← Back to home

NEBRASKA ASSOCIATION FOR DEVELOPMENTAL HOUSINGNon-Profit

EIN: 470609108

UEI: N8REGPNB4LE3

Audited by: Core CPAs

Oversight agency: 14 [Department of Housing and Urban Development]

View federal awards & risk assessment →

Data as of August 28, 2026

NEBRASKA ASSOCIATION FOR DEVELOPMENTAL HOUSING9 audit years22 findings18 repeat
9
Audit Years
22
Total Findings
18
Repeat Findings
$1.6M
Federal Awards Expended (FY 2024)

FY 2024-06-30

$1,584,433 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on October 7, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by April 7, 2026 (145 days ago).

What is a management decision? →
2024-003
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2023-003QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-003. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2024-003: Significant Deficiency in Internal Control over Compliance – 2019 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $3,300 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-003. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2024-003 Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation. The Project will repay the nonprofit sponsor’s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2025.

Prior Finding References

2023-003

About Special Tests and Provisions →
2024-004
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2023-004QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $1,500 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-004. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2024-004: Significant Deficiency in Internal Control over Compliance – 2020 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $1,500 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $1,500 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-004. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2024-004 Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation. The Project will repay the nonprofit sponsor’s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2025.

Prior Finding References

2023-004

About Special Tests and Provisions →
2024-005
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2023-005QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2024. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The Project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2024. Recommendation: The Project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Auditee Response/Corrective Action Plan: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-005. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2024-005: Significant Deficiency in Internal Control over Compliance – Replacement Reserve Funding Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $291,545 Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Condition: The replacement reserve is underfunded at June 30, 2024. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The Project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2024. Recommendation: The Project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Auditee Response/Corrective Action Plan: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-005. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2024-005 Due to the financial situation the Project is in at June 30, 2024, making this deposit is impossible. HUD has agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. If management is successful in negotiations with HUD, the anticipated completion date is June 30, 2025.

Prior Finding References

2023-005

About Special Tests and Provisions →
2024-006
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2023-006QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Project. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the replacement reserve for the duplicate release. The Project will repay the replacement reserve when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the replacement reserve when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-006. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2024-006: Significant Deficiency in Internal Control over Compliance – 2021 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $7,486 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Project. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2024. Recommendation: Due to cash flow constraints, the Project was not able to repay the replacement reserve for the duplicate release. The Project will repay the replacement reserve when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the replacement reserve when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2023-006. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2024-006 Due to cash flow constraints, the Project was not able to repay the replacement reserve. The Project will repay the replacement reserve when cash is available. If cash becomes available, the anticipated completion date is June 30, 2025.

Prior Finding References

2023-006

About Special Tests and Provisions →

FY 2023-06-30

UNMODIFIED OPINION, ADVERSE OPINION$1,772,393 federal awards expended

FAC accepted this audit on October 7, 2025 — management decision was due April 7, 2026.

2023-003
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2022-003QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-003. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2023-003: Significant Deficiency in Internal Control over Compliance – 2019 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $3,300 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-003. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2023-003 Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation. The Project will repay the nonprofit sponsor’s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2024.

Prior Finding References

2022-003

About Special Tests and Provisions →
2023-004
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2022-004QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $1,500 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-004. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2023-004: Significant Deficiency in Internal Control over Compliance – 2020 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $1,500 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor’s foundation on the Project’s behalf. Effect or Potential Effect: The replacement reserve is underfunded by $1,500 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation for the submitted invoice paid on the Project’s behalf. The Project will repay the nonprofit sponsor’s foundation when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the nonprofit sponsor’s foundation when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-004. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2023-004 Due to cash flow constraints, the Project was not able to repay the nonprofit sponsor’s foundation. The Project will repay the nonprofit sponsor’s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2024.

