Delta Partners Manor I10 audit years1 findings
10
Audit Years
1
Total Findings
0
Repeat Findings
$1.7M
Federal Awards Expended (FY 2025)

FY 2025-12-31

LOW-RISK AUDITEE$1,699,831 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 31, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 1, 2026 (29 days from today).

What is a management decision? →

FY 2024-12-31

LOW-RISK AUDITEE$1,689,663 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 30, 2025 — management decision was due March 30, 2026.

FY 2023-12-31

$1,666,676 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 4, 2024 — management decision was due October 4, 2024.

FY 2022-12-31

$1,673,705 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2023 — management decision was due September 30, 2023.

FY 2021-12-31

LOW-RISK AUDITEE$1,673,962 federal awards expended

FAC accepted this audit on May 15, 2022 — management decision was due November 15, 2022.

2021-001
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Project did not make twelve deposits in the Replacement Reserve. Cause: The Project did not have the available funds to make the required deposits. Effect or Potential Effect: The missed payments are noncompliance that could, at the discretion of HUD, result in the capital advance being called due, which would require the Project to reimburse HUD for the advance and pay interest. Perspective Information: The Project attempted to make the deposits, but lack of funds prohibited the satisfaction of this requirement. Due to timing of payments, the Project did not have funds to meet all of its operational needs and therefore, cannot make the payments to the Replacement Reserve. Repeat Finding: N/A. Recommendations: The Project should make the required deposit and ensure its cash management policies are sufficient to cover all monthly costs. Perspective: The Project is required to make twelve monthly payments to the Replacement Reserve. Auditors reviewed all transactions, noting that one payment was missing. Questioned Costs: N/A Views of Responsible Officials: Management concurs with the finding. Management will ensure deposits are made. Auditors' Evaluation of the Views of Responsible Officials: Management's response is appropriate to address the noncompliance that occurred and should address how to prevent reoccurrence in the future.

Show full finding ▾
Full finding narrative

Finding 2021-001: Section 202 Capital Advance (CFDA #14.157) Type of Finding: Significant Deficiency Criteria: The Regulatory Agreement requires the Project to make twelve deposits into the Replacement Reserve. Condition: The Project did not make twelve deposits in the Replacement Reserve. Cause: The Project did not have the available funds to make the required deposits. Effect or Potential Effect: The missed payments are noncompliance that could, at the discretion of HUD, result in the capital advance being called due, which would require the Project to reimburse HUD for the advance and pay interest. Perspective Information: The Project attempted to make the deposits, but lack of funds prohibited the satisfaction of this requirement. Due to timing of payments, the Project did not have funds to meet all of its operational needs and therefore, cannot make the payments to the Replacement Reserve. Repeat Finding: N/A. Recommendations: The Project should make the required deposit and ensure its cash management policies are sufficient to cover all monthly costs. Perspective: The Project is required to make twelve monthly payments to the Replacement Reserve. Auditors reviewed all transactions, noting that one payment was missing. Questioned Costs: N/A Views of Responsible Officials: Management concurs with the finding. Management will ensure deposits are made. Auditors' Evaluation of the Views of Responsible Officials: Management's response is appropriate to address the noncompliance that occurred and should address how to prevent reoccurrence in the future.

Corrective Action Plan

CORRECTIVE ACTION PLAN DECEMBER 31, 2021 U.S. Department of Housing and Urban Development Delta Partners Manor I (the "Project") respectfully submits the following corrective action plan for the year ended December 31, 2021. Audit Firm: Harper, Rains, Knight & Company, P.A. 1052 Highland Colony Parkway, Suite 100 Ridgeland, MS 39157 Audit Period: Year Ended December 31, 2021 Finding 2021-001: Section 202 Capital Advance Recommendation: The Project should make the required deposit and ensure its cash management policies are sufficient to cover all monthly costs. Actions Taken: Management concurs with the finding. Management will ensure deposits are made. If the U.S. Department of Housing and Urban Development for audit has questions regarding this plan, please call Scott Russell at 601-856-2362. Sincerely, Delta Partners Manor I By: _________________________________ Alpha Management Corporation

About Special Tests and Provisions →

FY 2020-12-31

LOW-RISK AUDITEE$1,674,818 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 4, 2021 — management decision was due October 4, 2021.

FY 2019-12-31

LOW-RISK AUDITEE$1,675,190 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 27, 2020 — management decision was due October 27, 2020.

FY 2018-12-31

$1,677,466 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 29, 2019 — management decision was due March 29, 2020.

FY 2017-12-31

$1,678,291 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 27, 2018 — management decision was due March 27, 2019.

FY 2016-12-31

$1,672,275 federal awards expendedNo findings recorded this year

FAC accepted this audit on May 2, 2017 — management decision was due November 2, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Mississippi

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.