← Back to home

WESTCHESTER INSTITUTE FOR HUMAN DEVELOPMENTNon-Profit

EIN: 200738248

UEI: FFJYM5V5GD37

Audited by: Cerini & Associates, LLP

Oversight agency: 93 [Department of Health and Human Services]

View federal awards & risk assessment →

Data as of September 7, 2026

WESTCHESTER INSTITUTE FOR HUMAN DEVELOPMENT8 audit years1 findings
8
Audit Years
1
Total Findings
0
Repeat Findings
$1.9M
Federal Awards Expended (FY 2025)

FY 2025-12-31

LOW-RISK AUDITEE$1,857,074 federal awards expendedNo findings recorded this year

FY 2024-12-31

LOW-RISK AUDITEE$2,288,845 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 6, 2025 — management decision was due December 6, 2025.

FY 2023-12-31

LOW-RISK AUDITEE$2,351,850 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 4, 2024 — management decision was due December 4, 2024.

FY 2022-12-31

LOW-RISK AUDITEE$2,371,389 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 4, 2023 — management decision was due December 4, 2023.

FY 2021-12-31

LOW-RISK AUDITEE$3,056,841 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 8, 2022 — management decision was due December 8, 2022.

FY 2020-12-31

$2,020,079 federal awards expendedNo findings recorded this year

FAC accepted this audit on September 29, 2021 — management decision was due March 29, 2022.

FY 2019-12-31

$1,457,017 federal awards expended

FAC accepted this audit on October 4, 2020 — management decision was due April 4, 2021.

2019-001
Reporting
SIGNIFICANT DEFICIENCY

During the current year audit, it was discovered that the Organization did not timely submit the required data collection form for one of the two prior years in conformity with 45 CFR Section 75.512. Criteria: Internal controls should be in place to provide reasonable assurance that an individual ensures that all reporting required by the Office of Management and Budget ("OMB") and Uniform Guidance is timely submitted after obtaining proper management approval. Cause: There were no procedures in place to ensure an individual in management tracked the filing due date. This resulted in the data collection form and related audit package not being timely submitted. Effect: Because of the lack of an internal control process over reporting, the data collection form and related audit package was not submitted timely in accordance with OMB rules and regulations. Recommendation: Procedures should be implemented to designate an individual within management to oversee the completion and submission of the data collection form and related audit package. Views of Responsible Officials and Planned Corrective Actions: Westchester Institute for Human Development agrees with the finding. The Organization has designated an individual to track the filing of the form and related audit package, and has implemented the recommended procedures.

Show full finding ▾
Full finding narrative

2019-001 Non-timely filing of reports Condition: During the current year audit, it was discovered that the Organization did not timely submit the required data collection form for one of the two prior years in conformity with 45 CFR Section 75.512. Criteria: Internal controls should be in place to provide reasonable assurance that an individual ensures that all reporting required by the Office of Management and Budget ("OMB") and Uniform Guidance is timely submitted after obtaining proper management approval. Cause: There were no procedures in place to ensure an individual in management tracked the filing due date. This resulted in the data collection form and related audit package not being timely submitted. Effect: Because of the lack of an internal control process over reporting, the data collection form and related audit package was not submitted timely in accordance with OMB rules and regulations. Recommendation: Procedures should be implemented to designate an individual within management to oversee the completion and submission of the data collection form and related audit package. Views of Responsible Officials and Planned Corrective Actions: Westchester Institute for Human Development agrees with the finding. The Organization has designated an individual to track the filing of the form and related audit package, and has implemented the recommended procedures.

Corrective Action Plan

Finding 2019-001: The Organization did not timely submit the required data collection form for one of the prior two years in conformity with 45 CFR Section 75.512. Name of Contact Person: Marianne Ventrice, Chief Financial and Administrative Officer Corrective Action Plan: The Organization has undergone a single audit as required by Uniform Guidance for the year ended December 31, 2019 and has implemented procedures and designated an individual to monitor the timely filing of the data collection form. As part of the process, the Organization intends to file its data collection form with the Federal Audit Clearinghouse upon completion of its audit under Uniform Guidance. Anticipated Completion Date: Immediately

About Reporting →

FY 2016-12-31

LOW-RISK AUDITEE$1,422,482 federal awards expendedNo findings recorded this year

FAC accepted this audit on June 28, 2017 — management decision was due December 28, 2017.

Browse other Single Audit organizations in New York

Start tracking findings →

Do you fund this organization?

Add it to a monitored group and get alerted when a new audit, finding, repeat finding, or management-decision deadline shows up — instead of checking back.

Checking several at once? Portfolio view →

Product

Resources

Legal

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.

© 2026 Single Audit Intelligence. All data is public domain.