← Back to home

Spectrum River Vale Apartments, Inc.Non-Profit

EIN: 521788788

UEI: KFTNKNJU89F3

Audited by: Mercadien. P.C. CPAs

Oversight agency: 14 [Department of Housing and Urban Development]

View federal awards & risk assessment →

Data as of August 28, 2026

Spectrum River Vale Apartments, Inc.10 audit years10 findings3 repeat
10
Audit Years
10
Total Findings
3
Repeat Findings
$1.9M
Federal Awards Expended (FY 2025)

FY 2025-12-31

LOW-RISK AUDITEE$1,927,943 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 24, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 24, 2026 (25 days from today).

What is a management decision? →

FY 2024-12-31

MATERIAL NONCOMPLIANCE DISCLOSEDLOW-RISK AUDITEE$1,937,109 federal awards expended

FAC accepted this audit on March 17, 2025 — management decision was due September 17, 2025.

2024-001
Special Tests & Provisions
OTHER MATTERS

Management made only nine of the twelve required monthly deposits into the replacement reserve account during the year under audit. Cause: The client experienced cash shortages during the year under audit which led to difficulties in having the available cash flow to make the required deposits. Effect: The replacement reserve account had a lower balance than was required as of December 31, 2024. Recommendation: We recommend that management of the Organization closely adhere to the HUD guidance requiring deposits. If monthly deposits cannot be made, the Organization should request an exemption form from HUD allowing them to postpone these deposits for a period of time. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Show full finding ▾
Full finding narrative

Finding: 2024-001 Program: U.S. Department of Housing and Urban Development Supportive Housing for Persons with Disabilities (Section 811) and Capital Advance Criteria or specific requirement: Management is required to make monthly deposits into the replacement reserve account at amounts that are set by HUD. Condition: Management made only nine of the twelve required monthly deposits into the replacement reserve account during the year under audit. Cause: The client experienced cash shortages during the year under audit which led to difficulties in having the available cash flow to make the required deposits. Effect: The replacement reserve account had a lower balance than was required as of December 31, 2024. Recommendation: We recommend that management of the Organization closely adhere to the HUD guidance requiring deposits. If monthly deposits cannot be made, the Organization should request an exemption form from HUD allowing them to postpone these deposits for a period of time. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Corrective Action Plan

The three remaining monthly deposits for 2024 were made in January 2025. Management will perform a review of monthly deposits at mid-year and before year-end to ensure that all twelve deposits are made within the calendar year.

About Special Tests and Provisions →

FY 2023-12-31

LOW-RISK AUDITEE$1,948,059 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 29, 2024 — management decision was due September 29, 2024.

FY 2022-12-31

LOW-RISK AUDITEE$1,951,396 federal awards expended

FAC accepted this audit on March 26, 2023 — management decision was due September 26, 2023.

2022-002
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Organization made a transfer out of the replacement reserve account, totaling $7,940, without receiving proper approval from HUD. Cause: Due to operating cash flow shortages, the Organization made transfers as needed without obtaining proper HUD fund authorization. Effect: The transfer of funds out of the replacement reserve account require prior approval from HUD, therefore, the Organization is in violation of the HUD regulatory agreement. Recommendation: We recommend that the Organization obtain proper approval from HUD for all transfers or disbursements being made out of the replacement reserve account prior to the transfer of any funds. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Show full finding ▾
Full finding narrative

Finding: 2022-002 Program: U.S. Department of Housing and Urban Development Supportive Housing for Persons with Disabilities (Section 811) and Capital Advance Criteria or specific requirement: In accordance with the HUD regulatory agreement, the Organization shall establish a replacement reserve account to aid in funding extraordinary maintenance and repair and replacement of capital items. All disbursements and transfers from the reserve account must be approved by HUD. Condition: The Organization made a transfer out of the replacement reserve account, totaling $7,940, without receiving proper approval from HUD. Cause: Due to operating cash flow shortages, the Organization made transfers as needed without obtaining proper HUD fund authorization. Effect: The transfer of funds out of the replacement reserve account require prior approval from HUD, therefore, the Organization is in violation of the HUD regulatory agreement. Recommendation: We recommend that the Organization obtain proper approval from HUD for all transfers or disbursements being made out of the replacement reserve account prior to the transfer of any funds. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Corrective Action Plan

