EIN: 636001019
UEI: RHGFENNQKXZ6
Audited by: CARR, RIGGS & INGRAM, L.L.C.
Oversight agency: 84 [Department of Education]
View federal awards & risk assessment →
Data as of September 2, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on May 12, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by November 12, 2026 (70 days from today).
What is a management decision? →FAC accepted this audit on May 22, 2025 — management decision was due November 22, 2025.
Item 2024‐001 Special Tests and Provisions – Wage Rate Requirements (Repeat) Education Stabilization Fund (ESF) ALN# 84.425U U.S. Department of Education Passed through the State Department of Education Grant period beginning during fiscal year ended September 30, 2021 (84.425U) Criteria – Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non-Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition – Adequate controls were not in place to ensure that contractors and subcontractors provided timely certified payrolls throughout the construction projects. Cause –There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect – Lack of supporting documentation could lead to disallowed costs. However, our audit disclosed no instances of unallowable costs. Questioned Costs – $27,406. Recommendation – We recommend the strengthening of controls to ensure certified payrolls are received for each week in which construction work is performed. Management’s Response – The Board will strengthen the controls in place to provide assurance that all certified payrolls are received each week in which construction work is performed.
Show full finding ▾Hide full finding ▴Item 2024‐001 Special Tests and Provisions – Wage Rate Requirements (Repeat) Education Stabilization Fund (ESF) ALN# 84.425U U.S. Department of Education Passed through the State Department of Education Grant period beginning during fiscal year ended September 30, 2021 (84.425U) Criteria – Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non-Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition – Adequate controls were not in place to ensure that contractors and subcontractors provided timely certified payrolls throughout the construction projects. Cause –There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect – Lack of supporting documentation could lead to disallowed costs. However, our audit disclosed no instances of unallowable costs. Questioned Costs – $27,406. Recommendation – We recommend the strengthening of controls to ensure certified payrolls are received for each week in which construction work is performed. Management’s Response – The Board will strengthen the controls in place to provide assurance that all certified payrolls are received each week in which construction work is performed.
Item 2024‐001 – Special Tests and Provisions – Wage Rate Requirements (Repeat) Recommendation: 2 CFR 200.303 requires the non-Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non- Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. The Chief School Financial Officer, Linda Harper, should review documentation for inclusion of the prevailing wage rate clauses in construction contracts as part of the bid process prior to expenditures being made. She should also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed. Action Taken: Management has reviewed the requirements of 2 CFR Section 200.303 and 2 CFR 200.326 relating to wage rate requirements and agrees with the recommendation. Management has already communicated with all current contractors and subcontractors regarding the wage rate requirements for contracts in progress and has implemented additional procedures for future projects effective October 1, 2024. These additional procedures include the Chief School Financial Officer (CSFO), Linda Harper, reviewing all proposed construction contracts for inclusion of the prevailing wage rate clause as part of the bid process prior to expenditures being made. The CSFO will also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed.
2023-001
FAC accepted this audit on April 18, 2024 — management decision was due October 18, 2024.
Item 2023‐001 Special Tests and Provisions – Wage Rate Requirements (Repeat) Education Stabilization Fund (ESF) ALN# 84.425 U.S. Department of Education Passed through the State Department of Education Grant period – Years ended September 30, 2021 (84.425U) and September 30, 2020 (84.425D) Criteria – Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non‐Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non‐Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition – Adequate controls were not in place to ensure that contractors and subcontractors were notified of the requirements to comply with the wage rate requirements and to provide timely certified payrolls throughout the construction projects. Cause – A clause describing the Wage Rate Requirements was not added to the construction contracts. There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect – Lack of notification of the wage rate requirements to the contractors and subcontractors could lead to disallowed costs. We noted that certain payments to contractors selected for testing did not have supporting documentation of certified payrolls. However, our audit disclosed no instances of unallowable costs. Questioned Costs – $117,000. Recommendation – We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. Management’s Response – The Board will strengthen the controls in place to provide assurance that proper prevailing wage rate clauses are added to construction contracts and certified payrolls are received each week in which construction work is performed.
Show full finding ▾Hide full finding ▴Item 2023‐001 Special Tests and Provisions – Wage Rate Requirements (Repeat) Education Stabilization Fund (ESF) ALN# 84.425 U.S. Department of Education Passed through the State Department of Education Grant period – Years ended September 30, 2021 (84.425U) and September 30, 2020 (84.425D) Criteria – Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non‐Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non‐Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition – Adequate controls were not in place to ensure that contractors and subcontractors were notified of the requirements to comply with the wage rate requirements and to provide timely certified payrolls throughout the construction projects. Cause – A clause describing the Wage Rate Requirements was not added to the construction contracts. There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect – Lack of notification of the wage rate requirements to the contractors and subcontractors could lead to disallowed costs. We noted that certain payments to contractors selected for testing did not have supporting documentation of certified payrolls. However, our audit disclosed no instances of unallowable costs. Questioned Costs – $117,000. Recommendation – We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. Management’s Response – The Board will strengthen the controls in place to provide assurance that proper prevailing wage rate clauses are added to construction contracts and certified payrolls are received each week in which construction work is performed.
