EIN: 816000732
UEI: G1NJJ78GNK25
Audited by: Nexus CPA Group, PLLC
Oversight agency: 84 [Department of Education]
View federal awards & risk assessment →
Data as of September 2, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on March 19, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 19, 2026 (16 days from today).
What is a management decision? →FAC accepted this audit on March 31, 2025 — management decision was due October 1, 2025.
FAC accepted this audit on March 21, 2024 — management decision was due September 21, 2024.
FAC accepted this audit on March 30, 2023 — management decision was due September 30, 2023.
The District did not require a contract indicating the requirement of prevailing wage rate and weekly certified payrolls submitted for federal construction project with contractor. Criteria: All laborers and mechanics employed by contractors or subcontractors to work on construction contracts in excess of $2,000 financed by federal assistance funds must be paid wages not less than those established for the locality of the project (prevailing wage rates) by the Department of Labor (DOL) (40 USC 3141--3144, 3146, and 3147. Nonfederal entities shall include in their construction contracts subject to the Wage Rate Requirements (which still may be referenced as the Davis-Bacon Act) a provision that the contractor or subcontractor comply with those requirements and the DOL regulations (29 CFR Part 5, Labor Standards Provisions Applicable to Contacts Governing Federally Financed and Assisted Construction). This includes a requirement for the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls) (29 CFR sections 5.5 and 5.6; the A-102 Common Rule (section 36(i)(5)); OMB Circular A-110 (2 CFR Part 215, Appendix A, Contract Provisions); 2 CFR Part 176, Subpart C; and 2 CFR section 200.326). Context: During th testing of expenditures for the ESSER II project we noted construction projects in excess of $2,000. Effect: The District was not in compliance with the prevailing wage rate requirement and the internal control system of the District did not identify the need for the compliance. Cause: Internal control procedures were not in place to ensure a contract was draw up to include the prevailing wage rate clause and to ensure the weekly certified payrolls were submitted to the District. Recommendation: The District should implement internal control procedures for any construction contracts in excess of $2,000 funded with federal monies include a contract with the prevailing wage rate clause and submission of weekly certified payrolls.
Show full finding ▾Hide full finding ▴2022-009 Prevailing Wage Rate Internal Control and Compliance CFDA Title: ESSER II CFDA Number: 84.425D Federal Award Number: 036-0648-92-2021 Federal Agency: Department of Education Pass-through Entity: Montana Office of Public Instruction Condition: The District did not require a contract indicating the requirement of prevailing wage rate and weekly certified payrolls submitted for federal construction project with contractor. Criteria: All laborers and mechanics employed by contractors or subcontractors to work on construction contracts in excess of $2,000 financed by federal assistance funds must be paid wages not less than those established for the locality of the project (prevailing wage rates) by the Department of Labor (DOL) (40 USC 3141--3144, 3146, and 3147. Nonfederal entities shall include in their construction contracts subject to the Wage Rate Requirements (which still may be referenced as the Davis-Bacon Act) a provision that the contractor or subcontractor comply with those requirements and the DOL regulations (29 CFR Part 5, Labor Standards Provisions Applicable to Contacts Governing Federally Financed and Assisted Construction). This includes a requirement for the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls) (29 CFR sections 5.5 and 5.6; the A-102 Common Rule (section 36(i)(5)); OMB Circular A-110 (2 CFR Part 215, Appendix A, Contract Provisions); 2 CFR Part 176, Subpart C; and 2 CFR section 200.326). Context: During th testing of expenditures for the ESSER II project we noted construction projects in excess of $2,000. Effect: The District was not in compliance with the prevailing wage rate requirement and the internal control system of the District did not identify the need for the compliance. Cause: Internal control procedures were not in place to ensure a contract was draw up to include the prevailing wage rate clause and to ensure the weekly certified payrolls were submitted to the District. Recommendation: The District should implement internal control procedures for any construction contracts in excess of $2,000 funded with federal monies include a contract with the prevailing wage rate clause and submission of weekly certified payrolls.
FINDING 2022-009: Prevailing Wage Rate Internal Control and Compliance Response: Going forward all construction using federal funds in excess of $2000 will have a contract stating the prevailing wage rate clause and submission of weekly certified payrolls.
FAC accepted this audit on April 27, 2022 — management decision was due October 27, 2022.
FAC accepted this audit on April 20, 2021 — management decision was due October 20, 2021.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Montana →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.