EIN: 231668292
UEI: N1MHAG18U2C7
Audited by: Gorman & Associates, PC
Oversight agency: 10 [Department of Agriculture]
View federal awards & risk assessment →
Data as of August 28, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on March 18, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 18, 2026 (17 days from today).
What is a management decision? →During testing of ESSER III, we noted that the District had unspent funds remaining after reconciling the grant expenditures to the Final Expenditure Report (FER). Upon further review of the FER and discussions with District staff, we determined that expenditures related to the Federal Set-Aside awards had been mistakenly included in the FER for ESSER III, despite the use of separate source codes for each. The District believed the Set-Aside funds were part of the ESSER III award, and therefore included the Set-Aside expenditures when preparing the FER for ESSER III. Because the District’s reports for ESSER III were including the Set-Aside expenditures, the District believe ESSER III had been fully expended when, in fact, allowable ESSER III expenditures remained unreported. During the current fiscal year, the District subsequently identified certain allowable ESSER III expenditures incurred during the 2023-24 fiscal year that were coded to non-federal sources and reclassified them as ESSER III expenditures for that year. These expenditures were not identified as ESSER III expenditures in the prior fiscal year and were not included in the SEFA until they were identified during the current fiscal year. As a result, the SEFA for the year ended June 30, 2024 understated ESSER III expenditures. Cause: The District misunderstood the structure of the ESSER III and Federal Set-Aside awards and believed that the Set-Aside funds were part of the ESSER III allocation. As a result of the misunderstanding, the District included the expenditures for the Set-Asides with the ESSER III expenditures when submitting the FER for ESSER III. Effect: Federal expenditures for ESSER III were understated on the District’s SEFA for the year ended June 30, 2024. A correction was made in the current fiscal year to properly report the expenditures in the period in which they were incurred. Context: The expenditures identified were allowable costs that were incurred during fiscal year 2023-24. The issue did not involve unallowable costs, eligibility violations, or misuse of federal funds. Rather, the finding resulted from misunderstanding the structure of ESSER III and the Federal Set-Aside awards, which led to miscoding and reporting errors. Once identified, the District worked with the auditors to correct the error and properly report the expenditures. Recommendation: We recommend the District provide additional training to staff responsible for federal grant accounting to ensure a clear understanding of grant award structures to facilitate proper grant tracking and reporting. View of Responsible Officials: The District agrees with the finding and the recommendation and will take steps to ensure the staff responsible are properly trained and educated on each grant received by the District.
Show full finding ▾Hide full finding ▴Finding 2025-002: Significant Deficiency – Internal Control Over Federal Award Reporting (ESSER III) Type of Finding: Internal Control Federal Program: Education Stabilization Fund - ARP-ESSER ALN: 84.425U Federal Award Year: 2021 Federal Agency: Department of Education Pass-thru entity: PA Department of education Pass-thru nos: 223-21-0422 Questioned Costs: None Repeat Finding: No Type of Compliance Requirement: Reporting Criteria: 2 CFR 200.510(b) requires the Schedule of Expenditures of Federal Awards (SEFA) to fairly present total federal expenditures for each federal program in the period in which they are incurred. Condition: During testing of ESSER III, we noted that the District had unspent funds remaining after reconciling the grant expenditures to the Final Expenditure Report (FER). Upon further review of the FER and discussions with District staff, we determined that expenditures related to the Federal Set-Aside awards had been mistakenly included in the FER for ESSER III, despite the use of separate source codes for each. The District believed the Set-Aside funds were part of the ESSER III award, and therefore included the Set-Aside expenditures when preparing the FER for ESSER III. Because the District’s reports for ESSER III were including the Set-Aside expenditures, the District believe ESSER III had been fully expended when, in fact, allowable ESSER III expenditures remained unreported. During the current fiscal year, the District subsequently identified certain allowable ESSER III expenditures incurred during the 2023-24 fiscal year that were coded to non-federal sources and reclassified them as ESSER III expenditures for that year. These expenditures were not identified as ESSER III expenditures in the prior fiscal year and were not included in the SEFA until they were identified during the current fiscal year. As a result, the SEFA for the year ended June 30, 2024 understated ESSER III expenditures. Cause: The District misunderstood the structure of the ESSER III and Federal Set-Aside awards and believed that the Set-Aside funds were part of the ESSER III allocation. As a result of the misunderstanding, the District included the expenditures for the Set-Asides with the ESSER III expenditures when submitting the FER for ESSER III. Effect: Federal expenditures for ESSER III were understated on the District’s SEFA for the year ended June 30, 2024. A correction was made in the current fiscal year to properly report the expenditures in the period in which they were incurred. Context: The expenditures identified were allowable costs that were incurred during fiscal year 2023-24. The issue did not involve unallowable costs, eligibility violations, or misuse of federal funds. Rather, the finding resulted from misunderstanding the structure of ESSER III and the Federal Set-Aside awards, which led to miscoding and reporting errors. Once identified, the District worked with the auditors to correct the error and properly report the expenditures. Recommendation: We recommend the District provide additional training to staff responsible for federal grant accounting to ensure a clear understanding of grant award structures to facilitate proper grant tracking and reporting. View of Responsible Officials: The District agrees with the finding and the recommendation and will take steps to ensure the staff responsible are properly trained and educated on each grant received by the District.
Significant Deficiency 2025-002 (Internal Control Over Federal Award Reporting – ESSER III) Federal Program: Education Stabilization Fund - ARP-ESSER ALN: 84.425U Condition: Allowable ESSER III expenditures incurred during fiscal year 2023-24 were not identified or included on the Schedule of Expenditures of Federal Awards (SEFA) for that year. In addition, expenditures related to Federal Set-Aside awards were mistakenly included in the Final Expenditure Report for ESSER III, resulting from a misunderstanding of the structure of the federal awards. Recommendation: Strengthen internal controls Corrective Action: The District will provide targeted training to staff responsible for federal grant accounting to ensure a clear understanding of federal grant award structures, including the distinction between ESSER III and related Federal Set-Aside awards. This training will cover grant setup, expenditure coding, and reporting requirements. Person Responsible: Brenda VanBuskirk, Business Manager Proposed Completion Date: December 31, 2025
FAC accepted this audit on January 20, 2025 — management decision was due July 20, 2025.
FAC accepted this audit on January 19, 2024 — management decision was due July 19, 2024.
FAC accepted this audit on January 30, 2023 — management decision was due July 30, 2023.
FAC accepted this audit on January 12, 2022 — management decision was due July 12, 2022.
FAC accepted this audit on December 20, 2020 — management decision was due June 20, 2021.
FAC accepted this audit on January 12, 2020 — management decision was due July 12, 2020.
FAC accepted this audit on January 2, 2019 — management decision was due July 2, 2019.
GSA_MIGRATION
Show full finding ▾Hide full finding ▴GSA_MIGRATION
GSA_MIGRATION
2017-001
FAC accepted this audit on January 4, 2018 — management decision was due July 4, 2018.
GSA_MIGRATION
Show full finding ▾Hide full finding ▴GSA_MIGRATION
GSA_MIGRATION
FAC accepted this audit on January 15, 2017 — management decision was due July 15, 2017.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in Pennsylvania →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.