ASI SIOUX FALLS, INC.11 audit years1 findings
11
Audit Years
1
Total Findings
0
Repeat Findings
$2.1M
Federal Awards Expended (FY 2026)

FY 2026-03-31

$2,058,583 federal awards expendedNo findings recorded this year

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on June 24, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 24, 2026 (115 days from today).

What is a management decision? →

FY 2025-03-31

$2,052,207 federal awards expendedNo findings recorded this year

FAC accepted this audit on July 17, 2025 — management decision was due January 17, 2026.

FY 2024-03-31

$2,045,275 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 9, 2024 — management decision was due March 9, 2025.

FY 2023-03-31

$2,045,732 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 12, 2023 — management decision was due June 12, 2024.

FY 2022-03-31

$2,047,435 federal awards expendedNo findings recorded this year

FAC accepted this audit on December 11, 2022 — management decision was due June 11, 2023.

FY 2021-03-31

$2,036,435 federal awards expended

FAC accepted this audit on November 9, 2021 — management decision was due May 9, 2022.

2021-001
Cost Allowability
QUESTIONED COSTSOTHER MATTERS

In 1 of 25 cash disbursements tested, the Project paid the expense of another project under common management. Criteria: The Project should not pay the expenses of another project. Effect: The amount of expenses incorrectly paid was $50 out of a total sample of disbursements of $5,174. Context: A sample of disbursements was selected for testing of compliance. The test found one disbursement that was not in compliance. The non compliance had a financial effect outlined below. The details and results of the sample are as follows: Number Dollars Population 221 $105,646 Sample 25 $5,174 Not in Compliance 1 $50 Questioned Costs $50 Cause: The Project mistakenly paid an invoice of another project under common management. Recommendation: The Project should carefully review invoices before payment to make sure it pays only the amounts applicable to each project. Views of Responsible Officials and Planned Corrective Actions: The Project agrees with the finding. The accounts payable staff will be reminded to be careful when entering invoices for payment. Total - Department of Housing and Urban Development $50 Non-compliance code - R

Show full finding ▾
Full finding narrative

ASI SIOUX FALLS, INC. HUD PROJECT NO. 091-HD013 SCHEDULE OF FINDINGS AND QUESTIONED COSTS (CONTINUED) YEAR ENDED MARCH 31, 2021 C. Findings and Questioned Costs - Major Federal Award Programs Audit Questioned Costs DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT FINDING 2021-001: SECTION 811, CFDA 14.181 Condition: In 1 of 25 cash disbursements tested, the Project paid the expense of another project under common management. Criteria: The Project should not pay the expenses of another project. Effect: The amount of expenses incorrectly paid was $50 out of a total sample of disbursements of $5,174. Context: A sample of disbursements was selected for testing of compliance. The test found one disbursement that was not in compliance. The non compliance had a financial effect outlined below. The details and results of the sample are as follows: Number Dollars Population 221 $105,646 Sample 25 $5,174 Not in Compliance 1 $50 Questioned Costs $50 Cause: The Project mistakenly paid an invoice of another project under common management. Recommendation: The Project should carefully review invoices before payment to make sure it pays only the amounts applicable to each project. Views of Responsible Officials and Planned Corrective Actions: The Project agrees with the finding. The accounts payable staff will be reminded to be careful when entering invoices for payment. Total - Department of Housing and Urban Development $50 Non-compliance code - R

Corrective Action Plan

ASI SIOUX FALLS, INC. HUD PROJECT NO. 091-HD013 CORRECTIVE ACTION PLAN YEAR ENDED MARCH 31, 2021 DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT ASI - Sioux Falls, Inc. respectfully submits the following corrective action plan for the year ended March 31, 2021. Name and address of independent public accounting firm: Hinrichs & Associates, Ltd. 1000 Shelard Parkway, Suite 110 Minneapolis, MN 55426 Audit Period: March 31, 2021 The findings from the March 31, 2021 schedule of findings and questioned costs are discussed below. The findings are numbered consistently with the numbers assigned in the schedule. Section A of the schedule, Summary of Audit Results, does not include findings and is not addressed. FINDINGS - FINANCIAL STATEMENT AUDIT NONE FINDINGS - FEDERAL AWARD PROGRAMS AUDIT DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT FINDING 2021-001: SECTION 811, CFDA 14.181 The Project paid an invoice related to another project under common management. Recommendation: The Project should carefully review invoices before payment to make sure it pays for only those costs related to the Project. Action Taken: The Project agrees with the finding. The accounts payable staff was reminded in April 2021 to be careful when entering invoices for payment. If the Department of Housing and Urban Development has questions regarding this plan, please call Chuck Reuter at 651-645-7271.

About Allowable Costs / Cost Principles →

FY 2020-03-31

$2,033,786 federal awards expendedNo findings recorded this year

FAC accepted this audit on November 30, 2020 — management decision was due May 30, 2021.

FY 2019-03-31

$2,026,861 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 13, 2019 — management decision was due April 13, 2020.

FY 2018-03-31

$2,020,576 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 9, 2018 — management decision was due April 9, 2019.

FY 2017-03-31

$2,023,730 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 16, 2017 — management decision was due April 16, 2018.

FY 2016-03-31

$2,022,232 federal awards expendedNo findings recorded this year

FAC accepted this audit on October 23, 2016 — management decision was due April 23, 2017.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Minnesota

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.