EIN: 680545808
UEI: ZN8GBZJNM694
Audited by: Forvis Mazars, LLP
Oversight agency: 93 [Department of Health and Human Services]
View federal awards & risk assessment →
Data as of August 28, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on January 16, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by July 16, 2026 (44 days ago).
What is a management decision? →Coronavirus State and Local Fiscal Recovery Funds Assistance Listing No. 21.027 U.S. Department of Treasury Missouri Primary Care Association Criteria or specific requirement – Reporting (2 CFR 200.329) Condition – The Organization’s internal controls over compliance were not able to ensure progress reporting required to be submitted to the pass-through entity was completed timely. Cause – The Organization does not have internal controls over compliance in place to ensure all grant reporting requirements are satisfied timely. Effect or potential effect – The Organization did not submit the required quarterly and annual performance reports in a timely manner. Questioned costs – None Context – The Organization is required to submit quarterly status reports and an annual performance report to the pass-through entity in a timely manner. Identification as a repeat finding, if applicable – Not a repeat finding Recommendation – The Organization should consider implementing a grant reporting calendar for all grants with reporting requirements.
Show full finding ▾Hide full finding ▴Coronavirus State and Local Fiscal Recovery Funds Assistance Listing No. 21.027 U.S. Department of Treasury Missouri Primary Care Association Criteria or specific requirement – Reporting (2 CFR 200.329) Condition – The Organization’s internal controls over compliance were not able to ensure progress reporting required to be submitted to the pass-through entity was completed timely. Cause – The Organization does not have internal controls over compliance in place to ensure all grant reporting requirements are satisfied timely. Effect or potential effect – The Organization did not submit the required quarterly and annual performance reports in a timely manner. Questioned costs – None Context – The Organization is required to submit quarterly status reports and an annual performance report to the pass-through entity in a timely manner. Identification as a repeat finding, if applicable – Not a repeat finding Recommendation – The Organization should consider implementing a grant reporting calendar for all grants with reporting requirements.
Coronavirus State and Local Fiscal Recovery Funds Assistance Listing No. 21.027 U.S. Department of Treasury Missouri Primary Care Association Criteria or specific requirement – Reporting (2 CFR 200.329) Condition – The Organization’s internal controls over compliance were not able to ensure progress reporting required to be submitted to the pass-through entity was completed timely. Cause – The Organization’s internal controls over compliance did not ensure all grant reporting requirements were completed timely. Effect or potential effect – The Organization did not submit the required quarterly and annual performance reports in a timely manner. Questioned costs – None Context – The Organization is required to submit quarterly status reports and an annual performance report to the pass-through entity in a timely manner. Identification as a repeat finding, if applicable – Not a repeat finding Recommendation – The Organization should consider implementing a grant reporting calendar for all grants with reporting requirements. Views of responsible officials and planned corrective actions – In order for this finding not to occur in the future, the Chief Financial Officer will • Create a Grant calendar to track report due dates • Hold quarterly meetings with managers to ensure we have all reports submitted timely in the future Contact person responsible for corrective action – Toby Barnett, Chief Financial Officer Anticipated completion date – December 2025
FAC accepted this audit on February 27, 2025 — management decision was due August 27, 2025.
FAC accepted this audit on February 8, 2024 — management decision was due August 8, 2024.
FAC accepted this audit on January 3, 2023 — management decision was due July 3, 2023.
Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution Assistance Listing Number 93.498 U.S. Department of Health and Human Services Criteria or Specific Requirement ? Reporting (45 CFR 75.342) and Activities Allowed/Unallowed and Cost Principles (Pub. L. No. 116-136, 134 Stat. 563 and Pub. L. No. 116-139, 134 Stat. 622 and 623) Condition ? The Organization is required to prepare and submit period-one Provider Relief Fund (PRF) reporting. This report is to be prepared using accurate financial information and submitted by the deadline established. Questioned Costs ? Unknown Context ? The period one PRF report was tested. The Organization selected option one to report lost revenues based on quarterly actuals. The quarterly figures were calculated and reporting using post date versus service date. In addition, settlements related to the Medicaid cost report along with incentive revenue for 2019, 2020, and 2021 were improperly excluded from quarterly revenues related to patient care. Effect ? Errors were made in reporting quarterly Total Revenue from Patient Care. Lost revenues were not accurately reported. Cause ? The Organization calculated and reported patient service revenue by post date versus service date. The Organization also improperly excluded certain patient service revenue components in their calculation. Identification as a Repeat Finding ? Not a repeat finding. Recommendation ? Policies and procedures over federal grant reporting should be modified to ensure reports are prepared using complete and accurate information. Views of Responsible Officials and Planned Corrective Actions ? During the 2022 audit of Community Health Center of Central Missouri, our auditors found two instances of the PRF calculation being calculated incorrectly. The two instances were: 1) Lost revenue was calculated on a quarterly basis using post-date instead of date of service which resulted in a negative patient service revenue balance in self pay during 2020 Quarter 1-Quarter 3 2) Lost revenue was calculated without consideration of Medicaid cost report settlement and incentive revenue. This has resulted in a finding in the current year financial statements audit. Management has evaluated the finding and reviewed whether any funds need to be repaid and evaluated its controls around future provider relief reporting cycles. It has been determined that even with the two errors identified lost revenues would have been sufficient to obligate the entire award. Therefore, we have determined no repayment is necessary. If allowed in future provider relief reporting periods, Community Health Center of Central Missouri will correct the misreporting. Toby Barnett, Chief Financial Officer, is the party that has overall responsibility for this corrective action. The anticipated completion date is unknown at this time due to reporting portal for period 1 being closed. It is unknown if HHS will allow corrections to period 1 reports.
