← Back to home

SEDA-COG JOINT RAIL AUTHORITYLocal Government

EIN: 232746067

UEI: LHD3ABUMDFN5

Audited by: 301413443

Oversight agency: 20 [Department of Transportation]

View federal awards & risk assessment →

Data as of September 2, 2026

SEDA-COG JOINT RAIL AUTHORITY1 audit years1 findings
1
Audit Years
1
Total Findings
0
Repeat Findings
$4.7M
Federal Awards Expended (FY 2024)

FY 2024-12-31

$4,714,597 federal awards expended

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on September 3, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 3, 2026 (184 days ago).

What is a management decision? →
2024-002
Cost Allowability
OTHER MATTERS

2024-002 - (Noncompliance) Uniform Guidance Written Policies/Procedures Federal Program: Assistance Listing #20.205 Highway Planning and Construction, U.S. Department of Transportation, Passed Through Pennsylvania Department Transportation, Pass-Through Entity Identifying Numbers: U034865000, U034923000, and U02A100400 Prior Year Finding Number: N/A Criteria: The Uniform Guidance requires written policies and/or procedures in the areas of allowability of costs and cash management. Condition/Context: While the Authority has informal policies and procedures surrounding the administration of its federal programs, these policies and procedures have not been formally documented to ensure compliance with the areas of allowability of costs and cash management as required under the Uniform Guidance. Questioned Costs: N/A Cause: The Authority has not yet prepared its written policies/procedures required by the Uniform Guidance. Effect: The Authority is not in compliance with certain requirements of the Uniform Guidance and as such, employees do not currently have the benefit of these written policies and/or procedures to assist in managing and directing its federal award programs. Recommendation: We recommend that Authority management prepare the required written policies/procedures related to allowability of costs and cash management outlined with the Uniform Guidance. Views of Responsible Officials and Planned Corrective Actions: Management understands and is working to formally document the required elements of its policies and procedures pursuant to the Uniform Guidance.

Show full finding ▾
Full finding narrative

2024-002 - (Noncompliance) Uniform Guidance Written Policies/Procedures Federal Program: Assistance Listing #20.205 Highway Planning and Construction, U.S. Department of Transportation, Passed Through Pennsylvania Department Transportation, Pass-Through Entity Identifying Numbers: U034865000, U034923000, and U02A100400 Prior Year Finding Number: N/A Criteria: The Uniform Guidance requires written policies and/or procedures in the areas of allowability of costs and cash management. Condition/Context: While the Authority has informal policies and procedures surrounding the administration of its federal programs, these policies and procedures have not been formally documented to ensure compliance with the areas of allowability of costs and cash management as required under the Uniform Guidance. Questioned Costs: N/A Cause: The Authority has not yet prepared its written policies/procedures required by the Uniform Guidance. Effect: The Authority is not in compliance with certain requirements of the Uniform Guidance and as such, employees do not currently have the benefit of these written policies and/or procedures to assist in managing and directing its federal award programs. Recommendation: We recommend that Authority management prepare the required written policies/procedures related to allowability of costs and cash management outlined with the Uniform Guidance. Views of Responsible Officials and Planned Corrective Actions: Management understands and is working to formally document the required elements of its policies and procedures pursuant to the Uniform Guidance.

Corrective Action Plan

Recommendation: We recommend that Authority management prepare the required written policies/procedures related to allowability of costs and cash management outlined with the Uniform Guidance. Management Response: Management concurs with finding. Planned Corrective Action: The accounting staff will work with the operations staff to prepare the necessary written policies/procedures. Persons Responsible: Jamie Carnes, Fiscal Controller, SEDA-COG Anticipated Completion Date: October 31, 2025

About Allowable Costs / Cost Principles →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Browse other Single Audit organizations in Pennsylvania

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and filing records.

Start monitoring →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.