← Back to home

Champaign Urbana Mass Transit DistrictLocal Government

EIN: 370925614

UEI: S4JJZN2L5UW4

Audited by: Baker Tilly US, LLP

Oversight agency: 20 [Department of Transportation]

View federal awards & risk assessment →

Data as of September 7, 2026

Champaign Urbana Mass Transit District10 audit years2 findings
10
Audit Years
2
Total Findings
0
Repeat Findings
$12.7M
Federal Awards Expended (FY 2025)

FY 2025-06-30

LOW-RISK AUDITEE$12,721,397 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on January 23, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by July 23, 2026 (51 days ago).

What is a management decision? →
Funder? Track this deadline →

FY 2024-06-30

LOW-RISK AUDITEE$18,866,652 federal awards expended

FAC accepted this audit on January 23, 2025 — management decision was due July 23, 2025.

2024-001
Reporting
SIGNIFICANT DEFICIENCY

The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Show full finding ▾
Full finding narrative

Criteria: Nonfederal entities in receipt of federal funds must comply with the requirements of 2 CFR 200.303(a), which require an entity to establish and maintain effective internal control over the federal award to ensure compliance with federal statutes, regulations, and the terms and conditions of the federal award. This includes properly identifying all federal awards subject to the Uniform Guidance and fairly presenting the required information, including the assistance listing number (ALN), in the schedule of expenditures of federal awards (SEFA). Condition: The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Corrective Action Plan

We have reviewed the control procedures around preparation and review of the schedule of expenditures of federal awards (SEFA) and implemented an independent review of the assistance listing numbers (ALN} per the grant agreements in the initial review of the SEFA. The improved procedures will provide the needed structure to fulfill management's responsibility to accurately report the grantor agency/ pass-through grantor, assistance listing number, federal program name and number, and expenditures. Identification of major programs, utilizing the guidelines in the Office of Management and Budget's (0MB) Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance} are the responsibility of the auditor.

About Reporting →
2024-001
Reporting
SIGNIFICANT DEFICIENCY

The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Show full finding ▾
Full finding narrative

Criteria: Nonfederal entities in receipt of federal funds must comply with the requirements of 2 CFR 200.303(a), which require an entity to establish and maintain effective internal control over the federal award to ensure compliance with federal statutes, regulations, and the terms and conditions of the federal award. This includes properly identifying all federal awards subject to the Uniform Guidance and fairly presenting the required information, including the assistance listing number (ALN), in the schedule of expenditures of federal awards (SEFA). Condition: The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Corrective Action Plan

We have reviewed the control procedures around preparation and review of the schedule of expenditures of federal awards (SEFA) and implemented an independent review of the assistance listing numbers (ALN) per the grant agreements in the initial review of the SEFA. The improved procedures will provide the needed structure to fulfill management's responsibility to accurately report the grantor agency / pass-through grantor, assistance listing number, federal program name and number, and expenditures. Identification of major programs, utilizing the guidelines in the Office of Management and Budget's (OMB) Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) are the responsibility of the auditor.

About Reporting →

FY 2024-06-30

LOW-RISK AUDITEE$18,866,652 federal awards expended

FAC accepted this audit on April 30, 2025 — management decision was due October 30, 2025.

2024-001
Reporting
SIGNIFICANT DEFICIENCY

The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Show full finding ▾
Full finding narrative

Criteria: Nonfederal entities in receipt of federal funds must comply with the requirements of 2 CFR 200.303(a), which require an entity to establish and maintain effective internal control over the federal award to ensure compliance with federal statutes, regulations, and the terms and conditions of the federal award. This includes properly identifying all federal awards subject to the Uniform Guidance and fairly presenting the required information, including the assistance listing number (ALN), in the schedule of expenditures of federal awards (SEFA). Condition: The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Corrective Action Plan

We have reviewed the control procedures around preparation and review of the schedule of expenditures of federal awards (SEFA) and implemented an independent review of the assistance listing numbers (ALN} per the grant agreements in the initial review of the SEFA. The improved procedures will provide the needed structure to fulfill management's responsibility to accurately report the grantor agency/ pass-through grantor, assistance listing number, federal program name and number, and expenditures. Identification of major programs, utilizing the guidelines in the Office of Management and Budget's (0MB) Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance} are the responsibility of the auditor.

About Reporting →
2024-001
Reporting
SIGNIFICANT DEFICIENCY

The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Show full finding ▾
Full finding narrative

Criteria: Nonfederal entities in receipt of federal funds must comply with the requirements of 2 CFR 200.303(a), which require an entity to establish and maintain effective internal control over the federal award to ensure compliance with federal statutes, regulations, and the terms and conditions of the federal award. This includes properly identifying all federal awards subject to the Uniform Guidance and fairly presenting the required information, including the assistance listing number (ALN), in the schedule of expenditures of federal awards (SEFA). Condition: The schedule of expenditures of federal awards was reissued after an error was identified by management in the schedule of expenditures of federal awards, specifically in the assistance listing number (ALN) under grant IL-2023-028-00, after the report was originally issued. Cause: The District had a minor lapse in internal controls related to the preparation and review of the schedule of expenditures of federal awards. Management detected the error in the ALN number of grant IL-2023-028-00; however, the audit report had already been issued. Effect: Without adequate internal controls over preparation and review of the schedule of expenditures of federal awards, it is possible that material errors would not be detected in a timely manner and could be reported. Questioned Costs: None noted. Recommendation: We recommend that the District review the control procedures around preparation and review of the schedule of expenditures of federal awards and implement an independent review of the ALN numbers per the grant agreements in the initial review of the SEFA.

Corrective Action Plan

We have reviewed the control procedures around preparation and review of the schedule of expenditures of federal awards (SEFA) and implemented an independent review of the assistance listing numbers (ALN) per the grant agreements in the initial review of the SEFA. The improved procedures will provide the needed structure to fulfill management's responsibility to accurately report the grantor agency / pass-through grantor, assistance listing number, federal program name and number, and expenditures. Identification of major programs, utilizing the guidelines in the Office of Management and Budget's (OMB) Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) are the responsibility of the auditor.

About Reporting →

FY 2023-06-30

LOW-RISK AUDITEE$10,565,432 federal awards expendedNo findings recorded this year

FAC accepted this audit on March 6, 2024 — management decision was due September 6, 2024.

FY 2022-06-30

LOW-RISK AUDITEE$9,439,203 federal awards expendedNo findings recorded this year

FAC accepted this audit on February 23, 2023 — management decision was due August 23, 2023.

FY 2021-06-30

LOW-RISK AUDITEE$13,075,234 federal awards expendedNo findings recorded this year

FAC accepted this audit on February 21, 2022 — management decision was due August 21, 2022.

FY 2020-06-30

LOW-RISK AUDITEE$7,643,887 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 13, 2020 — management decision was due June 13, 2021.

FY 2019-06-30

$2,307,803 federal awards expendedNo findings recorded this year

FAC accepted this audit on November 19, 2019 — management decision was due May 19, 2020.

FY 2018-06-30

$1,168,225 federal awards expendedNo findings recorded this year

FAC accepted this audit on February 6, 2019 — management decision was due August 6, 2019.

FY 2017-06-30

$10,088,369 federal awards expendedNo findings recorded this year

FAC accepted this audit on February 14, 2018 — management decision was due August 14, 2018.

Browse other Single Audit organizations in Illinois

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.