← Back to home

The Water Works and Gas Board of the City of Red BayLocal Government

EIN: 636001813

UEI: U9XQGWHFXJ63

Audited by: The Sparks CPA Firm, P.C.

Oversight agency: 66 [Environmental Protection Agency]

View federal awards & risk assessment →

Data as of August 31, 2026

The Water Works and Gas Board of the City of Red Bay1 audit years2 findings
1
Audit Years
2
Total Findings
0
Repeat Findings
$1.3M
Federal Awards Expended (FY 2022)

FY 2022-09-30

MATERIAL NONCOMPLIANCE DISCLOSED$1,321,721 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on April 22, 2024. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 22, 2024 (680 days ago).

What is a management decision? →
2022-005
Procurement & Suspension/Debarment
SIGNIFICANT DEFICIENCY

The entity has no written standards of conduct per 2 CFR section 200.318(c). Context: The Water Works and Gas Board of the City of Red Bay does not have a written policy for standards of conduct. Effect: The entity is not in compliance with 2 CFR section 200.318(c). Cause: The entity failed to adopt a written standard of conduct. Repeat Finding: No Recommendation: The entity should adopt written standards of conduct to cover conflicts of interest and govern the performance of its employees engaged in the selection, award, and administration of contracts. Board’s Response: The Water Works and Gas Board of the City of Red Bay will maintain a written standards of conduct and comply with all State laws in relation the Board members and employees in regard to their relationship with vendors and contractors.

Show full finding ▾
Full finding narrative

2022-005 AL# 66.468 – Capitalization Grants for Drinking Water State Revolving Funds Environmental Protection Agency – Passed Through the Alabama State Department of Environmental Management I – Procurement Significant Deficiency Criteria: Per 2 CFR section 200.318(c) entities are required to have written standards of conduct that cover conflicts of interest and govern the performance of its employees engaged in the selection, award, and administration of contracts. Condition: The entity has no written standards of conduct per 2 CFR section 200.318(c). Context: The Water Works and Gas Board of the City of Red Bay does not have a written policy for standards of conduct. Effect: The entity is not in compliance with 2 CFR section 200.318(c). Cause: The entity failed to adopt a written standard of conduct. Repeat Finding: No Recommendation: The entity should adopt written standards of conduct to cover conflicts of interest and govern the performance of its employees engaged in the selection, award, and administration of contracts. Board’s Response: The Water Works and Gas Board of the City of Red Bay will maintain a written standards of conduct and comply with all State laws in relation the Board members and employees in regard to their relationship with vendors and contractors.

Corrective Action Plan

2022-005 a. Name of Contact Person Responsible for Corrective Action: Jeff Burks, General Manager, and Cynthia Fowler, Office Manager & Comptroller Phone Number: (256) 356-8622 b. Corrective Action Planned: The Water Works and Gas Board of the City of Red Bay will maintain a written policy for conduct that covers conflicts of interest and governs the performance of its employees engaged in the selection, award, and administration of contracts. c. Anticipated Completion Date: Immediately

About Procurement and Suspension and Debarment →
2022-006
Cash Management
MATERIAL WEAKNESS

During test work, instances were noted where The Water Works and Gas Board of the City of Red Bay did not pay the cost of the invoices prior to requesting reimbursement. The expenditures were allowable and approved by Alabama State Department of Environmental Management for reimbursement, but the invoices were not paid prior to requesting the reimbursement from Alabama State Department of Environmental Management. Context: The Water Works and Gas Board of the City of Red Bay did not ensure that invoices were paid prior to submitting them for reimbursement to Alabama State Department of Environmental Management. Effect: The entity is not in compliance with 2 CFR section 200.305(b)(3) and Section 2.2(b) of the Special Conditions Loan Agreement. Cause: The Water Works and Gas Board of the City of Red Bay did not ensure that invoices were paid prior to requesting reimbursement. Repeat Finding: No Recommendation: The Water Works and Gas Board of the City of Red Bay should ensure that invoices are paid prior to requesting reimbursement from the pass-through entity. Board’s Response: The Water Works and Gas Board of the City of Red Bay will ensure payments under reimbursable grants are made prior to reimbursement requests.

Show full finding ▾
Full finding narrative

2022-006 AL# 66.468 – Capitalization Grants for Drinking Water State Revolving Funds Environmental Protection Agency – Passed Through the Alabama State Department of Environmental Management C – Cash Management Material Weakness and Noncompliance Criteria: The SRF Loan program is a reimbursable grant administered by ADEM. When non-Federal entities are funded under the reimbursement method, the entity they request reimbursement for expenses paid that are allowable to the grant under (2CFR section 200.305(b)(3)) and Section 2.2(b) of the Special Conditions Loan Agreement. Condition: During test work, instances were noted where The Water Works and Gas Board of the City of Red Bay did not pay the cost of the invoices prior to requesting reimbursement. The expenditures were allowable and approved by Alabama State Department of Environmental Management for reimbursement, but the invoices were not paid prior to requesting the reimbursement from Alabama State Department of Environmental Management. Context: The Water Works and Gas Board of the City of Red Bay did not ensure that invoices were paid prior to submitting them for reimbursement to Alabama State Department of Environmental Management. Effect: The entity is not in compliance with 2 CFR section 200.305(b)(3) and Section 2.2(b) of the Special Conditions Loan Agreement. Cause: The Water Works and Gas Board of the City of Red Bay did not ensure that invoices were paid prior to requesting reimbursement. Repeat Finding: No Recommendation: The Water Works and Gas Board of the City of Red Bay should ensure that invoices are paid prior to requesting reimbursement from the pass-through entity. Board’s Response: The Water Works and Gas Board of the City of Red Bay will ensure payments under reimbursable grants are made prior to reimbursement requests.

Corrective Action Plan

2022-006 a. Name of Contact Person Responsible for Corrective Action: Jeff Burks, General Manager, and Cynthia Fowler, Office Manager & Comptroller Phone Number: (256) 356-8622 b. Corrective Action Planned: The Water Works and Gas Board of the City of Red Bay will ensure payments under reimbursable grants are made prior to reimbursement requests. c. Anticipated Completion Date: Immediately

About Cash Management →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Alabama

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.