← Back to home

Pipeline Research Council International, Inc.Non-Profit

EIN: 522202924

UEI: Q27PF937MDK8

Audited by: CBIZ CPAs P.C.

Oversight agency: 20 [Department of Transportation]

View federal awards & risk assessment →

Data as of September 2, 2026

Pipeline Research Council International, Inc.5 audit years3 findings
5
Audit Years
3
Total Findings
0
Repeat Findings
$1.2M
Federal Awards Expended (FY 2024)

FY 2024-12-31

$1,159,923 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on September 26, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 26, 2026 (165 days ago).

What is a management decision? →

FY 2023-12-31

$771,350 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 25, 2024 — management decision was due March 25, 2025.

FY 2022-12-31

LOW-RISK AUDITEE$1,266,838 federal awards expended

FAC accepted this audit on September 28, 2023 — management decision was due March 28, 2024.

2022-002
Other
MATERIAL WEAKNESSOTHER MATTERS

Finding No. 2022-002 Internal Control over Preparation of Schedule of Expenditures of Federal Awards (?SEFA?) ? Material Weakness in Internal Control over Compliance; U.S. Department of Transportation; Research and Development Cluster: PHMSA Pipeline Safety Research and Development; ALN #20.723; Various federal awards (see Schedule of Expenditures of Federal Awards) Criteria Uniform Guidance prescribes the required Schedule of Expenditures of Federal Awards (SEFA) contents and delineates how or what is deemed to be expenditures for purposes of completing the SEFA, including that the accrual basis of accounting be used in the preparation of the SEFA. Condition Over the course of PRCI?s federal awards with cost-share requirements, management recorded inconsistent amounts related to federal expenditures for the year ended December 31, 2022. Context The requirements of PRCI?s federal awards are such that costs are required to be incurred by PRCI in order to meet the deliverables identified in the related fixed price contracts with PHMSA. Initial amounts reported by PRCI on the SEFA corresponded with PRCI?s share of expenditures over its cost share requirement associated with its performance towards meeting the deliverables identified, resulting in a SEFA expense recognition that did not necessarily align with the period the expenses were incurred, as required by the accrual basis of accounting. This resulted in timing differences as to when federal expenditures and cost sharing were being recognized in any given fiscal year in relation to SEFA reporting. However, at the end of the respective contract periods, cost share requirements were met in full, but not always within the period of performance (see finding 2022-003 below). Cause PRCI did not have a systematic process in place to allocate federal expenditures and cost sharing over the contract period and failed to understand the need account for federal expenditures on the accrual basis regardless of when deliverables are met and invoiced under the contract. Effect A difference noted between reported federal expenditures against the cost share requirement could lead to awards being over or under drawn and not in compliance with respective awards. Questioned Costs None. Recommendation To ensure adequate internal controls over the preparation of the SEFA, we recommend that PRCI enhance internal controls over the preparation of the SEFA to ensure that it is prepared by one individual with another individual reviewing the underlying support to ensure completeness and accuracy. Views of Responsible Officials and Planned Corrective Actions See Corrective Action Plan

Show full finding ▾
Full finding narrative

Finding No. 2022-002 Internal Control over Preparation of Schedule of Expenditures of Federal Awards (?SEFA?) ? Material Weakness in Internal Control over Compliance; U.S. Department of Transportation; Research and Development Cluster: PHMSA Pipeline Safety Research and Development; ALN #20.723; Various federal awards (see Schedule of Expenditures of Federal Awards) Criteria Uniform Guidance prescribes the required Schedule of Expenditures of Federal Awards (SEFA) contents and delineates how or what is deemed to be expenditures for purposes of completing the SEFA, including that the accrual basis of accounting be used in the preparation of the SEFA. Condition Over the course of PRCI?s federal awards with cost-share requirements, management recorded inconsistent amounts related to federal expenditures for the year ended December 31, 2022. Context The requirements of PRCI?s federal awards are such that costs are required to be incurred by PRCI in order to meet the deliverables identified in the related fixed price contracts with PHMSA. Initial amounts reported by PRCI on the SEFA corresponded with PRCI?s share of expenditures over its cost share requirement associated with its performance towards meeting the deliverables identified, resulting in a SEFA expense recognition that did not necessarily align with the period the expenses were incurred, as required by the accrual basis of accounting. This resulted in timing differences as to when federal expenditures and cost sharing were being recognized in any given fiscal year in relation to SEFA reporting. However, at the end of the respective contract periods, cost share requirements were met in full, but not always within the period of performance (see finding 2022-003 below). Cause PRCI did not have a systematic process in place to allocate federal expenditures and cost sharing over the contract period and failed to understand the need account for federal expenditures on the accrual basis regardless of when deliverables are met and invoiced under the contract. Effect A difference noted between reported federal expenditures against the cost share requirement could lead to awards being over or under drawn and not in compliance with respective awards. Questioned Costs None. Recommendation To ensure adequate internal controls over the preparation of the SEFA, we recommend that PRCI enhance internal controls over the preparation of the SEFA to ensure that it is prepared by one individual with another individual reviewing the underlying support to ensure completeness and accuracy. Views of Responsible Officials and Planned Corrective Actions See Corrective Action Plan

