EIN: 046001361
UEI: JNC3YYJ7PJH3
Audited by: ROSELLI, CLARK AND ASSOCIATES
Oversight agency: 21 [Department of the Treasury]
View federal awards & risk assessment →
Data as of August 28, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on March 30, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 30, 2026 (32 days from today).
What is a management decision? →Expenditures were not reconciled to the general ledger for reporting submitted to the U.S. Department of the Treasury and Bristol County, Massachusetts. Cause: The Town did not have procedures in place to perform reconciliations of required grant reporting. Effect: The Town potentially overstated expenditures by approximately $528,000 and $127,000 in reporting submitted to the U.S. Department of the Treasury and Bristol County, Massachusetts, respectively. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The Town should implement procedures to reconcile all federal reporting to the general ledger. Views of Responsible Official: Management agrees with the finding.
Show full finding ▾Hide full finding ▴2025-001 U.S. Department of the Treasury Direct Award and Passed through Bristol County, Massachusetts COVID-19 – Coronavirus State and Local Fiscal Recovery Funds – ALN 21.027 Significant Deficiency in Internal Controls over Compliance and Compliance Finding Criteria: The compliance supplement identifies four Key Line Items required to be reported to the federal awarding agency which include (1) current period obligation, (2) cumulative obligation, (3) current period expenditure and (4) cumulative expenditure. Per 2 CFR 200.1, an obligation is an order placed for property and services, contracts and subawards made, and similar transactions that require payment. Condition: Expenditures were not reconciled to the general ledger for reporting submitted to the U.S. Department of the Treasury and Bristol County, Massachusetts. Cause: The Town did not have procedures in place to perform reconciliations of required grant reporting. Effect: The Town potentially overstated expenditures by approximately $528,000 and $127,000 in reporting submitted to the U.S. Department of the Treasury and Bristol County, Massachusetts, respectively. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The Town should implement procedures to reconcile all federal reporting to the general ledger. Views of Responsible Official: Management agrees with the finding.
Finding 2025-001 Condition: Expenditures were not reconciled to the general ledger for reporting submitted to the U.S. Department of the Treasury and Bristol County, Massachusetts. Corrective Action Planned: To ensure the accuracy of ARPA reporting, and all Federal Grants, a reconciliation process will be implemented and followed by all involved. Anticipated Completion Date: April 30, 2026 Contact: Nicole Pearsall, Town Accountant
FAC accepted this audit on March 6, 2025 — management decision was due September 6, 2025.
FAC accepted this audit on April 30, 2024 — management decision was due October 30, 2024.
Obligations were overstated by approximately $800,000 on the March 31, 2023 Project and Expenditure report. Cause: The Town did not have a clear understanding of the reporting requirements for obligations and reported the entire grant award as obligated. Effect: The Town did not properly report amounts obligated in the March 31, 2023 Project and Expenditure report. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The Town should implement procedures to only report obligations on the Project and Expenditure reporting for items that meet the federal criteria for reporting as an obligation. Views of Responsible Official: Management agrees with the finding.
Show full finding ▾Hide full finding ▴2023-001 U.S. Department of the Treasury COVID-19 – Coronavirus State and Local Fiscal Recovery Funds – ALN 21.027 Criteria: The compliance supplement identifies four Key Line Items required to be reported to the federal awarding agency which include (1) current period obligation, (2) cumulative obligation, (3) current period expenditure and (4) cumulative expenditure. Per 2 CFR 200.1, an obligation is an order placed for property and services, contracts and subawards made, and similar transactions that require payment. Condition: Obligations were overstated by approximately $800,000 on the March 31, 2023 Project and Expenditure report. Cause: The Town did not have a clear understanding of the reporting requirements for obligations and reported the entire grant award as obligated. Effect: The Town did not properly report amounts obligated in the March 31, 2023 Project and Expenditure report. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The Town should implement procedures to only report obligations on the Project and Expenditure reporting for items that meet the federal criteria for reporting as an obligation. Views of Responsible Official: Management agrees with the finding.
Condition: Obligations were overstated by approximately $800,000 on the March 31, 2023 Project and Expenditure report. Corrective Action Planned: Will adjust on March 31, 2024 Project and Expenditure report. Anticipated Completion Date: April 30, 2024 Contact: Nicole Pearsall, Town Accountant
FAC accepted this audit on March 29, 2023 — management decision was due September 29, 2023.
FAC accepted this audit on May 24, 2022 — management decision was due November 24, 2022.
FAC accepted this audit on June 9, 2021 — management decision was due December 9, 2021.
Time and effort certifications were not maintained for grant employees? whose salaries and wages were not supported by detailed time records for the period March 2020 through June 2020. Cause: The School did not maintain proper payroll records. Effect: The School is not in compliance with applicable cost principles related to salaries and wages. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The School should implement procedures to obtain time and effort certifications from grant employees whose wages are not supported with detailed time records. Time and effort certifications should be obtained on a semi-annual basis for employees whose work is solely for a single grant and on a monthly basis for employees whose work involves more than one grant or activity. Views of Responsible Officials: Management agrees with the finding.
Show full finding ▾Hide full finding ▴Criteria: Per 2 CFR section 200.430(i) of the Uniform Guidance, charges to federal awards for salaries and wages must be based on records that accurately reflect the work performed. Semiannual or monthly time and effort certifications are to be utilized if the non-federal entity?s records do not meet the related standards described in the Uniform Guidance. Condition: Time and effort certifications were not maintained for grant employees? whose salaries and wages were not supported by detailed time records for the period March 2020 through June 2020. Cause: The School did not maintain proper payroll records. Effect: The School is not in compliance with applicable cost principles related to salaries and wages. Questioned Costs: None Repeat Finding from Prior Year: No Recommendation: The School should implement procedures to obtain time and effort certifications from grant employees whose wages are not supported with detailed time records. Time and effort certifications should be obtained on a semi-annual basis for employees whose work is solely for a single grant and on a monthly basis for employees whose work involves more than one grant or activity. Views of Responsible Officials: Management agrees with the finding.
Condition: Time and effort certifications were not maintained for grant employees? whose salaries and wages were not supported by detailed time records for the period March 2020 through June 2020. Corrective Action Planned: Time and effort certifications were not maintained for Title I employees during the months of March-June due to the COVID-19 closure. The Director will continue to compile these certifications for employees paid from future federal grants. Anticipated Completion Date: Fiscal year 2021 Contact: Darren Elwell, Director of Curriculum and Grants, Westport Community Schools
FAC accepted this audit on March 22, 2020 — management decision was due September 22, 2020.
FAC accepted this audit on April 17, 2019 — management decision was due October 17, 2019.
FAC accepted this audit on April 2, 2018 — management decision was due October 2, 2018.
FAC accepted this audit on June 29, 2017 — management decision was due December 29, 2017.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and filing records.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.