← Back to home

MICHIGAN INTERFAITH HOUSING CORPORATION, INC.Non-Profit

EIN: 382292400

UEI: NXW5M4RLM175

Audited by: WIPFLI LLP

Oversight agency: 14 [Department of Housing and Urban Development]

View federal awards & risk assessment →

Data as of August 28, 2026

MICHIGAN INTERFAITH HOUSING CORPORATION, INC.10 audit years2 findings
10
Audit Years
2
Total Findings
0
Repeat Findings
$1.6M
Federal Awards Expended (FY 2025)

FY 2025-12-31

$1,639,032 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on April 22, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 22, 2026 (51 days from today).

What is a management decision? →

FY 2024-12-31

$1,744,629 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 17, 2025 — management decision was due October 17, 2025.

FY 2023-12-31

$1,779,043 federal awards expended

FAC accepted this audit on April 26, 2024 — management decision was due October 26, 2024.

2023-003
Special Tests & Provisions
SIGNIFICANT DEFICIENCYOTHER MATTERS

As of December 31, 2023, the replacement reserve account was underfunded by $714. Beginning in April of 2023, the increase in the monthly required deposit amount was inadvertently not made and the required amount from March 2023 continued to be paid throughout 2023. This caused the annual replacement reserve to be underfunded by $714 at December 31, 2023. Criteria: The Project’s regulatory agreement required monthly deposits of $3,541.49 be made into the replacement reserve account beginning in April 2023. Cause: Management did not update the financial institution on the increased deposit requirement. Effect: The replacement reserve account is underfunded at December 31, 2023, by $714. Recommendation: Management should deposit $714 into the replacement reserve account and ensure the monthly deposits are made in the correct amount. View of Responsible Officials: Management will transfer $714 to the replacement reserve account, will monitor the monthly replacement reserve deposits in the future, and will notify the financial institution of future increases.

Show full finding ▾
Full finding narrative

U.S. Department of Housing and Urban Development Finding 2023-003, CFDA #14.155 Section 223(f) – Insured Mortgage Condition: As of December 31, 2023, the replacement reserve account was underfunded by $714. Beginning in April of 2023, the increase in the monthly required deposit amount was inadvertently not made and the required amount from March 2023 continued to be paid throughout 2023. This caused the annual replacement reserve to be underfunded by $714 at December 31, 2023. Criteria: The Project’s regulatory agreement required monthly deposits of $3,541.49 be made into the replacement reserve account beginning in April 2023. Cause: Management did not update the financial institution on the increased deposit requirement. Effect: The replacement reserve account is underfunded at December 31, 2023, by $714. Recommendation: Management should deposit $714 into the replacement reserve account and ensure the monthly deposits are made in the correct amount. View of Responsible Officials: Management will transfer $714 to the replacement reserve account, will monitor the monthly replacement reserve deposits in the future, and will notify the financial institution of future increases.

Corrective Action Plan

Finding # 2023.003 View of Responsible Officials: Management will transfer $714 to the replacement reserve account, will monitor the monthly replacement reserve deposits in the future, and will notify the financial institution of future increases. Responsible Party: Darrell Lancour Estimated Completion: December 31, 2024

About Special Tests and Provisions →

FY 2022-12-31

$1,818,130 federal awards expended

FAC accepted this audit on April 26, 2023 — management decision was due October 26, 2023.

2022-003
Reporting
SIGNIFICANT DEFICIENCYOTHER MATTERS

The Project did not properly file the audit package and data collection form submission with the Federal Audit Clearinghouse by the required deadline for the year ended December 31, 2021. Criteria: The Federal Audit Clearinghouse requites the Project to submit the audit package and data collection form the earlier of 30 days after receipt of the auditor?s report or 9 months after the end of the fiscal year. Cause: In testing the required report submission, we observed that the annual data collection form and audit report submission were not filed by the required due date. Effect: If the report submission is not filed by the required deadline, the Project is out of compliance with the terms and conditions of its Federal awards. Recommendation: We recommend the Project review its processes and procedures and develop a tracking spreadsheet to aid in monitoring reporting requirements and help ensure the deadlines are properly met. View of Responsible Officials: The Project will review its processes and procedures over reporting submissions required under its Federal awards and will submit the audit report and data collection form for the year ended December 31, 2022, within the required deadline.

Show full finding ▾
Full finding narrative

U.S. Department of Housing and Urban Development Finding 2022.003, CFDA #14.155 Section 223(f) ? Insured Mortgage Condition: The Project did not properly file the audit package and data collection form submission with the Federal Audit Clearinghouse by the required deadline for the year ended December 31, 2021. Criteria: The Federal Audit Clearinghouse requites the Project to submit the audit package and data collection form the earlier of 30 days after receipt of the auditor?s report or 9 months after the end of the fiscal year. Cause: In testing the required report submission, we observed that the annual data collection form and audit report submission were not filed by the required due date. Effect: If the report submission is not filed by the required deadline, the Project is out of compliance with the terms and conditions of its Federal awards. Recommendation: We recommend the Project review its processes and procedures and develop a tracking spreadsheet to aid in monitoring reporting requirements and help ensure the deadlines are properly met. View of Responsible Officials: The Project will review its processes and procedures over reporting submissions required under its Federal awards and will submit the audit report and data collection form for the year ended December 31, 2022, within the required deadline.

Corrective Action Plan

Finding # 2022.003 View of Responsible Officials: The Project will review its processes and procedures over reporting submissions required under its Federal awards and will submit the audit report and data collection form for the year ended December 31, 2022, within the required deadline. Responsible Party: Darrell Lancour Estimated Completion: December 31, 2022

About Reporting →

FY 2021-12-31

LOW-RISK AUDITEE$1,879,874 federal awards expendedNo findings recorded this year

FAC accepted this audit on August 18, 2022 — management decision was due February 18, 2023.

FY 2020-12-31

LOW-RISK AUDITEE$1,934,166 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 26, 2021 — management decision was due October 26, 2021.

FY 2019-12-31

LOW-RISK AUDITEE$1,988,026 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 29, 2020 — management decision was due March 29, 2021.

FY 2018-12-31

LOW-RISK AUDITEE$2,023,897 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 7, 2019 — management decision was due December 7, 2019.

FY 2017-12-31

LOW-RISK AUDITEE$2,064,768 federal awards expendedNo findings recorded this year

FAC accepted this audit on May 24, 2018 — management decision was due November 24, 2018.

FY 2016-12-31

$2,081,268 federal awards expendedNo findings recorded this year

FAC accepted this audit on April 25, 2017 — management decision was due October 25, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Michigan

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.