Corrective Action Plan

2022-002 Internal Control over Preparation of Schedule of Expenditures of Federal Awards (SEFA) United States Department of Transportation (?USDOT?) Auditor?s Recommendation: To ensure adequate internal controls over the preparation of the SEFA, we recommend that PRCI enhance internal controls over the preparation of the SEFA to ensure that it is prepared by one individual with another individual reviewing the underlying support to ensure completeness and accuracy. Explanation of disagreement with audit finding: There is no disagreement with audit finding. Action taken in response to finding: PRCI has implemented a new accounting system in 2023, which tracks the expenses relating the federal awards and expenditures and automatically creates a SEFA. This will allow for a cleaner preparation and review of the SEFA.

About Other →
2022-003
Period of Performance
MATERIAL WEAKNESSQUESTIONED COSTSOTHER MATTERS

Finding No. 2022-003: Period of Performance ? Material Weakness in Internal Control over Compliance; U.S. Department of Transportation; Research and Development Cluster: PHMSA Pipeline Safety Research and Development; ALN #20.723; Various federal awards (see Schedule of Expenditures of Federal Awards) Criteria Uniform Guidance prescribes to be eligible for federal funding, expenditures must be expended in the period of performance identified by the federal awarding agency. Condition For multiple federal awards, PRCI incurred and reported expenditures outside of the period of performance as identified in the original award agreements. We were unable to obtain appropriate evidence related to modifying the related periods of performance to allow for these expenditures to be recorded outside of the identified period of performance. Context PRCI management was not in compliance with the period of performance requirements. There were six federal award contracts during the year ended December 31, 2022 where amounts were incurred after the period of performance for these awards had ended. The amounts incurred outside of the period of performance included $117,328 of federal award expenditures and $58,334 of cost share requirement. Cause According to PRCI management, employee turnover and inadequate procedures resulted in lack of documentation supporting compliance with the period of performance requirements. Additionally, for certain contracts, the structure over the deliverables in the federal awards are such that some deliverables, which triggers the fixed fee draw allowed in the contracts, were originally scheduled outside of the period of performance without the appropriate documentation to extend the related period of performance. Effect Noncompliance with the period of performance requirement could result in the federal awarding agency imposing conditions or taking corrective actions, including additional requirements or withholding/terminating funds. Questioned Costs $117,328 Recommendation PRCI management should develop and implement procedures and modify accounting structures to ensure compliance with period of performance requirements. Views of Responsible Officials and Planned Corrective Actions See Corrective Action Plan

Show full finding ▾
Full finding narrative

Finding No. 2022-003: Period of Performance ? Material Weakness in Internal Control over Compliance; U.S. Department of Transportation; Research and Development Cluster: PHMSA Pipeline Safety Research and Development; ALN #20.723; Various federal awards (see Schedule of Expenditures of Federal Awards) Criteria Uniform Guidance prescribes to be eligible for federal funding, expenditures must be expended in the period of performance identified by the federal awarding agency. Condition For multiple federal awards, PRCI incurred and reported expenditures outside of the period of performance as identified in the original award agreements. We were unable to obtain appropriate evidence related to modifying the related periods of performance to allow for these expenditures to be recorded outside of the identified period of performance. Context PRCI management was not in compliance with the period of performance requirements. There were six federal award contracts during the year ended December 31, 2022 where amounts were incurred after the period of performance for these awards had ended. The amounts incurred outside of the period of performance included $117,328 of federal award expenditures and $58,334 of cost share requirement. Cause According to PRCI management, employee turnover and inadequate procedures resulted in lack of documentation supporting compliance with the period of performance requirements. Additionally, for certain contracts, the structure over the deliverables in the federal awards are such that some deliverables, which triggers the fixed fee draw allowed in the contracts, were originally scheduled outside of the period of performance without the appropriate documentation to extend the related period of performance. Effect Noncompliance with the period of performance requirement could result in the federal awarding agency imposing conditions or taking corrective actions, including additional requirements or withholding/terminating funds. Questioned Costs $117,328 Recommendation PRCI management should develop and implement procedures and modify accounting structures to ensure compliance with period of performance requirements. Views of Responsible Officials and Planned Corrective Actions See Corrective Action Plan

Corrective Action Plan

2022-003 Period of Performance USDOT Auditor?s Recommendation: PRCI management should develop and implement procedures and modify accounting structures to ensure compliance with period of performance requirements. Explanation of disagreement with the audit finding: There is no disagreement with the audit finding. Action taken in response to finding: PRCI has worked with the awarding agency to ensure that all grants are extended to an appropriate period of performance. PRCI additionally has reviewed the contracts with its vendors to ensure that they are billing timely for the contractual obligations of the grant awards. PRCI staff will work with USDOT staff to rectify any current contracted agreements where this same finding may exist in the future but acceptance for any agreement changes would be required by both parties.