Item 2023‐001 – Special Tests and Provisions – Wage Rate Requirements (Repeat) Recommendation: 2 CFR 200.303 requires the non‐Federal entity to “(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non‐ Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.” 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. The Chief School Financial Officer, Linda Harper, should review documentation for inclusion of the prevailing wage rate clauses in construction contracts as part of the bid process prior to expenditures being made. She should also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed. Action Taken: Management has reviewed the requirements of 2 CFR Section 200.303 and 2 CFR 200.326 relating to wage rate requirements and agrees with the recommendation. Management has already communicated with all current contractors and subcontractors regarding the wage rate requirements for contracts in progress and has implemented additional procedures for future projects effective January 1, 2023. These additional procedures include the Chief School Financial Officer (CSFO), Linda Harper, reviewing all proposed construction contracts for inclusion of the prevailing wage rate clause as part of the bid process prior to expenditures being made. The CSFO will also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed.
2022-001
FAC accepted this audit on April 12, 2023 — management decision was due October 12, 2023.
Item 2022-001 Special Tests and Provisions ? Wage Rate Requirements Education Stabilization Fund (ESF) ALN# 84.425 U.S. Department of Education Passed through the State Department of Education Grant period ? Years ended September 30, 2021 (84.425U) and September 30, 2020 (84.425D) Criteria ? Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non-Federal entity to ?(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.? 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition ? Adequate controls were not in place to ensure that contractors and subcontractors were notified of the requirements to comply with the wage rate requirements and provided timely certified payrolls throughout the construction projects. Cause ? A clause describing the Wage Rate Requirements was not added to the construction contracts. There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect ? Lack of notification of the wage rate requirements to the contractors and subcontractors could lead to disallowed costs. We noted that 5 out of the 9 payments to contractors selected for testing did not have supporting documentation of certified payrolls. However, our audit disclosed no instances of unallowable costs. Questioned Costs ? Not determinable. Recommendation ? We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. Management?s Response ? The Board will strengthen the controls in place to provide assurance that proper prevailing wage rate clauses are added to construction contracts and certified payrolls are received from each week in which construction work is performed.
Show full finding ▾Hide full finding ▴Item 2022-001 Special Tests and Provisions ? Wage Rate Requirements Education Stabilization Fund (ESF) ALN# 84.425 U.S. Department of Education Passed through the State Department of Education Grant period ? Years ended September 30, 2021 (84.425U) and September 30, 2020 (84.425D) Criteria ? Grantees should have controls in place to ensure that contractors and subcontractors are notified of the requirement to pay prevailing wage rates to all laborers and mechanics employed on construction contracts in excess of $2,000 financed by federal assistance funds and to submit weekly certified payrolls for each week in which contract work is performed. 2 CFR 200.303 requires the non-Federal entity to ?(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.? 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). Condition ? Adequate controls were not in place to ensure that contractors and subcontractors were notified of the requirements to comply with the wage rate requirements and provided timely certified payrolls throughout the construction projects. Cause ? A clause describing the Wage Rate Requirements was not added to the construction contracts. There was a lack of sufficient controls over the communication of this requirement to ensure the accuracy and completeness of the certified payrolls being provided to the Board. Effect ? Lack of notification of the wage rate requirements to the contractors and subcontractors could lead to disallowed costs. We noted that 5 out of the 9 payments to contractors selected for testing did not have supporting documentation of certified payrolls. However, our audit disclosed no instances of unallowable costs. Questioned Costs ? Not determinable. Recommendation ? We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. Management?s Response ? The Board will strengthen the controls in place to provide assurance that proper prevailing wage rate clauses are added to construction contracts and certified payrolls are received from each week in which construction work is performed.
Item 2022-001 ? Special Tests and Provisions ? Wage Rate Requirements Recommendation: 2 CFR 200.303 requires the non-Federal entity to ?(a) establish and maintain effective internal controls over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal statutes, regulations, and the terms and conditions of the Federal award.? 2 CFR 200.326 and 29 CFR Part 5, Labor Standards Provisions Applicable to Contracts Governing Federally Financed and Assisted Construction (DOL Regulations) require the contractor or subcontractor to submit to the nonfederal entity weekly, for each week in which any contract work is performed, a copy of the payroll and a statement of compliance (certified payrolls). We recommend the strengthening of controls to ensure the prevailing wage rate clauses are included in the contracts and that certified payrolls are received for each week in which construction work is performed. The Chief School Financial Officer, Linda Harper, should review documentation for inclusion of the prevailing wage rate clauses in construction contracts as part of the bid process prior to expenditures being made. She should also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed. Action Taken: Management has reviewed the requirements of 2 CFR Section 200.303 and 2 CFR 200.326 relating to wage rate requirements and agrees with the recommendation. Management has already communicated with all contractors and subcontractors regarding the wage rate requirements and has implemented additional procedures, effective January 1, 2023, stating that the Chief School Financial Officer, Linda Harper, will review documentation for inclusion of the prevailing wage rate clauses in construction contracts as part of the bid process prior to expenditures being made. She will also review all invoices received from contractors and subcontractors to ensure that the certified payroll information is received for all weeks for which construction work is performed.
FAC accepted this audit on April 21, 2022 — management decision was due October 21, 2022.
FAC accepted this audit on April 7, 2021 — management decision was due October 7, 2021.
FAC accepted this audit on May 5, 2020 — management decision was due November 5, 2020.
FAC accepted this audit on April 30, 2019 — management decision was due October 30, 2019.
GSA_MIGRATION
Show full finding ▾Hide full finding ▴GSA_MIGRATION
GSA_MIGRATION
FAC accepted this audit on April 24, 2018 — management decision was due October 24, 2018.
FAC accepted this audit on June 21, 2017 — management decision was due December 21, 2017.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Alabama →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.