← Back to home

Belview, City ofLocal Government

EIN: 416004971

UEI: S6LGFNK4SB47

Audited by: Oberloh & Oberloh Ltd

Oversight agency: 10 [Department of Agriculture]

View federal awards & risk assessment →

Data as of September 7, 2026

Belview, City of2 audit years4 findings4 repeat
2
Audit Years
4
Total Findings
4
Repeat Findings
$2.5M
Federal Awards Expended (FY 2025)

FY 2025-12-31

$2,530,089 federal awards expended
2025-001
Reporting
SIGNIFICANT DEFICIENCYREPEAT OF 2024-001

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to prepare the financial statements and maintain a working knowledge of the required disclosures.

Show full finding ▾
Full finding narrative

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to prepare the financial statements and maintain a working knowledge of the required disclosures.

Corrective Action Plan

Proposed Completion Date: The City Council will implement the above procedures immediately.

Prior Finding References

2024-001

About Reporting →
2025-002
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2024-002

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to maintain proper segregation of duties.

Show full finding ▾
Full finding narrative

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to maintain proper segregation of duties.

Corrective Action Plan

Proposed Completion Date: The City Council will implement the above procedures immediately.

Prior Finding References

2024-002

About Other →

FY 2024-12-31

$860,888 federal awards expended

FAC accepted this audit on August 19, 2025 — management decision was due February 19, 2026.

2024-001
Reporting
SIGNIFICANT DEFICIENCYREPEAT OF 2023-001

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to prepare the financial statements and maintain a working knowledge of the required disclosures.

Show full finding ▾
Full finding narrative

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to prepare the financial statements and maintain a working knowledge of the required disclosures.

Corrective Action Plan

Proposed Completion Date: The City Council will implement the above procedures immediately.

Prior Finding References

2023-001

About Reporting →
2024-002
Other
SIGNIFICANT DEFICIENCYREPEAT OF 2023-002

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to maintain proper segregation of duties.

Show full finding ▾
Full finding narrative

Views of Responsible Officials and Planned Corrective Actions: Management agrees with the recommendation that it is not cost effective for the City to maintain proper segregation of duties.

Corrective Action Plan

Proposed Completion Date: The City Council will implement the above procedures immediately.

Prior Finding References

2023-002

About Other →

Browse other Single Audit organizations in Minnesota

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.