Prior Finding References

2022-004

About Special Tests and Provisions →
2023-005
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2022-005QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2023. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The Project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2023. Recommendation: The Project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Auditee Response/Corrective Action Plan: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-005. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2023-005: Significant Deficiency in Internal Control over Compliance – Replacement Reserve Funding Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $291,545 Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Condition: The replacement reserve is underfunded at June 30, 2023. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The Project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2023. Recommendation: The Project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Auditee Response/Corrective Action Plan: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-005. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2023-005 Due to the financial situation the Project is in at June 30, 2023, making this deposit is impossible. HUD has agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. If management is successful in negotiations with HUD, the anticipated completion date is June 30, 2024.

Prior Finding References

2022-005

About Special Tests and Provisions →
2023-006
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2022-006QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Project. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the replacement reserve for the duplicate release. The Project will repay the replacement reserve when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the replacement reserve when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-006. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Show full finding ▾
Full finding narrative

FINDING 2023-006: Significant Deficiency in Internal Control over Compliance – 2021 Replacement Reserve Drawdowns Federal Program: ALN 14.157 – Supportive Services for the Elderly (Section 202) Pass-Through Entity: U.S. Department of Housing and Urban Development Award Number: N/A Compliance Requirement: N – Special Tests and Provisions Type of Finding: Significant Deficiency in Internal Control over Compliance Questioned Costs: $7,486 Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Project. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2023. Recommendation: Due to cash flow constraints, the Project was not able to repay the replacement reserve for the duplicate release. The Project will repay the replacement reserve when cash is available. Auditee Response/Corrective Action Plan: Management agrees with the finding. The Project will repay the replacement reserve when cash is available. Repeat Finding: This is a repeat finding. The prior year finding reference number was 2022-006. Planned Implementation Date: There is not an anticipated completion date. Person Responsible for Corrective Action: Manager

Corrective Action Plan

Finding 2023-006 Due to cash flow constraints, the Project was not able to repay the replacement reserve. The Project will repay the replacement reserve when cash is available. If cash becomes available, the anticipated completion date is June 30, 2024.

Prior Finding References

2022-006

About Special Tests and Provisions →

FY 2022-06-30

GOING CONCERN$1,782,325 federal awards expended

FAC accepted this audit on October 12, 2022 — management decision was due April 12, 2023.

2022-003
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2021-003QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2022. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $3,300 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2021-003. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2022. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2019. The Company should repay the nonprofit sponsor?s foundation $3,300. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2023. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2021-003

About Other →
2022-004
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2021-004QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2022. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $1,500 Repeat Finding: This is a repeat finding. The prior year finding reference numbers was 2021-004. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2022. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2020. The Company should repay the nonprofit sponsor?s foundation $1,500. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2023. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2021-004

About Other →
2022-005
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2021-005QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2022. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2022. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Reporting Views of Responsible Officials: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently.

Show full finding ▾
Full finding narrative

Questioned Costs: $291,545 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2021-005. Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Condition: The replacement reserve is underfunded at June 30, 2022. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2022. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. HUD is requesting the debt service savings from December 1, 2012 until August 31, 2019 be placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to get the past debt service saving deposit requirement suspended permanently. Reporting Views of Responsible Officials: Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - The replacement reserve is underfunded at June 30, 2022. The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to the financial situation the Company is in at June 30, 2022, making this deposit is impossible. HUD has agreed to suspend the monthly required debt service savings deposit effective September 1, 2019. Management is negotiating with HUD to get the past debt service saving deposit requirement suspended permanently. If management is successful in negotiations with HUD, the anticipated completion date is June 30, 2023. Terry Burns is the auditee official responsible for communicating with HUD.

Prior Finding References

2021-005

About Other →
2022-006
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2021-006QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2021. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2022. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Company. Recommendation: Due to cash flow constraints, the Company was not able to repay the replacement reserve for the duplicate release. The Company will repay the replacement reserve when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the replacement reserve when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $7,486 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2021-006. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2021. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2022. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Company. Recommendation: Due to cash flow constraints, the Company was not able to repay the replacement reserve for the duplicate release. The Company will repay the replacement reserve when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the replacement reserve when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2021. The Company should repay the replacement reserve $7,486. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the replacement reserve. The Company will repay the replacement reserve when cash is available. If cash becomes available, the anticipated completion date is June 30, 2023. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2021-006

About Other →

FY 2021-06-30

GOING CONCERN$1,818,862 federal awards expended

FAC accepted this audit on October 12, 2021 — management decision was due April 12, 2022.

