PPEP MICROBUSINESS AND HOUSING DEVELOPMENT CORPORATIONNon-Profit

EIN: 860326269

UEI: HKJKQBBF1HB1

Audited by: ADDINGTON & ASSOCIATES, PLLC

Oversight agency: 10 [Department of Agriculture]

View federal awards & risk assessment →

Data as of August 28, 2026

PPEP MICROBUSINESS AND HOUSING DEVELOPMENT CORPORATION10 audit years2 findings
10
Audit Years
2
Total Findings
0
Repeat Findings
$4M
Federal Awards Expended (FY 2025)

FY 2025-06-30

MATERIAL NONCOMPLIANCE DISCLOSEDLOW-RISK AUDITEE$4,039,667 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on June 4, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 4, 2026 (95 days from today).

What is a management decision? →
2025-003
Activities Allowed or Unallowed / Cost Allowability
MATERIAL WEAKNESSMODIFIED OPINION

See the response at Finding 2025-002 for the history of homes purchased under the Department of Labor’s National Farmworkers Jobs Program and administration of the program. The Organization received the results of the July 2025 program monitoring report by the Department of Labor on March 30, 2026. The Organization is currently working to resolve the compliance findings and to provide additional documentation, as requested. Additionally, the Organization is reviewing the monitoring report to determine whether changes to the current grant controls are deemed necessary. In the event that the Department of Labor deems that pre-approval is necessary, adequate pre-obligation workflow procedures will be developed and implemented immediately.

Show full finding ▾
Full finding narrative

See the response at Finding 2025-002 for the history of homes purchased under the Department of Labor’s National Farmworkers Jobs Program and administration of the program. The Organization received the results of the July 2025 program monitoring report by the Department of Labor on March 30, 2026. The Organization is currently working to resolve the compliance findings and to provide additional documentation, as requested. Additionally, the Organization is reviewing the monitoring report to determine whether changes to the current grant controls are deemed necessary. In the event that the Department of Labor deems that pre-approval is necessary, adequate pre-obligation workflow procedures will be developed and implemented immediately.

Corrective Action Plan

See the response at Finding 2025-004 for the history of homes purchased under the Department of Labor’s National Farmworkers Jobs Program and administration of the program. The Organization received the results of the July 2025 program monitoring report by the Department of Labor on March 30, 2026. The Organization is currently working to resolve the compliance findings and to provide additional documentation, as requested. Additionally, the Organization is reviewing the monitoring report to determine whether changes to the current grant controls are deemed necessary. In the event that the Department of Labor deems that pre-approval is necessary, adequate pre-obligation workflow procedures will be developed and implemented immediately.

About Activities Allowed or Unallowed, Allowable Costs / Cost Principles →
2025-004
Activities Allowed or Unallowed / Cost Allowability
MATERIAL WEAKNESSMODIFIED OPINIONQUESTIONED COSTS

PMHDC contends that it has substantially complied with the purpose of the award and has successfully developed permanent and temporary farm labor rental housing to meet the dire needs of migrant and seasonal farmworkers. The Organization is of the belief that the lack of prior written approval was an administrative oversight, not previously enforced by the Department of Labor, and PMHDC, therefore, vigorously defends its position that no costs should be disallowed.

Show full finding ▾
Full finding narrative

PMHDC contends that it has substantially complied with the purpose of the award and has successfully developed permanent and temporary farm labor rental housing to meet the dire needs of migrant and seasonal farmworkers. The Organization is of the belief that the lack of prior written approval was an administrative oversight, not previously enforced by the Department of Labor, and PMHDC, therefore, vigorously defends its position that no costs should be disallowed.

Corrective Action Plan

PMHDC contends that it has substantially complied with the purpose of the award and has successfully developed permanent and temporary farm labor rental housing to meet the dire needs of migrant and seasonal farmworkers. The Organization is of the belief that the lack of prior written approval was an administrative oversight, not previously enforced by the Department of Labor, and PMHDC, therefore, vigorously defends its position that no costs should be disallowed.

About Activities Allowed or Unallowed, Allowable Costs / Cost Principles →

FY 2024-06-30

LOW-RISK AUDITEE$4,097,346 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 31, 2025 — management decision was due October 1, 2025.

FY 2023-06-30

LOW-RISK AUDITEE$4,281,089 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2024 — management decision was due September 30, 2024.

FY 2022-06-30

LOW-RISK AUDITEE$3,924,383 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2023 — management decision was due September 30, 2023.

FY 2021-06-30

LOW-RISK AUDITEE$4,760,738 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 1, 2022 — management decision was due March 1, 2023.

FY 2020-06-30

LOW-RISK AUDITEE$4,445,343 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2021 — management decision was due September 30, 2021.

FY 2019-06-30

LOW-RISK AUDITEE$4,663,897 federal awards expendedNo findings recorded this year

FAC accepted this audit on July 15, 2020 — management decision was due January 15, 2021.

FY 2018-06-30

LOW-RISK AUDITEE$4,585,173 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 28, 2019 — management decision was due September 28, 2019.

FY 2017-06-30

LOW-RISK AUDITEE$4,373,548 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 26, 2018 — management decision was due September 26, 2018.

FY 2016-06-30

LOW-RISK AUDITEE$4,317,658 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2017 — management decision was due September 30, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Arizona

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.