BOYD COUNTY SCHOOLS DISTRICT NO. 512 audit years2 findings
2
Audit Years
2
Total Findings
0
Repeat Findings
$917K
Federal Awards Expended (FY 2024)

FY 2024-08-31

$916,987 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on May 30, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by November 30, 2025 (286 days ago).

What is a management decision? →
Funder? Track this deadline →
2024-005
Other
SIGNIFICANT DEFICIENCY

The District does not have a system of internal control that would provide management with reasonable assurance that the District's schedule of expenditures of federal awards and related disclosures are complete and presented in accordance with the modified cash basis of accounting. As such, management requested us to compile the trial balance from the general ledger and prepare a draft of the schedule of expenditures of federal awards, including the related note disclosures. Cause: Management does not prepare the schedule of expenditures of federal awards in accordance with the modified cash basis of accounting. Potential Effect: The potential exists that a material misstatement of the schedule of expenditures of federal awards could occur and not be prevented or detected by the District's internal control. Recommendation: We recommend that the District review and approve the proposed auditor adjusting entries and the adequacy of schedule of the expenditures of federal awards disclosures prepared by the auditors and apply analytic procedures to the draft financial statements, among other procedures as considered necessary by management.

Show full finding ▾
Full finding narrative

Criteria: As described in our engagement letter, management is responsible for establishing and maintaining internal controls, including monitoring, and for the fair presentation of the schedule of expenditures of federal awards, including the notes to the schedule of expenditures of federal awards, in conformity with the modified cash basis of accounting. Condition: The District does not have a system of internal control that would provide management with reasonable assurance that the District's schedule of expenditures of federal awards and related disclosures are complete and presented in accordance with the modified cash basis of accounting. As such, management requested us to compile the trial balance from the general ledger and prepare a draft of the schedule of expenditures of federal awards, including the related note disclosures. Cause: Management does not prepare the schedule of expenditures of federal awards in accordance with the modified cash basis of accounting. Potential Effect: The potential exists that a material misstatement of the schedule of expenditures of federal awards could occur and not be prevented or detected by the District's internal control. Recommendation: We recommend that the District review and approve the proposed auditor adjusting entries and the adequacy of schedule of the expenditures of federal awards disclosures prepared by the auditors and apply analytic procedures to the draft financial statements, among other procedures as considered necessary by management.

Corrective Action Plan

The District relies on the auditor to propose adjustments necessary to prepare the schedule of expenditures of federal awards including the related note disclosures. The District reviews schedule of expenditures of federal awards and approves all adjustments.

About Other →

FY 2022-08-31

NON-GAAP BASIS$867,866 federal awards expended

FAC accepted this audit on November 9, 2022 — management decision was due May 9, 2023.

2022-004
Other
SIGNIFICANT DEFICIENCY

2022-004 INTERNAL CONTROL OVER SCHEDULE OF EXPENDITURES OF FEDERAL AWARDS PREPARATION AND REVIEW Criteria As described in our engagement letter, management is responsible for establishing and maintaining internal controls, including monitoring, and for the fair presentation of the schedule of expenditures of federal awards, including the notes to the schedule of expenditures of federal awards, in conformity with the modified cash basis of accounting. Condition The District does not have a system of internal control that would provide management with reasonable assurance that the District's schedule of expenditures of federal awards and related disclosures are complete and presented in accordance with the modified cash basis of accounting. As such, management requested us to compile the trial balance from the general ledger and prepare a draft of the schedule of expenditures of federal awards, including the related note disclosures. Cause Management does not prepare the schedule of expenditures of federal awards in accordance with the modified cash basis of accounting. Potential Effect The potential exists that a material misstatement of the schedule of expenditures of federal awards could occur and not be prevented or detected by the District's internal control. Recommendation We recommend that the District review and approve the proposed auditor adjusting entries and the adequacy of schedule of the expenditures of federal awards disclosures prepared by the auditors and apply analytic procedures to the draft financial statements, among other procedures as considered necessary by management. Views of Responsible Officials and Planned Corrective Actions The District relies on the auditor to propose adjustments necessary to prepare the schedule of expenditures of federal awards including the related note disclosures. The District reviews schedule of expenditures of federal awards and approves all adjustments.

Show full finding ▾
Full finding narrative

2022-004 INTERNAL CONTROL OVER SCHEDULE OF EXPENDITURES OF FEDERAL AWARDS PREPARATION AND REVIEW Criteria As described in our engagement letter, management is responsible for establishing and maintaining internal controls, including monitoring, and for the fair presentation of the schedule of expenditures of federal awards, including the notes to the schedule of expenditures of federal awards, in conformity with the modified cash basis of accounting. Condition The District does not have a system of internal control that would provide management with reasonable assurance that the District's schedule of expenditures of federal awards and related disclosures are complete and presented in accordance with the modified cash basis of accounting. As such, management requested us to compile the trial balance from the general ledger and prepare a draft of the schedule of expenditures of federal awards, including the related note disclosures. Cause Management does not prepare the schedule of expenditures of federal awards in accordance with the modified cash basis of accounting. Potential Effect The potential exists that a material misstatement of the schedule of expenditures of federal awards could occur and not be prevented or detected by the District's internal control. Recommendation We recommend that the District review and approve the proposed auditor adjusting entries and the adequacy of schedule of the expenditures of federal awards disclosures prepared by the auditors and apply analytic procedures to the draft financial statements, among other procedures as considered necessary by management. Views of Responsible Officials and Planned Corrective Actions The District relies on the auditor to propose adjustments necessary to prepare the schedule of expenditures of federal awards including the related note disclosures. The District reviews schedule of expenditures of federal awards and approves all adjustments.

Corrective Action Plan

Finding: 2022-004 Name of Contact Person: Michael Sanne, Superintendent Corrective Action: The District relies on the auditor to propose adjustments necessary to prepare the schedule of expenditures of federal awards including the related note disclosures. The District reviews the schedule of expenditures of federal awards and approves all adjustments. Proposed Completion Date: Immediately

About Other →

Browse other Single Audit organizations in Nebraska

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.