2021-003
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2020-003QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2021. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $3,300 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2020-003. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2021. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2019. The Company should repay the nonprofit sponsor?s foundation $3,300. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2022. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2020-003

About Other →
2021-004
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2020-004QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2021. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $1,500 Repeat Finding: This is a repeat finding. The prior year finding reference numbers was 2020-004. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2021. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2020. The Company should repay the nonprofit sponsor?s foundation $1,500. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2022. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2020-004

About Other →
2021-005
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2020-005QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2021. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2021. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend this requirement for one year. HUD is now requesting the debt service savings since 2012 to placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Show full finding ▾
Full finding narrative

Questioned Costs: $291,545 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2020-005. Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Condition: The replacement reserve is underfunded at June 30, 2021. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2021. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend this requirement for one year. HUD is now requesting the debt service savings since 2012 to placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - The replacement reserve is underfunded at June 30, 2021. The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to the financial situation the Company is in at June 30, 2021, making this deposit is impossible. Management is negotiating with HUD to suspend the debt service savings deposit. HUD has suspended the debt service savings from September 1, 2019, through August 31, 2021. Management is negotiating with HUD to suspend the debt service savings deposit permanently. If management is successful in negotiations with HUD, the anticipated completion date is June 30, 2022. Terry Burns is the auditee official responsible for communicating with HUD.

Prior Finding References

2020-005

About Other →
2021-006
Other
SIGNIFICANT DEFICIENCYQUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2021. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2021. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Company. Recommendation: Due to cash flow constraints, the Company was not able to repay the replacement reserve for the duplicate release. The Company will repay the replacement reserve when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the replacement reserve when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $7,486 Repeat Finding: This is not a repeat finding. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2021. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $7,486 at June 30, 2021. Cause: Form HUD-9250 was submitted by management. The mortgage company transferred the amount from the replacement reserve to the insurance escrow. In addition, the mortgage company issued a check to the Company. Recommendation: Due to cash flow constraints, the Company was not able to repay the replacement reserve for the duplicate release. The Company will repay the replacement reserve when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the replacement reserve when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2021. The Company should repay the replacement reserve $7,486. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the replacement reserve. The Company will repay the replacement reserve when cash is available. If cash becomes available, the anticipated completion date is June 30, 2022. Terry Burns is the auditee official responsible for completing this task.

About Other →

FY 2020-06-30

GOING CONCERN$1,852,796 federal awards expended

FAC accepted this audit on October 14, 2020 — management decision was due April 14, 2021.

2020-003
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2019-004QUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $3,300 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2019-004. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2019. The Company should repay the nonprofit sponsor?s foundation $3,300. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2021. Terry Burns is the auditee official responsible for completing this task.

Prior Finding References

2019-004

About Other →
2020-004
Other
SIGNIFICANT DEFICIENCYQUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $1,500 Repeat Finding: This is not a repeat finding. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2020. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $1,500 at June 30, 2020. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - Too much was distributed from the replacement reserve in 2020. The Company should repay the nonprofit sponsor?s foundation $1,500. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation. The Company will repay the nonprofit sponsor?s foundation when cash is available. If cash becomes available, the anticipated completion date is June 30, 2021. Terry Burns is the auditee official responsible for completing this task.

About Other →
2020-005
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2019-005QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2020. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2020. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend this requirement for one year. HUD is now requesting the debt service savings since 2012 to placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Show full finding ▾
Full finding narrative

