ASSOCIATION OF VILLAGE COUNCIL PRESIDENTS REGIONAL HOUSING AUTHORITY

EIN: 920048664

UEI: EATUQFX9ENE9

Data as of August 20, 2026

12
Audit Years
2
Total Findings
0
Repeat Findings

FY 2022-09-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on August 13, 2023. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by February 13, 2024, which was (920 days ago).

What is a management decision? →
2022-002
Reporting
Condition

Association of Village Council Presidents Housing Authority (the Authority) had the following finding for the year ended September 30, 2022: Finding 2022?002. Program information All federal programs. Statement of condition The Authority did not submit its federal single audit reports within the 12 months of year end (9 months of year end Uniform Guidance requirement plus the 3?month COVID?19 extension). Criteria OMB Uniform Guidance requires that single audit reports be submitted to the Federal Audit Clearinghouse within 9 months of year end. Cause of condition Failure to submit a federal single audit report in the required timeframe. Effect of condition Due to late single audit reports, grantors may reduce or cease funding. Questioned Costs Not determined. Recommendation We recommend that the Authority devote the necessary resources to ensure that the audit is completed within 9 months of year end. Response See corrective action plan.

Corrective Action Plan

2021?002 Jeff Lowrey, CFO Management agrees with the finding. Management intends to devote necessary attention to timely filing of reports. To be implemented immediately.

About Reporting →

FY 2017-09-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on June 27, 2018. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 27, 2018, which was (2794 days ago).

What is a management decision? →
2017-003
Cost Allowability
MATERIAL WEAKNESS
Condition

GSA_MIGRATION

Corrective Action Plan

GSA_MIGRATION

About Allowable Costs / Cost Principles →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.