CITY OF DILLON, MONTANALocal Government

EIN: 816001255

UEI: JMVMLD51L8D8

Audited by: AMATICS CPA GROUP

Oversight agency: 21 [Department of the Treasury]

View federal awards & risk assessment →

Data as of September 7, 2026

CITY OF DILLON, MONTANA2 audit years3 findings1 repeat
2
Audit Years
3
Total Findings
1
Repeat Findings
$848.7K
Federal Awards Expended (FY 2023)

FY 2023-06-30

$848,734 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 24, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 24, 2025 (351 days ago).

What is a management decision? →
Funder? Track this deadline →
2023-001
Reporting
REPEAT OF 2022-003OTHER MATTERS

As of February 19, 2025, the fiscal year 2023 reporting package and data collection form had not been submitted to the Federal Audit Clearinghouse. Cause: The City’s fiscal year 2023 audit was not completed by nine months after the end of the audit period. Effect: The City is out of compliance with 2 CFR 200.512(a). Recommendation: Procedures should be developed to ensure the single audit reporting package and data collection form are filed by the due date. Response: The City has developed a schedule and timeline to ensure timely filing of the single audit reporting package and data collection form.

Show full finding ▾
Full finding narrative

Criteria: Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.512(a) requires the reporting package and data collection form to be submitted to the Federal Audit Clearinghouse the earlier of 30 calendar days after the reports are received from the auditor or nine months after the end of the audit period. Condition: As of February 19, 2025, the fiscal year 2023 reporting package and data collection form had not been submitted to the Federal Audit Clearinghouse. Cause: The City’s fiscal year 2023 audit was not completed by nine months after the end of the audit period. Effect: The City is out of compliance with 2 CFR 200.512(a). Recommendation: Procedures should be developed to ensure the single audit reporting package and data collection form are filed by the due date. Response: The City has developed a schedule and timeline to ensure timely filing of the single audit reporting package and data collection form.

Corrective Action Plan

Corrective Action Planned: The City of Dillon has engaged a Certified Public Accountant (CPA) to prepare the fiscal year ended June 30, 2024 audit that is expected to be completed in summer 2025. Name(s) of Contact Person(s) Responsible for Corrective Action: City Clerk, Kami Hoerning. City Treasurer, Karen Kipp. City Mayor, John McGinley. Anticipated Completion Date: Summer 2025

Prior Finding References

2022-003

About Reporting →

FY 2022-06-30

$2,145,233 federal awards expended

FAC accepted this audit on July 15, 2024 — management decision was due January 15, 2025.

2022-002
Procurement & Suspension/Debarment
OTHER MATTERS

The City does not have formal documented procurement policies and procedures related to expenditures of federal awards. Cause: The City Council forms a committee to review and approve disbursements of federal funds. This process is the City’s general practice but does not follow written procurement policies and procedures. Effect: The City is out of compliance with general procurement standards under 2 CFR 200.318. Recommendation: The City should adopt formal documented procurement policies and procedures related to expenditures of federal awards. Response: The City Clerk and Mayor, with help from the Treasurer, will develop and implement documented procurement procedures that conform to the procurement standards relating to Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.317 through 200.327.

Show full finding ▾
Full finding narrative

Criteria: Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.318 General Procurement Standards requires entities to have documented procurement procedures that conform to the procurement standards identified in 2 CFR 200.317 through 200.327. Condition: The City does not have formal documented procurement policies and procedures related to expenditures of federal awards. Cause: The City Council forms a committee to review and approve disbursements of federal funds. This process is the City’s general practice but does not follow written procurement policies and procedures. Effect: The City is out of compliance with general procurement standards under 2 CFR 200.318. Recommendation: The City should adopt formal documented procurement policies and procedures related to expenditures of federal awards. Response: The City Clerk and Mayor, with help from the Treasurer, will develop and implement documented procurement procedures that conform to the procurement standards relating to Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.317 through 200.327.

Corrective Action Plan

Corrective Action Planned: The City Clerk and Mayor, with help from the Treasurer, will develop and implement documented procurement procedures that conform to the procurement standards relating to Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.317 through 200.327 Name(s) of Contact Person(s) Responsible for Corrective Action: City Clerk, Kami Hoerning. City Treasurer, Karen Kipp. City Mayor, John McGinley. Anticipated Completion Date: Summer 2024

About Procurement and Suspension and Debarment →
2022-003
Reporting
OTHER MATTERS

As of May 2024, the fiscal year 2022 reporting package and data collection form had not been submitted to the Federal Audit Clearinghouse. Cause: The City’s fiscal year 2022 audit was not completed by nine months after the end of the audit period. Effect: The City is out of compliance with 2 CFR 200.512(a). Recommendation: Procedures should be developed to ensure the single audit reporting package and data collection form are filed by the due date. Response: With the January 1, 2022 simultaneous staffing turnover of Mayor, Clerk, Deputy Clerk, Water Clerk, City Judge, Court Clerk, and City Attorney, the City of Dillon was delayed in closing the fiscal year 2022 books. The City has engaged a Certified Public Accountant (CPA) to prepare the fiscal year 2023 annual financial report and an audit firm to perform the fiscal year 2023 audit, which is expected to be completed in summer 2024.

Show full finding ▾
Full finding narrative

Criteria: Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) 200.512(a) requires the reporting package and data collection form to be submitted to the Federal Audit Clearinghouse the earlier of 30 calendar days after the reports are received from the auditor or nine months after the end of the audit period. Condition: As of May 2024, the fiscal year 2022 reporting package and data collection form had not been submitted to the Federal Audit Clearinghouse. Cause: The City’s fiscal year 2022 audit was not completed by nine months after the end of the audit period. Effect: The City is out of compliance with 2 CFR 200.512(a). Recommendation: Procedures should be developed to ensure the single audit reporting package and data collection form are filed by the due date. Response: With the January 1, 2022 simultaneous staffing turnover of Mayor, Clerk, Deputy Clerk, Water Clerk, City Judge, Court Clerk, and City Attorney, the City of Dillon was delayed in closing the fiscal year 2022 books. The City has engaged a Certified Public Accountant (CPA) to prepare the fiscal year 2023 annual financial report and an audit firm to perform the fiscal year 2023 audit, which is expected to be completed in summer 2024.

Corrective Action Plan

Corrective Action Planned: The City has engaged a Certified Public Accountant (CPA) to prepare the fiscal year 2023 annual financial report and an audit firm to perform the fiscal year 2023 audit, which is expected to be completed in summer 2024. Name(s) of Contact Person(s) Responsible for Corrective Action: City Clerk, Kami Hoerning. City Treasurer, Karen Kipp. City Mayor, John McGinley. Anticipated Completion Date: Summer 2024

About Reporting →

Browse other Single Audit organizations in Montana

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.