← Back to home

CENTERPOINTE, INC. AND CONTROLLED ORGANIZATIONNon-Profit

EIN: 470550702

UEI: DXE5DDQ2LE17

Audit also covers EIN: 205966956

Audited by: BRADY MARTZ

Oversight agency: 14 [Department of Housing and Urban Development]

View federal awards & risk assessment →

Data as of September 7, 2026

CENTERPOINTE, INC. AND CONTROLLED ORGANIZATION10 audit years8 findings5 repeat
10
Audit Years
8
Total Findings
5
Repeat Findings
$3.7M
Federal Awards Expended (FY 2025)

FY 2025-06-30

LOW-RISK AUDITEE$3,699,566 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on February 10, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by August 10, 2026 (33 days ago).

What is a management decision? →
Funder? Track this deadline →

FY 2024-06-30

LOW-RISK AUDITEE$4,085,387 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 31, 2025 — management decision was due October 1, 2025.

FY 2023-06-30

LOW-RISK AUDITEE$3,951,032 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 29, 2024 — management decision was due September 29, 2024.

FY 2022-06-30

LOW-RISK AUDITEE$7,129,937 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 22, 2023 — management decision was due September 22, 2023.

FY 2021-06-30

LOW-RISK AUDITEE$4,874,275 federal awards expendedNo findings recorded this year

FAC accepted this audit on February 28, 2022 — management decision was due August 28, 2022.

FY 2020-06-30

LOW-RISK AUDITEE$3,784,057 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 22, 2020 — management decision was due June 22, 2021.

FY 2019-06-30

$4,047,816 federal awards expended

FAC accepted this audit on November 19, 2019 — management decision was due May 19, 2020.

2019-001
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2018-001QUESTIONED COSTSOTHER MATTERS

In accordance with the Residual Receipts Authority ? Section 202/811 Project Rental Assistance Contract (PRAC) Memorandum, the property may only retain a balance of $250 * 10 units = $2,500. At June 30, 2019, the balance of the residual receipts account was $2,541 and therefore $41 needs to be remitted to HUD. Cause: A breakdown in the Organization?s internal controls over special tests and provisions of the program did not allow for the organization to fully comply with the maintenance of required accounts. Effect or potential effect: The Organization did not comply with the deposit requirements of the residual receipts account. Recommendation: The Organization should review its internal control system over special tests and provisions to determine improvements that can be made to ensure compliance with established account requirements of the program.

Show full finding ▾
Full finding narrative

2019-001 Identification data: U.S. Department of Housing and Urban Development (?HUD?), Supportive Housing for Persons with Disabilities (Section 811), CFDA No. 14.181, Award 103-HD035-NP-CMI, Award Period, June 17, 2008 through June 15, 2048 and Award NE-26-Q061-001, Award Period July 15, 2009 through April 30, 2018. Criteria: Title 24 CFR section 891.400(e) requires the Organization to establish and maintain specific accounts, including a project account, replacement reserve, and residual receipts account. Each account requires specific conditions and uses of account funds and are subject to approval by HUD. Condition: In accordance with the Residual Receipts Authority ? Section 202/811 Project Rental Assistance Contract (PRAC) Memorandum, the property may only retain a balance of $250 * 10 units = $2,500. At June 30, 2019, the balance of the residual receipts account was $2,541 and therefore $41 needs to be remitted to HUD. Cause: A breakdown in the Organization?s internal controls over special tests and provisions of the program did not allow for the organization to fully comply with the maintenance of required accounts. Effect or potential effect: The Organization did not comply with the deposit requirements of the residual receipts account. Recommendation: The Organization should review its internal control system over special tests and provisions to determine improvements that can be made to ensure compliance with established account requirements of the program.

Corrective Action Plan

Corrective Action Planned: Management will review requirements related to residual receipts accounts and will establish a procedure to monitor and provide for the timely review of required account activities.

Prior Finding References

2018-001

About Special Tests and Provisions →

FY 2018-06-30

$3,619,845 federal awards expended

FAC accepted this audit on November 29, 2018 — management decision was due May 29, 2019.

2018-001
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2017-004QUESTIONED COSTSOTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2017-004

About Special Tests and Provisions →

FY 2017-06-30

LOW-RISK AUDITEE$2,854,410 federal awards expended

FAC accepted this audit on October 1, 2017 — management decision was due April 1, 2018.

2017-001
Eligibility
SIGNIFICANT DEFICIENCYREPEAT OF 2016-002OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2016-002

About Eligibility →
2017-002
Eligibility
SIGNIFICANT DEFICIENCY

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Eligibility →
2017-003
Eligibility
SIGNIFICANT DEFICIENCYOTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Eligibility →
2017-004
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Special Tests and Provisions →

FY 2016-06-30

$2,751,789 federal awards expended

FAC accepted this audit on September 22, 2016 — management decision was due March 22, 2017.

2016-001
Special Tests & Provisions
SIGNIFICANT DEFICIENCYREPEAT OF 2015-001OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-001

About Special Tests and Provisions →
2016-002
Eligibility
SIGNIFICANT DEFICIENCYREPEAT OF 2015-002OTHER MATTERS

GSA_MIGRATION

Show full finding ▾
Full finding narrative

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

Prior Finding References

2015-002

About Eligibility →

Browse other Single Audit organizations in Nebraska

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.