← Back to home

FULTON PUBLIC SCHOOL DISTRICTLocal Government

EIN: 436001370

UEI: PN54N3F4FPV6

Audited by: GERDING, KORTE, & CHITWOOD, CPAS

Oversight agency: 84 [Department of Education]

View federal awards & risk assessment →

Data as of September 7, 2026

FULTON PUBLIC SCHOOL DISTRICT10 audit years2 findings
10
Audit Years
2
Total Findings
0
Repeat Findings
$2.6M
Federal Awards Expended (FY 2025)

FY 2025-06-30

NON-GAAP BASIS$2,611,068 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on December 23, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by June 23, 2026 (83 days ago).

What is a management decision? →
Funder? Track this deadline →
2025-001
Eligibility
OTHER MATTERS

Based on the above regulations, the District was required to verify a sample of 9 applications. However, only 7 applications were verified, but the District reported 9 applications as verified on the verification report submitted to Missouri Department of Elementary and Secondary Education.Cause: The District did not verify the required number of applications because staff misunderstood the federal verification process and associated sampling requirements.Effect: The District was not in compliance with the verification requirements.Questioned Costs: Unknown. To determine the questioned costs, we would need to determine the number of free or reduced meals consumed by students included on the two applications not verified. Because the verification was not performed, we could not determine the questioned costs.Recommendation: We recommend the District provide food service personnel with additional training on the federal verification process and sampling requirements to ensure the correct number of applications are selected and reviewed each year. A supervisory review should be implemented to confirm compliance before the verification report is finalized and submitted to Missouri Department of Elementary and Secondary Education.Fulton Public School District’s Response & Corrective Action Plan: The District will provide food service staff with additional training on the federal verification process and sampling requirements. The District will conduct an internal review, at least twice a year, of a sample of verifications to ensure it is meeting the verification requirements.Official Responsible for Ensuring Corrective Action Plan: Dr. Ty Crain, SuperintendentPlanned Completion Date for the Corrective Action Plan: Fiscal Year 2026

Show full finding ▾
Full finding narrative

2025-001: Verification of Free & Reduced Price Applications (NSLP) – Child Nutrition Cluster (Assistance Listing No. 10.553 and 10.555) Criteria: Section 9(b)(3) of the National School Lunch Act and Federal Regulations at 7 CFR 245.6a(c)1 establish requirements for school districts in conducting verification of eligibility for free and reduced price meals based on applications in participating schools. Condition: Based on the above regulations, the District was required to verify a sample of 9 applications. However, only 7 applications were verified, but the District reported 9 applications as verified on the verification report submitted to Missouri Department of Elementary and Secondary Education.Cause: The District did not verify the required number of applications because staff misunderstood the federal verification process and associated sampling requirements.Effect: The District was not in compliance with the verification requirements.Questioned Costs: Unknown. To determine the questioned costs, we would need to determine the number of free or reduced meals consumed by students included on the two applications not verified. Because the verification was not performed, we could not determine the questioned costs.Recommendation: We recommend the District provide food service personnel with additional training on the federal verification process and sampling requirements to ensure the correct number of applications are selected and reviewed each year. A supervisory review should be implemented to confirm compliance before the verification report is finalized and submitted to Missouri Department of Elementary and Secondary Education.Fulton Public School District’s Response & Corrective Action Plan: The District will provide food service staff with additional training on the federal verification process and sampling requirements. The District will conduct an internal review, at least twice a year, of a sample of verifications to ensure it is meeting the verification requirements.Official Responsible for Ensuring Corrective Action Plan: Dr. Ty Crain, SuperintendentPlanned Completion Date for the Corrective Action Plan: Fiscal Year 2026

Corrective Action Plan

The District will provide food service staff with additional training on the federal verification process and sampling requirements.  The District will conduct an internal review, at least twice a year, of a sample of verifications to ensure it is meeting the verification requirements.

About Eligibility →

FY 2024-06-30

$4,313,072 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 6, 2024 — management decision was due June 6, 2025.

FY 2023-06-30

NON-GAAP BASIS$4,959,322 federal awards expendedNo findings recorded this year

FAC accepted this audit on January 4, 2024 — management decision was due July 4, 2024.

FY 2022-06-30

NON-GAAP BASIS$4,215,459 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 13, 2022 — management decision was due June 13, 2023.

FY 2021-06-30

NON-GAAP BASIS$3,049,469 federal awards expended

FAC accepted this audit on December 21, 2021 — management decision was due June 21, 2022.

2021-001
Reporting / Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

The District did not perform verification procedures until March 11, 2021, which is after the required deadline of February 28, 2021. Cause: The District performed the verification procedures March 22, 2021. Effect: The District was not in compliance with the verification requirements. Questioned Costs: Unknown Recommendation: We recommend the District perform the verification of free & reduced price applications by the deadline, including any extensions.

Show full finding ▾
Full finding narrative

2021-001: Verification of Free & Reduced Price Applications (NSLP) Criteria: The District must verify the current free and reduced price eligibility of households selected from a sample of applications that it has approved for free and reduced price meals by the required deadline. The initial deadline was November 15, 2020, but was extended to February 28, 2021. Condition: The District did not perform verification procedures until March 11, 2021, which is after the required deadline of February 28, 2021. Cause: The District performed the verification procedures March 22, 2021. Effect: The District was not in compliance with the verification requirements. Questioned Costs: Unknown Recommendation: We recommend the District perform the verification of free & reduced price applications by the deadline, including any extensions.

Corrective Action Plan

Fulton Public School District?s Response & Corrective Action Plan: The District will ensure future verifications of free & reduced price applications will be completed by the deadline published by DESE. Official Responsible for Ensuring Corrective Action Plan: Dr. Ty Crain, Superintendent Planned Completion Date for the Corrective Action Plan: Fiscal Year 2022

About Reporting, Special Tests and Provisions →

FY 2020-06-30

NON-GAAP BASIS$2,111,497 federal awards expendedNo findings recorded this year

FAC accepted this audit on January 14, 2021 — management decision was due July 14, 2021.

FY 2019-06-30

NON-GAAP BASIS$2,114,986 federal awards expendedNo findings recorded this year

FAC accepted this audit on January 23, 2020 — management decision was due July 23, 2020.

FY 2018-06-30

NON-GAAP BASIS$1,966,331 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 26, 2018 — management decision was due June 26, 2019.

FY 2017-06-30

NON-GAAP BASIS$2,117,978 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 26, 2017 — management decision was due June 26, 2018.

FY 2016-06-30

NON-GAAP BASIS$2,184,489 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 20, 2016 — management decision was due June 20, 2017.

Browse other Single Audit organizations in Missouri

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.