Questioned Costs: $291,545 Repeat Finding: This is a repeat finding. The prior year finding reference numbers were 2019-005 and 2018-003. Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Condition: The replacement reserve is underfunded at June 30, 2020. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $291,545 at June 30, 2020. Cause: When the mortgage was refinanced in 2011, the regulatory agreement required the debt service savings to be deposited into the reserve for replacements account. HUD agreed to suspend this requirement for one year. HUD is now requesting the debt service savings since 2012 to placed in the reserve for replacement account. The project has been unable to pay the debt service savings portion of the monthly replacement reserve deposits due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Corrective Action Plan

a. Comments on the Finding and Each Recommendation - The replacement reserve is underfunded at June 30, 2020. The project should make a deposit to the replacement reserve account in the amount of $291,545 or negotiate with HUD to suspend the debt service savings deposit. Management agrees with the finding and recommendation. b. Action Planned on the Finding - Due to the financial situation the Company is in at June 30, 2020, making this deposit is impossible. Management is negotiating with HUD to suspend the debt service savings deposit. HUD has suspended the debt service savings from September 1, 2019, through August 31, 2020. Management is negotiating with HUD to suspend the debt service savings deposit permanently. If management is successful in negotiations with HUD, the anticipated completion date is June 30, 2021. Terry Burns is the auditee official responsible for communicating with HUD.

Prior Finding References

2019-005

About Other →

FY 2019-06-30

GOING CONCERN$1,891,966 federal awards expended

FAC accepted this audit on January 14, 2020 — management decision was due July 14, 2020.

2019-004
Other
SIGNIFICANT DEFICIENCYQUESTIONED COSTS

Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Show full finding ▾
Full finding narrative

Questioned Costs: $3,300 Repeat Finding: This is not a repeat finding. Condition: Due to an administrative error, too much was distributed from the replacement reserve in 2019. Criteria: All releases from the replacement reserve should be for qualified expenses and should be approved by HUD. Effect or Potential Effect: The replacement reserve is underfunded by $3,300 at June 30, 2019. Cause: An invoice was submitted by management, but was paid by the nonprofit sponsor?s foundation on the Company?s behalf. Recommendation: Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor?s foundation for the submitted invoice paid on the Company?s behalf. The Company will repay the nonprofit sponsor?s foundation when cash is available. Reporting Views of Responsible Officials: Management agrees with the finding. The company will repay the nonprofit sponsor?s foundation when cash is available.

Corrective Action Plan

Due to cash flow constraints, the Company was not able to repay the nonprofit sponsor's foundation. The Company will repay the nonprofit sponsor's foundation when cash is available.

About Other →
2019-005
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2018-003QUESTIONED COSTS

The replacement reserve is underfunded at June 30, 2019. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $43,542 at June 30, 2019. Cause: HUD issued a change in the monthly deposit effective April 1, 2018, from $4,801 to $4,877. The project is unable to pay the debt service savings portion of this deposit due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $43,542 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Show full finding ▾
Full finding narrative

Questioned Costs: $43,542 Repeat Finding: This is a repeat finding. The prior year finding reference number was 2018-003. Information on Universe Population Size: Monthly replacement reserve deposits. Sample Size Information: 12 monthly payments. Condition: The replacement reserve is underfunded at June 30, 2019. Criteria: According to the regulatory agreement, a monthly deposit must be made into the replacement reserve at an amount mandated by HUD. Effect or Potential Effect: The replacement reserve was underfunded by $43,542 at June 30, 2019. Cause: HUD issued a change in the monthly deposit effective April 1, 2018, from $4,801 to $4,877. The project is unable to pay the debt service savings portion of this deposit due to their financial situation. Recommendation: The project should make a deposit to the replacement reserve account in the amount of $43,542 or negotiate with HUD to suspend the debt service savings deposit. Reporting Views of Responsible Officials: Management is negotiating with HUD to suspend the debt service savings deposit.

Corrective Action Plan

Management is negotiating with HUD to suspend the debt service savings deposit.

Prior Finding References

2018-003

About Other →

FY 2018-06-30

GOING CONCERN$1,924,200 federal awards expended

FAC accepted this audit on October 14, 2018 — management decision was due April 14, 2019.

2018-003
Other
SIGNIFICANT DEFICIENCYQUESTIONED COSTS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Other →

FY 2017-06-30

GOING CONCERN$1,955,780 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 15, 2017 — management decision was due April 15, 2018.

FY 2016-06-30

GOING CONCERN$1,991,367 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 18, 2016 — management decision was due April 18, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Iowa

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.