Finding: 2022-002 Finding Description: The Organization made a transfer out of the replacement reserve account, totaling $7,940, without receiving proper approval from HUD. Corrective Action Taken or Planned: A transfer of $7,940 will be made to the replacement reserve account on or before April 30, 2023.In addition, no transfers will be made out of the replacement reserve account without written HUD approval. Any transfers made out of the replacement reserve account must be approved by the CFO after receiving HUD approval. Contact Person Responsible for Corrective Action: Danny Rosario, CFO Anticipated Completion Date: April 30, 2023

About Special Tests and Provisions →
2022-003
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Organization had excess funds over $250 remaining in the residual receipts account which have not been remitted to HUD upon PRAC termination. Cause: The Organization?s understanding was that payments of excess residual receipts balances were to be made once requested from HUD. Effect: The Organization has not remitted any funds to HUD at the time of the PRAC termination, therefore, it is in violation of the HUD regulatory agreement. Recommendation: We recommend that the organization determine the appropriate excess funds which should be remitted to HUD?s Accounting Center and properly remit those funds on an annual basis upon PRAC termination to remain in compliance. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Show full finding ▾
Full finding narrative

Finding: 2022-003 Program: U.S. Department of Housing and Urban Development Supportive Housing for Persons with Disabilities (Section 811) and Capital Advance Criteria or specific requirement: In accordance with the HUD memorandum for Section 811 Project Rental Assistance Contract (?PRAC?) properties, the Organization shall establish a residual receipts account to house any surplus funds at the end of the fiscal year. Any balance greater than $250 per unit in a residual receipts account must be remitted to HUD?s Accounting Center upon ?termination? of the PRAC. Termination is defined as the expiration of the contract term, which for most PRACs falls on the annual contract anniversary date. Condition: The Organization had excess funds over $250 remaining in the residual receipts account which have not been remitted to HUD upon PRAC termination. Cause: The Organization?s understanding was that payments of excess residual receipts balances were to be made once requested from HUD. Effect: The Organization has not remitted any funds to HUD at the time of the PRAC termination, therefore, it is in violation of the HUD regulatory agreement. Recommendation: We recommend that the organization determine the appropriate excess funds which should be remitted to HUD?s Accounting Center and properly remit those funds on an annual basis upon PRAC termination to remain in compliance. Views of responsible officials and planned corrective actions: Management is in agreement with the finding. See Corrective Action Plan.

Corrective Action Plan

Finding: 2022-003 Finding Description: The Organization had excess funds over $250 remaining in the residual receipts account which have not been remitted to HUD upon PRAC termination. Corrective Action Taken or Planned: Residual receipts that are due to HUD will be made on or before April 30, 2023. Contact Person Responsible for Corrective Action: Danny Rosario, CFO Anticipated Completion Date: April 30, 2023

About Special Tests and Provisions →

FY 2021-12-31

$1,974,671 federal awards expended

FAC accepted this audit on April 13, 2022 — management decision was due October 13, 2022.

2021-002
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Organization had surplus cash in its December 31, 2021, financial statements of $32,966 which was required to be deposited by March 2, 2022, and was not deposited. Cause: There was significant turnover in the accounting department throughout the calendar year, with several key positions left unfilled for several months due to personnel issues. This led to the protracted audit, resulting in delays in completing the surplus cash calculation necessary to determine the amount of payment due to HUD. Effect: The Organization did not deposit the surplus cash within 60 days after the close of the fiscal year, therefore, it is in violation of the HUD regulatory agreement. Recommendation: We recommend a process be put in place to ensure the calculation and any necessary deposits are made timely.

Show full finding ▾
Full finding narrative

Finding: 2021-002 Program: U.S. Department of Housing and Urban Development Supportive Housing for Persons with Disabilities (Section 811) and Capital Advance Criteria or specific requirement: In accordance with the HUD regulatory agreement, the Organization shall establish a residual receipts account and make deposits into the account within 60 days after the close of the fiscal year based on the surplus cash calculation. Condition: The Organization had surplus cash in its December 31, 2021, financial statements of $32,966 which was required to be deposited by March 2, 2022, and was not deposited. Cause: There was significant turnover in the accounting department throughout the calendar year, with several key positions left unfilled for several months due to personnel issues. This led to the protracted audit, resulting in delays in completing the surplus cash calculation necessary to determine the amount of payment due to HUD. Effect: The Organization did not deposit the surplus cash within 60 days after the close of the fiscal year, therefore, it is in violation of the HUD regulatory agreement. Recommendation: We recommend a process be put in place to ensure the calculation and any necessary deposits are made timely.

