EIN: 466000177
UEI: RLN9D3YFWWL3
Audited by: EIDE BAILLY LLP
Oversight agency: 21 [Department of the Treasury]
View federal awards & risk assessment →
Data as of August 28, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on August 13, 2024. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by February 13, 2025 (562 days ago).
What is a management decision? →In our testing of procurement, suspension, and debarment, it was noted that the City of Groton’s (the City) procurement policy followed state law which is some cases is less restrictive than federal law. We also noted that the policy does not include the required contract provisions that are needed in contracts with federal grants. Cause: Lack of oversight, awareness, or understanding of all of the specific requirements under the Uniform Guidance and applicable CFR sections, and controls were not adequately designed to ensure compliance with all of these requirements. Effect: A lack of established controls increases the overall risk that employees are not aware of the specific requirements with contracting and awarding contracts when federal grants are involved. Questioned Costs: None reported Context/Sampling: All vendors, which totaled two, were selected for procurement testing. Repeat Finding from Prior Year(s): No Recommendation: We recommend that management review Uniform Guidance and 2 CFR sections 200.318 through 200.326 to ensure that all items identified are included in the procurement policy. Views of Responsible Officials: Management agrees with the finding.
Show full finding ▾Hide full finding ▴2022-003 U.S. Department of Treasury Federal Financial Assistance Listing # 21.027 Award Years: 2021, 2022 Grant Award Number: Unknown COVID–19 Coronavirus State and Local Fiscal Recovery Funds Procurement, Suspension and Debarment Significant Deficiency in Internal Control over Compliance Criteria: Uniform Guidance and 2 CFR sections 200.318 through 200.326 set forth the procurement standards non‐federal entities other than states must follow when operating federal programs and the procurement procedures and contract requirements required depending on the amount of the transaction. Condition: In our testing of procurement, suspension, and debarment, it was noted that the City of Groton’s (the City) procurement policy followed state law which is some cases is less restrictive than federal law. We also noted that the policy does not include the required contract provisions that are needed in contracts with federal grants. Cause: Lack of oversight, awareness, or understanding of all of the specific requirements under the Uniform Guidance and applicable CFR sections, and controls were not adequately designed to ensure compliance with all of these requirements. Effect: A lack of established controls increases the overall risk that employees are not aware of the specific requirements with contracting and awarding contracts when federal grants are involved. Questioned Costs: None reported Context/Sampling: All vendors, which totaled two, were selected for procurement testing. Repeat Finding from Prior Year(s): No Recommendation: We recommend that management review Uniform Guidance and 2 CFR sections 200.318 through 200.326 to ensure that all items identified are included in the procurement policy. Views of Responsible Officials: Management agrees with the finding.
Finding 2022-003 Finding Summary: In testing of procurement, suspension, and debarment, the auditors noted that the City’s procurement policy followed state law which is some cases is less restrictive than federal law. They also noted that the policy does not include the required contract provisions that are needed in contracts with federal grants. Responsible Individuals: Douglas Heinrich, Finance Officer Corrective Action Plan: We will assess if we need to adopt a policy for procurement if we receive federal grants in the future. We will be aware of the contract requirements to ensure they are included in contracts which involve federal money. Anticipated Completion Date: December 31, 2024
In our testing of reporting, there was no documented control in place to review reports prior to submission for reporting directly to Department of Treasury. Cause: Lack of oversight, awareness, or understanding of all the specific requirements under the Uniform Guidance and applicable CFR sections, and controls were not adequately designed to ensure compliance with all of these requirements. Effect: Inaccurate information could have been reported or lines with required information could have been missed. Questioned Costs: None. Context/Sampling: Annual report for 2022. Repeat Finding from Prior Year(s): No Recommendation: We recommend a documented review process be implemented prior to report submission to ensure all lines are properly entered and agree to the applicable backup. Views of Responsible Officials: Management agrees with the finding.
Show full finding ▾Hide full finding ▴2022-004 U.S. Department of Treasury Federal Financial Assistance Listing # 21.027 Award Years: 2021, 2022 Grant Award Number: Unknown COVID-19 Coronavirus State and Local Fiscal Recovery Funds Reporting Significant Deficiency in Internal Control over Compliance Criteria: Annual reports are required by Department of Treasury for all awards received directly from Treasury. Condition: In our testing of reporting, there was no documented control in place to review reports prior to submission for reporting directly to Department of Treasury. Cause: Lack of oversight, awareness, or understanding of all the specific requirements under the Uniform Guidance and applicable CFR sections, and controls were not adequately designed to ensure compliance with all of these requirements. Effect: Inaccurate information could have been reported or lines with required information could have been missed. Questioned Costs: None. Context/Sampling: Annual report for 2022. Repeat Finding from Prior Year(s): No Recommendation: We recommend a documented review process be implemented prior to report submission to ensure all lines are properly entered and agree to the applicable backup. Views of Responsible Officials: Management agrees with the finding.
Finding 2022-004 Finding Summary: In our testing of reporting, we did not have a documented control in place to review reports prior to submission for reporting directly to Department of Treasury. Responsible Individuals: Douglas Heinrich, Finance Officer Corrective Action Plan: We will adopt controls to have a review process added before the required reports for federal programs are submitted to federal or state agencies. Anticipated Completion Date: December 31, 2024
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.