St. Giles Manor, Inc.Non-Profit

EIN: 591900772

UEI: J752DNGBD1H4

Audited by: BROWDER & ASSOCIATES, PC

Oversight agency: 14 [Department of Housing and Urban Development]

View federal awards & risk assessment →

Data as of September 7, 2026

St. Giles Manor, Inc.10 audit years3 findings
10
Audit Years
3
Total Findings
0
Repeat Findings
$5.5M
Federal Awards Expended (FY 2025)

FY 2025-12-31

LOW-RISK AUDITEE$5,544,924 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on February 27, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by August 27, 2026 (12 days ago).

What is a management decision? →
Funder? Track this deadline →

FY 2024-12-31

$5,478,078 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 11, 2025 — management decision was due September 11, 2025.

FY 2023-12-31

LOW-RISK AUDITEE$5,516,407 federal awards expended

FAC accepted this audit on March 27, 2024 — management decision was due September 27, 2024.

2023-001
Other
SIGNIFICANT DEFICIENCYOTHER MATTERS

Management overstated assets and understated expenses by approximately $100,000 for the year ended December 31, 2023. Accounting errors were identified as a part of the audit and management adjusted the financial statements to correct the errors.

Show full finding ▾
Full finding narrative

Management overstated assets and understated expenses by approximately $100,000 for the year ended December 31, 2023. Accounting errors were identified as a part of the audit and management adjusted the financial statements to correct the errors.

Corrective Action Plan

SPM’s Controller of 15 years retired in early 2023. SPM has replaced this position with new leadership, and we are providing additional training to the accounting staff. We do not expect to have this issue going forward.

About Other →
2023-002
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

Management transferred $115,265 from a property held reserve to the operating account without HUD approval. This was a duplicate withdrawal.

Show full finding ▾
Full finding narrative

Management transferred $115,265 from a property held reserve to the operating account without HUD approval. This was a duplicate withdrawal.

Corrective Action Plan

SPM has hired a new Director of Treasury with responsibility for this activity. Additionally, SPM is investigating moving these funds to the lender held reserve account to avoid this issue in the future and eliminate the impact to the financial statement.

About Special Tests and Provisions →
2023-003
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

Management did not submit the required repayment plan to HUD for the RRF loan it received during the year.

Show full finding ▾
Full finding narrative

Management did not submit the required repayment plan to HUD for the RRF loan it received during the year.

Corrective Action Plan

SPM terminated the employment of the person responsible for this oversight and has implemented an internal control for its Financial Planning & Analysis department to monitor the management team’s compliance with these deadlines.

About Special Tests and Provisions →

FY 2022-12-31

LOW-RISK AUDITEE$5,592,493 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 30, 2023 — management decision was due September 30, 2023.

FY 2021-12-31

LOW-RISK AUDITEE$5,613,907 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 14, 2022 — management decision was due September 14, 2022.

FY 2020-12-31

LOW-RISK AUDITEE$5,664,280 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 8, 2021 — management decision was due September 8, 2021.

FY 2019-12-31

LOW-RISK AUDITEE$5,671,070 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 2, 2020 — management decision was due October 2, 2020.

FY 2018-12-31

LOW-RISK AUDITEE$5,711,856 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 14, 2019 — management decision was due September 14, 2019.

FY 2017-12-31

$5,734,930 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 13, 2018 — management decision was due September 13, 2018.

FY 2016-12-31

$5,751,619 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 21, 2017 — management decision was due September 21, 2017.

Browse other Single Audit organizations in Alabama

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.