Corrective Action Plan

Finding: 2021-002 Finding Description: The Organization had surplus cash in its December 31, 2021, financial statements of $32,966 which was required to be deposited by March 2, 2022, and was not deposited. Corrective Action Taken or Planned: The corrective action taken to address Finding 2021-001 will allow for surplus cash to be deposited timely within 60 days of year-end each year in the future. The 2021 surplus cash will be deposited on April 1, 2022. Contact Person Responsible for Corrective Action: William Muilenburg, CFO Anticipated Completion Date: April 2022

About Special Tests and Provisions →

FY 2020-12-31

MATERIAL NONCOMPLIANCE DISCLOSED$1,980,516 federal awards expended

FAC accepted this audit on August 25, 2021 — management decision was due February 25, 2022.

2020-002
Special Tests & Provisions
OTHER MATTERS

The Project had surplus cash in its December 31, 2019 financial statements of $79,694 which was required to be deposited by March 31, 2020 and was not deposited. Cause: The Project has been late in submitting its recertification documents and billings to HUD, which has resulted in cash flow shortages. This situation created the delay in making the required deposit in a timely manner as operating cash flows were not available. Effect or Potential Effect: The Project did not deposit the surplus cash within 90 days after the close of the fiscal year, therefore, it is in violation of the HUD regulatory agreement. However, this violation was rectified thereafter when the deposit was made on July 13, 2021.Recommendation: We recommend the Project continue to regularly monitor and update the calculation, especially as close to year-end as possible, to ensure necessary deposits can be made more timely. Management?s Response: Management will implement internal controls to address making deposits in a timely manner.Questioned Costs: None identified.

Show full finding ▾
Full finding narrative

Criteria: In accordance with the HUD regulatory agreement, the Project shall establish a residual receipts account and make deposits into the account within 90 days after the close of the fiscal year based on the surplus cash calculation. Condition: The Project had surplus cash in its December 31, 2019 financial statements of $79,694 which was required to be deposited by March 31, 2020 and was not deposited. Cause: The Project has been late in submitting its recertification documents and billings to HUD, which has resulted in cash flow shortages. This situation created the delay in making the required deposit in a timely manner as operating cash flows were not available. Effect or Potential Effect: The Project did not deposit the surplus cash within 90 days after the close of the fiscal year, therefore, it is in violation of the HUD regulatory agreement. However, this violation was rectified thereafter when the deposit was made on July 13, 2021.Recommendation: We recommend the Project continue to regularly monitor and update the calculation, especially as close to year-end as possible, to ensure necessary deposits can be made more timely. Management?s Response: Management will implement internal controls to address making deposits in a timely manner.Questioned Costs: None identified.

Corrective Action Plan

Management will implement internal controls to address making deposits in a timely manner. The finding 2020- 001 resulted in shortage of cash flow to make the deposit. Once cash was on hand management made the deposit in July 2021. See CAP

About Special Tests and Provisions →

FY 2019-12-31

MATERIAL NONCOMPLIANCE DISCLOSED$1,967,922 federal awards expended

FAC accepted this audit on September 29, 2020 — management decision was due March 29, 2021.

2019-002
Special Tests & Provisions
MODIFIED OPINIONREPEAT OF 2018-003

As of December 31, 2019 and 2018 the Project?s outstanding balances in due to affiliates were $67,087 and $60,793, respectively. During 2019 HUD disallowed the re-payment of these liabilities as the project did not obtain written authorization from HUD prior to these advances being disbursed. Cause: During 2018 and prior the Project utilized Spectrum for Living Development, Inc., an affiliated entity, as a common paymaster and therefore, the balances included within the due to affiliates accounts represent the expenditures related to the Project paid for by its affiliate on their behalf. The Project did not perform their recertification?s and invoicing to HUD in a timely manner and as a result, Spectrum for Living Development, Inc. paid the necessary and reasonable project expenses on behalf of the Project. This resulted in the increase of its balance due to affiliates. Effect or Potential Effect: The Project is in violation of its HUD regulatory agreement. If HUD does not approve the expenditures paid for on behalf of the Project, the Project could be responsible to pay funds back to the funding source. Questioned Costs: None identified. Recommendation: This condition has been partially resolved. During 2019 to avoid the use of intercompany transactions, the Project utilized its Project bank account to pay for expenditures. Also during 2019 the Project?s representative met with HUD enforcement Officer and explained that those expenses were legitimate of the Project and necessary to carry out the program. HUD enforcement Officer understood the situation and agreed to work with other colleagues within HUD to clarify the situation and allow for the loan to be re-pay. As of December 31, 2019, no formal resolution has been provided by HUD, we recommend that the Project representative continue to follow-up on this until a final decision is reached. Responsible Official?s Response: The Project has been in constant communication with its local representations as well as the DEC (compliance) to resolve this scenario. They have implemented all protocols by HUD and have followed the requirements. They are working with HUD officials to determine how to handle the funds held in the residual receipts account. Planned Implementation Date of Corrective Action: December 31, 2020 Person Responsible for Corrective Action: Chief Financial Officer

