EIN: 156000966
UEI: RWGMVFUMF831
Audited by: Bonadio & Co., LLP
Oversight agency: 10 [Department of Agriculture]
View federal awards & risk assessment →
Data as of August 31, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on February 4, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by August 4, 2026 (28 days ago).
What is a management decision? →FAC accepted this audit on September 25, 2025 — management decision was due March 25, 2026.
FAC accepted this audit on September 25, 2025 — management decision was due March 25, 2026.
The Town's internal controls were not designed effectively to ensure project expenditures on the United States Department of Agriculture (USDA) Form E – Rural Development (RD) Project Budget/Cost Certification Reporting were accurate and existed. Effect: The Town reported a duplicate expenditure incurred during the fiscal year ending December 31, 2023 on a Form E Report submitted to the USDA in the amount of approximately $15,000. Recommendation: The Town should design internal control procedures that require reconciliation of the expenditures reported on the Form Es submitted to Rural Development to the general ledger to ensure completeness and accuracy, as well as to detect any duplicate expenses that should be removed from the claim before submission. Management’s Response: The Town acknowledges the audit finding related to internal controls over compliance with USDA Rural Development reporting requirements. During the review, it was identified that two separate project expenditures were incorrectly reported under the same vendor on Form E for the fiscal year ending December 31, 2023. While the expenditures themselves were valid and supported, the misclassification resulted in an inaccurate representation of vendor reporting. Corrective Action Plan: To address this issue and prevent recurrence, the Town has implemented the following measures: 1. Reconciliation Procedures: Finance Department staff will reconcile all expenditures reported on USDA Form E – RD Project Budget/Cost Certification Reporting to the general ledger, ensuring both the accuracy of amounts and the correct vendor attribution. 2. Vendor Verification: A vendor cross-check process will be added to the review, requiring staff to match each reported expenditure to the appropriate invoice, purchase order, and vendor record before submission. 3. Review & Approval Controls: A supervisory review will be conducted prior to submission of Form E reports to verify vendor accuracy, in addition to ensuring no duplicate or misclassified expenditures are reported. The Town is committed to ensuring compliance with all USDA reporting requirements. By strengthening reconciliation, vendor verification, and review processes, we will reduce the risk of reporting errors and maintain accurate, reliable financial reporting moving forward.
Show full finding ▾Hide full finding ▴Reference Number: 2023-001 Grant Loan Program Reporting Criteria: Internal controls over compliance in relation to reporting requirements of grant loan programs should be designed to verify the expenditures submitted are complete and accurate and transactions exist. Cause/Condition: The Town's internal controls were not designed effectively to ensure project expenditures on the United States Department of Agriculture (USDA) Form E – Rural Development (RD) Project Budget/Cost Certification Reporting were accurate and existed. Effect: The Town reported a duplicate expenditure incurred during the fiscal year ending December 31, 2023 on a Form E Report submitted to the USDA in the amount of approximately $15,000. Recommendation: The Town should design internal control procedures that require reconciliation of the expenditures reported on the Form Es submitted to Rural Development to the general ledger to ensure completeness and accuracy, as well as to detect any duplicate expenses that should be removed from the claim before submission. Management’s Response: The Town acknowledges the audit finding related to internal controls over compliance with USDA Rural Development reporting requirements. During the review, it was identified that two separate project expenditures were incorrectly reported under the same vendor on Form E for the fiscal year ending December 31, 2023. While the expenditures themselves were valid and supported, the misclassification resulted in an inaccurate representation of vendor reporting. Corrective Action Plan: To address this issue and prevent recurrence, the Town has implemented the following measures: 1. Reconciliation Procedures: Finance Department staff will reconcile all expenditures reported on USDA Form E – RD Project Budget/Cost Certification Reporting to the general ledger, ensuring both the accuracy of amounts and the correct vendor attribution. 2. Vendor Verification: A vendor cross-check process will be added to the review, requiring staff to match each reported expenditure to the appropriate invoice, purchase order, and vendor record before submission. 3. Review & Approval Controls: A supervisory review will be conducted prior to submission of Form E reports to verify vendor accuracy, in addition to ensuring no duplicate or misclassified expenditures are reported. The Town is committed to ensuring compliance with all USDA reporting requirements. By strengthening reconciliation, vendor verification, and review processes, we will reduce the risk of reporting errors and maintain accurate, reliable financial reporting moving forward.
Corrective Action Plan: To address this issue and prevent recurrence, the Town has implemented the following measures: 1. Reconciliation Procedures: Finance Department staff will reconcile all expenditures reported on USDA Form E – RD Project Budget/Cost Certification Reporting to the general ledger, ensuring both the accuracy of amounts and the correct vendor attribution. 2. Vendor Verification: A vendor cross-check process will be added to the review, requiring staff to match each reported expenditure to the appropriate invoice, purchase order, and vendor record before submission. 3. Review & Approval Controls: A supervisory review will be conducted prior to submission of Form E reports to verify vendor accuracy, in addition to ensuring no duplicate or misclassified expenditures are reported. The Town is committed to ensuring compliance with all USDA reporting requirements. By strengthening reconciliation, vendor verification, and review processes, we will reduce the risk of reporting errors and maintain accurate, reliable financial reporting moving forward.
FAC accepted this audit on September 23, 2017 — management decision was due March 23, 2018.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Browse other Single Audit organizations in New York →
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.