EIN: 264548942
UEI: VK3TH2ZNZ118
Audited by: Maddox & Associates, APC
Oversight agency: 14 [Department of Housing and Urban Development]
View federal awards & risk assessment →
Data as of August 31, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on January 20, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by July 20, 2026 (44 days ago).
What is a management decision? →FAC accepted this audit on October 10, 2024 — management decision was due April 10, 2025.
FAC accepted this audit on January 31, 2024 — management decision was due July 31, 2024.
FAC accepted this audit on December 26, 2022 — management decision was due June 26, 2023.
FAC accepted this audit on October 27, 2021 — management decision was due April 27, 2022.
FAC accepted this audit on November 8, 2020 — management decision was due May 8, 2021.
FAC accepted this audit on October 29, 2019 — management decision was due April 29, 2020.
The project did not remit excess Residual Receipts to HUD. Cause: Residual Receipts account balance was not monitored. Effect or Potential Effect: Residual Receipts account is in excess of the required balance. Auditor Non-Compliance Code: Z Questioned Costs: There are no questioned costs. The finding does not relate to an undocumented transaction or unreasonable expenditure. Reporting Views of Responsible Officials: Management agrees with the finding. The excess funds were accrued to submit to HUD. Context: The project did not remit excess Residual Receipts to HUD. Recommendation: Management should monitor the Residual Receipts account balance and remit excess deposits to HUD. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The excess funds were accrued to submit to HUD. Response Indicator: Agree Completion Date: August 1, 2019 Response: Management agrees with the finding. The excess funds were accrued to submit to HUD.
Show full finding ▾Hide full finding ▴Finding Reference Number: 2019-001 Type of Finding: FA Finding Resolution Status: In Process Information on Universe Population Size: The finding was not a result of a sampling procedure. Sample Size Information: The finding was not a result of a sampling procedure. Identification of Repeat Finding and Finding Reference Number: This is not a repeat finding. Criteria: HUD Memorandum dated October 14, 2016, ?Continuing Remission of Excess PRAC Residual Receipts?, continues the requirement that ?Any balance greater than $250 per unit in a Residual Receipts account must be remitted to HUD?s Accounting Center upon ?termination? of the PRAC?. Statement of Condition: The project did not remit excess Residual Receipts to HUD. Cause: Residual Receipts account balance was not monitored. Effect or Potential Effect: Residual Receipts account is in excess of the required balance. Auditor Non-Compliance Code: Z Questioned Costs: There are no questioned costs. The finding does not relate to an undocumented transaction or unreasonable expenditure. Reporting Views of Responsible Officials: Management agrees with the finding. The excess funds were accrued to submit to HUD. Context: The project did not remit excess Residual Receipts to HUD. Recommendation: Management should monitor the Residual Receipts account balance and remit excess deposits to HUD. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The excess funds were accrued to submit to HUD. Response Indicator: Agree Completion Date: August 1, 2019 Response: Management agrees with the finding. The excess funds were accrued to submit to HUD.
Finding Reference Number: 2019-001 Concur or Do Not Concur: Concur Agree or Disagree with Auditor Recommendations: Agree Actions Taken or Planned on the Finding: Management agrees with the finding. The excess funds were accrued to submit to HUD. Completion Date: August 1, 2019
FAC accepted this audit on November 5, 2018 — management decision was due May 5, 2019.
FAC accepted this audit on December 3, 2017 — management decision was due June 3, 2018.
FAC accepted this audit on November 21, 2016 — management decision was due May 21, 2017.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Virginia →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.