Show full finding ▾
Full finding narrative

Finding No. 2019-002 ? Loans from Affiliates Information on the Federal Program: 14.181 Project Rental Assistance Under Section 811 Capital Grant Program, 14.181 Capital Grant (Mortgage) Finding Type: Noncompliance Criteria: In accordance with the HUD regulatory agreements, the Project is required to obtain authorization prior to receiving or paying loans from an affiliate. Condition: As of December 31, 2019 and 2018 the Project?s outstanding balances in due to affiliates were $67,087 and $60,793, respectively. During 2019 HUD disallowed the re-payment of these liabilities as the project did not obtain written authorization from HUD prior to these advances being disbursed. Cause: During 2018 and prior the Project utilized Spectrum for Living Development, Inc., an affiliated entity, as a common paymaster and therefore, the balances included within the due to affiliates accounts represent the expenditures related to the Project paid for by its affiliate on their behalf. The Project did not perform their recertification?s and invoicing to HUD in a timely manner and as a result, Spectrum for Living Development, Inc. paid the necessary and reasonable project expenses on behalf of the Project. This resulted in the increase of its balance due to affiliates. Effect or Potential Effect: The Project is in violation of its HUD regulatory agreement. If HUD does not approve the expenditures paid for on behalf of the Project, the Project could be responsible to pay funds back to the funding source. Questioned Costs: None identified. Recommendation: This condition has been partially resolved. During 2019 to avoid the use of intercompany transactions, the Project utilized its Project bank account to pay for expenditures. Also during 2019 the Project?s representative met with HUD enforcement Officer and explained that those expenses were legitimate of the Project and necessary to carry out the program. HUD enforcement Officer understood the situation and agreed to work with other colleagues within HUD to clarify the situation and allow for the loan to be re-pay. As of December 31, 2019, no formal resolution has been provided by HUD, we recommend that the Project representative continue to follow-up on this until a final decision is reached. Responsible Official?s Response: The Project has been in constant communication with its local representations as well as the DEC (compliance) to resolve this scenario. They have implemented all protocols by HUD and have followed the requirements. They are working with HUD officials to determine how to handle the funds held in the residual receipts account. Planned Implementation Date of Corrective Action: December 31, 2020 Person Responsible for Corrective Action: Chief Financial Officer

Corrective Action Plan

Spectrum hired a CFO in February 2019. Additionally, the Project has been in constant communication with its local representations as well as the DEC (compliance) to resolve this scenario. They have implemented all protocols by HUD and have followed the requirements. They are working with HUD officials to determine how to handle the funds held in the residual receipts account.

Prior Finding References

2018-003

About Special Tests and Provisions →

FY 2018-12-31

MATERIAL NONCOMPLIANCE DISCLOSED$1,985,831 federal awards expended

FAC accepted this audit on August 18, 2019 — management decision was due February 18, 2020.

2018-002
Special Tests & Provisions
REPEAT OF 2017-001OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2017-001

About Special Tests and Provisions →
2018-003
Special Tests & Provisions
MODIFIED OPINIONREPEAT OF 2017-002

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2017-002

About Special Tests and Provisions →

FY 2017-12-31

LOW-RISK AUDITEE$1,993,616 federal awards expended

FAC accepted this audit on August 13, 2018 — management decision was due February 13, 2019.

2017-001
Special Tests & Provisions
OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Special Tests and Provisions →
2017-002
Special Tests & Provisions
MODIFIED OPINION

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Special Tests and Provisions →

FY 2016-12-31

LOW-RISK AUDITEE$1,992,171 federal awards expendedNo findings recorded this year

FAC accepted this audit on May 30, 2017 — management decision was due November 30, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in New Jersey

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.