EIN: 636005391
UEI: GFGHZNQ758E1
Audited by: Carr, Riggs & Ingram, LLC
Oversight agency: 66 [Environmental Protection Agency]
View federal awards & risk assessment →
Data as of September 14, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on April 7, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 7, 2025 (343 days ago).
What is a management decision? →Assistance Listing Number: 66.468 Program Title: Capitalization Grants for Drinking Water Revolving Fund Pass-through Entity: Alabama Department of Environmental Management Contract Number and Year: FS010055.02 2022 Finding Type: Significant Deficiency Known Questioned Costs: None Criteria - 2 CFR Section 200.303(a) requires nonfederal entities receiving federal awards to establish and maintain internal control over the federal awards that provides reasonable assurance that the nonfederal entity is managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards. 2 CFR 200.305 Federal Payment requires nonfederal entities to establish written procedures to implement the requirements of cash management of federal funding. Condition - The Organization received federal funds prior to paying contractors and had no written procedures in place for appropriately handling those funds. Cause - The Organization has not developed or implemented written procedures for appropriately handling advance federal funds. Effect - Possible noncompliance with cash management requirements of the program. Recommendation - The Organization should develop, implement and comply with written procedures to meet the requirements of 2 CFR Section 200.303(a) and 2 CFR 200.305 Federal Payment. View of Responsible Officials - The General Manager has implemented policies and procedures so the Utilities Board of the City of Oneonta will not request advance payments. Payments to contractors will issue within 10 business days of receipt of approval from Project Engineer. In the event contractors can not be paid within 30 days, advanced funds received will be deposited into a designated insured interest bearing account until contractors are paid.
Show full finding ▾Hide full finding ▴Assistance Listing Number: 66.468 Program Title: Capitalization Grants for Drinking Water Revolving Fund Pass-through Entity: Alabama Department of Environmental Management Contract Number and Year: FS010055.02 2022 Finding Type: Significant Deficiency Known Questioned Costs: None Criteria - 2 CFR Section 200.303(a) requires nonfederal entities receiving federal awards to establish and maintain internal control over the federal awards that provides reasonable assurance that the nonfederal entity is managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards. 2 CFR 200.305 Federal Payment requires nonfederal entities to establish written procedures to implement the requirements of cash management of federal funding. Condition - The Organization received federal funds prior to paying contractors and had no written procedures in place for appropriately handling those funds. Cause - The Organization has not developed or implemented written procedures for appropriately handling advance federal funds. Effect - Possible noncompliance with cash management requirements of the program. Recommendation - The Organization should develop, implement and comply with written procedures to meet the requirements of 2 CFR Section 200.303(a) and 2 CFR 200.305 Federal Payment. View of Responsible Officials - The General Manager has implemented policies and procedures so the Utilities Board of the City of Oneonta will not request advance payments. Payments to contractors will issue within 10 business days of receipt of approval from Project Engineer. In the event contractors can not be paid within 30 days, advanced funds received will be deposited into a designated insured interest bearing account until contractors are paid.
The Utilites Board of the City of Oneonta will not request advance receipt of payment. The Organization will be following Procedure CFR section 200.305 (b)(1). Payments will be processed and issued within 10 business days of received date from engineer. If payments cannot be made within 30 days, received funds will be required deposited into a designated insured interest-bearing account until payments have been issued. Anticipated Completion Date: 2/4/2025 Responsible Person: Mark Gargus, General Manager
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Alabama →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.
Checking several at once? Portfolio view →
© 2026 Single Audit Intelligence. All data is public domain.