Show full finding ▾Hide full finding ▴Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution Assistance Listing Number 93.498 U.S. Department of Health and Human Services Criteria or Specific Requirement ? Reporting (45 CFR 75.342) and Activities Allowed/Unallowed and Cost Principles (Pub. L. No. 116-136, 134 Stat. 563 and Pub. L. No. 116-139, 134 Stat. 622 and 623) Condition ? The Organization is required to prepare and submit period-one Provider Relief Fund (PRF) reporting. This report is to be prepared using accurate financial information and submitted by the deadline established. Questioned Costs ? Unknown Context ? The period one PRF report was tested. The Organization selected option one to report lost revenues based on quarterly actuals. The quarterly figures were calculated and reporting using post date versus service date. In addition, settlements related to the Medicaid cost report along with incentive revenue for 2019, 2020, and 2021 were improperly excluded from quarterly revenues related to patient care. Effect ? Errors were made in reporting quarterly Total Revenue from Patient Care. Lost revenues were not accurately reported. Cause ? The Organization calculated and reported patient service revenue by post date versus service date. The Organization also improperly excluded certain patient service revenue components in their calculation. Identification as a Repeat Finding ? Not a repeat finding. Recommendation ? Policies and procedures over federal grant reporting should be modified to ensure reports are prepared using complete and accurate information. Views of Responsible Officials and Planned Corrective Actions ? During the 2022 audit of Community Health Center of Central Missouri, our auditors found two instances of the PRF calculation being calculated incorrectly. The two instances were: 1) Lost revenue was calculated on a quarterly basis using post-date instead of date of service which resulted in a negative patient service revenue balance in self pay during 2020 Quarter 1-Quarter 3 2) Lost revenue was calculated without consideration of Medicaid cost report settlement and incentive revenue. This has resulted in a finding in the current year financial statements audit. Management has evaluated the finding and reviewed whether any funds need to be repaid and evaluated its controls around future provider relief reporting cycles. It has been determined that even with the two errors identified lost revenues would have been sufficient to obligate the entire award. Therefore, we have determined no repayment is necessary. If allowed in future provider relief reporting periods, Community Health Center of Central Missouri will correct the misreporting. Toby Barnett, Chief Financial Officer, is the party that has overall responsibility for this corrective action. The anticipated completion date is unknown at this time due to reporting portal for period 1 being closed. It is unknown if HHS will allow corrections to period 1 reports.
During the 2022 audit of Community Health Center of Central Missouri, our auditors found two instances of the PRF calculation being calculated incorrectly. The two instances were: 1) Lost revenue was calculated on a quarterly basis using post-date instead of date of service which resulted in a negative patient service revenue balance in self pay during 2020 Quarter 1-Quarter 3 2) Lost revenue was calculated without consideration of Medicaid cost report settlement and incentive revenue. This has resulted in a finding in the current year financial statements audit. Management has evaluated the finding and reviewed whether any funds need to be repaid and evaluated its controls around future provider relief reporting cycles. It has been determined that even with the two errors identified lost revenues would have been sufficient to obligate the entire award. Therefore, we have determined no repayment is necessary. If allowed in future provider relief reporting periods, Community Health Center of Central Missouri will correct the misreporting. Toby Barnett, Chief Financial Officer, is the party that has overall responsibility for this corrective action. The anticipated completion date is unknown at this time due to reporting portal for period 1 being closed. It is unknown if HHS will allow corrections to period 1 reports.
FAC accepted this audit on January 17, 2022 — management decision was due July 17, 2022.
FAC accepted this audit on March 10, 2021 — management decision was due September 10, 2021.
FAC accepted this audit on November 19, 2019 — management decision was due May 19, 2020.
FAC accepted this audit on December 19, 2018 — management decision was due June 19, 2019.
FAC accepted this audit on November 26, 2017 — management decision was due May 26, 2018.
FAC accepted this audit on January 3, 2017 — management decision was due July 3, 2017.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.