audit of federal grant funds, and also our first year transitioned from a Cash-basis of accounting to an Accrual-basis of accounting, there are a number of policies and procedures that are in the process of being amended. It will take the Secretariat several months to bring our written process guides into alignment with “2 U.S. Code of Federal Regulations (CFR) Part 200”, as well as our Financial Regulations (2021) that will be considered for amendment at the upcoming 100th Session of the IPHC Finance and Administration Committee (FAC100) and subsequent 100th Session of the IPHC Annual Meeting (AM100) in late January 2024. During the 2nd quarter of FY2024 (1 January – 31 March 2024) the IPHC will undertake a thorough review of “2 U.S. Code of Federal Regulations (CFR) PART 200—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS” and update our procurement policies and processes accordingly. Anticipated completion date: Deadline: 1 April 2024.
Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-003 • Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria • 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation • IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200. Questioned Costs • Not applicable. Cause • IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Procurement Standards. Effect or Potential Effect • As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Procurement Standards. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200. - Procurement standards 2 CFR 200 Subpart D or 200.318-200.327 - Requirement for documented policies consistent with standards 200.318(a) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: As this was the IPHC’s first full GAAP Audit, Single Audit of federal grant funds, and also our first year transitioned from a Cash-basis of accounting to an Accrual-basis of accounting, there are a number of policies and procedures that are in the process of being amended. It will take the Secretariat several months to bring our written process guides into alignment with “2 U.S. Code of Federal Regulations (CFR) Part 200”, as well as our Financial Regulations (2021) that will be considered for amendment at the upcoming 100th Session of the IPHC Finance and Administration Committee (FAC100) and subsequent 100th Session of the IPHC Annual Meeting (AM100) in late January 2024. During the 2nd quarter of FY2024 (1 January – 31 March 2024) the IPHC will undertake a thorough review of “2 U.S. Code of Federal Regulations (CFR) PART 200—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS” and update our procurement policies and processes accordingly. Anticipated completion date: Deadline: 1 April 2024.
FAC accepted this audit on March 19, 2024 — management decision was due September 19, 2024.
Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-002 • Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Criteria • 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation • IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 nonpayroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs • $2,674 Cause • IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect • As a result, charges were made to Federal awards that were not allowable. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. o Allowability 200.403, 200.404, 200.405 o Allowable budget period – 200.403 (h) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: We acknowledge that the deficiencies identified, while minor in dollar value to the grant, represent areas for improvement. The specific issues identified were: 1. Field office rental: A field office rental statement was partially charged to the incorrect fiscal year. Reason: The landlord submitted the invoice for payment after the year-end close (FY2022) and was subsequently fully charged to FY2023, instead of being split across fiscal years. 2. Postage (2 elements): The IPHC loads postage stamps on a stamps.com account to process missing logbook notices to vessel owners, a function that pertains to a grant. Clear delineation of the cost of the stamps allocated to the grant and the stamps allocated to activities that do not qualify under the grant were not enumerated. The employee that requested the stamps in the procurement software did so because the lead team member was not available. When procuring the stamps the face-value of a stamp was used at $0.60 instead of $0.57, a discount the organization receives due to bulk purchase and stamp.com membership. The cost of this error was $9.96. At the start of FY2023, we used a single operating Fund (Fund 30 – Statistics) to record income and expenses for data related activities that included some grant funds. During the course of the year, we commenced the development of the new 5-year grant application with NOAA Fisheries to cover IPHC’s Directed Commercial Catch Sampling of Pacific halibut in Alaska (IPHC Grant 802) (Grant Number: NOAA-NMFS-AK-2023-2007663) from FY2022-FY2026. During this grant renewal/development process, a decision was taken to split Fund 30 – Statistics into two, with Fund 35 AK Cost-Recovery being created. This new Fund 35 was developed to contain only those expenses and income that were deemed as eligible under the grant rules. Over the course of the year, the Secretariat categorized income and expenses between the two Funds, which involved recoding some transactions coded to Fund 30 at the start of the fiscal year, to Fund 35 later in the year. For FY2024, we will continue to undertake monthly reconciliation and month-end close processes to ensure charges are appropriately coded and attributed. In addition, the year-end reconciliation and close processes will support the attestation of funds spent under the grant within one month of the fiscal year ending. This proactive approach aims to ensure timely completion for the single audit, allowing for comprehensive scrutiny of costs assigned to the grant before incorporating financial statements for review during the single audit process. Further, we will ensure preliminary scrutiny and month-end close of financial reports pertaining to grant funds before loading them to the auditors for review. Finally, our procedures have already been improved to ensure that costs charged to the federal awards are charged to the appropriate activity code and are allowable under federal cost principles. Anticipated completion date: Completed - 1 December 2023, and annually by year-end closeout.
Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-002 Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. CFR Part 200.403, 404, and 405 of Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 non-payroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs $2,674 Cause IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect As a result, charges were made to Federal awards that were not allowable or allocable to the award. Repeat Finding Not applicable. Recommendation We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200.403, 404, and 405 of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-002 • Significant deficiency in internal controls over compliance related to allowable costs and period of performance. Criteria • 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards require that costs must be necessary and reasonable for the performance of the Federal Award, that costs be determined in accordance with GAAP, and that costs be adequately documented including the allocation of those costs. Condition/Context for Evaluation • IPHC’s internal controls over non-payroll charges to the Federal Award did not include review for allowability, accrual in the proper period, or that adequate documentation existed to support the amounts charged or allocated. Three out of 25 nonpayroll disbursements tested did not include evidence supporting one or more of these controls. Questioned Costs • $2,674 Cause • IPHC’s operation of internal controls were not sufficient to ensure allowable costs were charged in accordance with 2 U.S. CFR 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Effect or Potential Effect • As a result, charges were made to Federal awards that were not allowable. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC ensure internal controls include reviewing costs charged to the Federal Award for conformity with 2 U.S. CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards for allowability, allocability, and reasonableness. o Allowability 200.403, 200.404, 200.405 o Allowable budget period – 200.403 (h) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: We acknowledge that the deficiencies identified, while minor in dollar value to the grant, represent areas for improvement. The specific issues identified were: 1. Field office rental: A field office rental statement was partially charged to the incorrect fiscal year. Reason: The landlord submitted the invoice for payment after the year-end close (FY2022) and was subsequently fully charged to FY2023, instead of being split across fiscal years. 2. Postage (2 elements): The IPHC loads postage stamps on a stamps.com account to process missing logbook notices to vessel owners, a function that pertains to a grant. Clear delineation of the cost of the stamps allocated to the grant and the stamps allocated to activities that do not qualify under the grant were not enumerated. The employee that requested the stamps in the procurement software did so because the lead team member was not available. When procuring the stamps the face-value of a stamp was used at $0.60 instead of $0.57, a discount the organization receives due to bulk purchase and stamp.com membership. The cost of this error was $9.96. At the start of FY2023, we used a single operating Fund (Fund 30 – Statistics) to record income and expenses for data related activities that included some grant funds. During the course of the year, we commenced the development of the new 5-year grant application with NOAA Fisheries to cover IPHC’s Directed Commercial Catch Sampling of Pacific halibut in Alaska (IPHC Grant 802) (Grant Number: NOAA-NMFS-AK-2023-2007663) from FY2022-FY2026. During this grant renewal/development process, a decision was taken to split Fund 30 – Statistics into two, with Fund 35 AK Cost-Recovery being created. This new Fund 35 was developed to contain only those expenses and income that were deemed as eligible under the grant rules. Over the course of the year, the Secretariat categorized income and expenses between the two Funds, which involved recoding some transactions coded to Fund 30 at the start of the fiscal year, to Fund 35 later in the year. For FY2024, we will continue to undertake monthly reconciliation and month-end close processes to ensure charges are appropriately coded and attributed. In addition, the year-end reconciliation and close processes will support the attestation of funds spent under the grant within one month of the fiscal year ending. This proactive approach aims to ensure timely completion for the single audit, allowing for comprehensive scrutiny of costs assigned to the grant before incorporating financial statements for review during the single audit process. Further, we will ensure preliminary scrutiny and month-end close of financial reports pertaining to grant funds before loading them to the auditors for review. Finally, our procedures have already been improved to ensure that costs charged to the federal awards are charged to the appropriate activity code and are allowable under federal cost principles. Anticipated completion date: Completed - 1 December 2023, and annually by year-end closeout.
Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-003 • Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria • 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation • IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200. Questioned Costs • Not applicable. Cause • IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Procurement Standards. Effect or Potential Effect • As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Procurement Standards. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200. - Procurement standards 2 CFR 200 Subpart D or 200.318-200.327 - Requirement for documented policies consistent with standards 200.318(a) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: As this was the IPHC’s first full GAAP Audit, Single Audit of federal grant funds, and also our first year transitioned from a Cash-basis of accounting to an Accrual-basis of accounting, there are a number of policies and procedures that are in the process of being amended. It will take the Secretariat several months to bring our written process guides into alignment with “2 U.S. Code of Federal Regulations (CFR) Part 200”, as well as our Financial Regulations (2021) that will be considered for amendment at the upcoming 100th Session of the IPHC Finance and Administration Committee (FAC100) and subsequent 100th Session of the IPHC Annual Meeting (AM100) in late January 2024. During the 2nd quarter of FY2024 (1 January – 31 March 2024) the IPHC will undertake a thorough review of “2 U.S. Code of Federal Regulations (CFR) PART 200—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS” and update our procurement policies and processes accordingly. Anticipated completion date: Deadline: 1 April 2024.
Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Show full finding ▾Hide full finding ▴Finding 2023-003 Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200.318(a) Questioned Costs Not applicable. Cause IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Subpart D Procurement Standards. Effect or Potential Effect As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Subpart D Procurement Standards. Repeat Finding Not applicable. Recommendation We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200 Subpart D. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying corrective action plan.
Finding Number 2023-003 • Significant deficiency in internal controls over compliance related to procurement. Federal Agency: U.S. Department of Commerce Program Title: Pacific Fisheries Data Program Assistance Listing Number: 11.437 Award Numbers: NOAA-NMFS-AK-2023-2007663 Award Period: October 1, 2022 to September 30, 2027 Criteria • 2 U.S. Code of Federal Regulations (CFR) Part 200 Uniform Administrative Requirements, Procurement Standards require that awardees use documented procurement procedures for the acquisition of property or services required under a Federal award or subaward. Condition/Context for Evaluation • IPHC's internal controls over procurement do not include the controls and procedures required by 2 CFR 200. Questioned Costs • Not applicable. Cause • IPHC has not yet modified its procurement policies with the requirements of the 2 CFR Part 200 Procurement Standards. Effect or Potential Effect • As a result, IPHC cannot be certain that procurements were conducted in accordance with the 2 CFR Part 200 Procurement Standards. Repeat Finding • Not applicable. Recommendation • We recommend that IPHC update its procurement policy to include all procurement requirements of 2 CFR Part 200. - Procurement standards 2 CFR 200 Subpart D or 200.318-200.327 - Requirement for documented policies consistent with standards 200.318(a) Contact Person(s): • Executive Director: David Wilson (david.wilson@iphc.int); • Assistant Director: Andrea Keikkala (andrea.keikkala@iphc.int) Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): Not applicable. Corrective action planned: As this was the IPHC’s first full GAAP Audit, Single Audit of federal grant funds, and also our first year transitioned from a Cash-basis of accounting to an Accrual-basis of accounting, there are a number of policies and procedures that are in the process of being amended. It will take the Secretariat several months to bring our written process guides into alignment with “2 U.S. Code of Federal Regulations (CFR) Part 200”, as well as our Financial Regulations (2021) that will be considered for amendment at the upcoming 100th Session of the IPHC Finance and Administration Committee (FAC100) and subsequent 100th Session of the IPHC Annual Meeting (AM100) in late January 2024. During the 2nd quarter of FY2024 (1 January – 31 March 2024) the IPHC will undertake a thorough review of “2 U.S. Code of Federal Regulations (CFR) PART 200—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS” and update our procurement policies and processes accordingly. Anticipated completion date: Deadline: 1 April 2024.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Washington →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.