About Period of Performance →

FY 2021-12-31

$1,234,160 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 18, 2022 — management decision was due March 18, 2023.

FY 2020-12-31

$1,803,666 federal awards expended

FAC accepted this audit on October 13, 2021 — management decision was due April 13, 2022.

2020-001
Procurement & Suspension/Debarment
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Organization did not document suspension and debarment certification or check the System for Award Management website for vendors contracted with in excess of $25,000 for all contractors tested. Questioned costs: None. Cause: Adequate procedures are not in place to verify if vendors contracted with the Organization related to the federal program in excess of $25,000 are not suspended, debarred, or otherwise excluded from doing business. Effect: Noncompliance with the federal award program's suspension and debarment compliance requirements could occur and not be detected and corrected timely. Repeat Finding: No. Recommendation: Procedures must be implemented to ensure all vendors contracted with the Organization have not been suspended or debarred or otherwise excluded from doing business, prior to procuring their services. In order to verify this, program management should either obtain debarment certifications from the vendors or check the System for Award Management website. Procedures must also be implemented to maintain documentation supporting the debarment and suspension checks performed. Views of Responsible Officials of the Auditee: There is no disagreement with the audit finding.

Show full finding ▾
Full finding narrative

2020-001 Suspension and Debarment Federal agency: Department of Transportation Federal program title: PHMSA Pipeline Safety Research and Development ?Other Transactions? CFDA Number: 20.723 Award Period: September 25, 2018 ? March 31, 2022 ? Significant Deficiency in Internal Control over Compliance ? Other Matters Criteria: Suspension and debarment regulations under 2 CFR should be followed. Condition: The Organization did not document suspension and debarment certification or check the System for Award Management website for vendors contracted with in excess of $25,000 for all contractors tested. Questioned costs: None. Cause: Adequate procedures are not in place to verify if vendors contracted with the Organization related to the federal program in excess of $25,000 are not suspended, debarred, or otherwise excluded from doing business. Effect: Noncompliance with the federal award program's suspension and debarment compliance requirements could occur and not be detected and corrected timely. Repeat Finding: No. Recommendation: Procedures must be implemented to ensure all vendors contracted with the Organization have not been suspended or debarred or otherwise excluded from doing business, prior to procuring their services. In order to verify this, program management should either obtain debarment certifications from the vendors or check the System for Award Management website. Procedures must also be implemented to maintain documentation supporting the debarment and suspension checks performed. Views of Responsible Officials of the Auditee: There is no disagreement with the audit finding.

Corrective Action Plan

United States Department of Transportation The Pipeline Research Council International, Inc. (Organization) respectfully submits the following corrective action plan for the year ended December 31, 2020. The finding from the Schedule of Findings and Questioned Costs is discussed below: FINANCIAL STATEMENT FINDINGS None MAJOR PROGRAM FINDING 2020-001 Suspension and Debarment United States Department of Transportation Recommendation: Procedures must be implemented to ensure all vendors contracted with the Organization have not been suspended or debarred or otherwise excluded from doing business, prior to procuring their services. In order to verify this, program management should either obtain debarment certifications from the vendors or check the System for Award Management website. Procedures must also be implemented to maintain documentation supporting the debarment and suspension checks performed. Explanation of disagreement with audit finding: There is no disagreement with audit finding. Action taken in response to finding: PRCI has added a checklist that is to be attached to request for proposals going forward which will have the prospective contractor provide their DUNS number, if available, and attest to the fact that they are not on the active exclusion listing. Upon selecting a contractor for federal awards, the Project Controls Analyst or Manager of Accounting will perform a search on sam.gov to ensure that the contractor(s) have provided information that is appropriate and complete. The search will be saved in PDF form. Additionally, on contracts which will be performing governmental work, an additional condition will be added to the Terms & Conditions of the new contract stating that the company attests to the fact that they are not on the active exclusions listing. Name of the contact person responsible for corrective action: Bethany Metzgar, Manager of Accounting Planned completion date for corrective action plan: September 30, 2021 If the Department of Transportation has questions regarding this plan, please call Bethany Metzgar at (703) 205-1600 x122 or email at bmetzgar@prci.org.

About Procurement and Suspension and Debarment →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Virginia

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.