TOWN OF MANVILLE

EIN: 830247722

UEI: QFQMCGHGAVN1

1
Audit Years
1
Total Findings
0
Repeat Findings

FY 2025-06-30

2025-003
Procurement & Suspension/Debarment
Condition

2025-003: Procurement Internal Control Policy - Significant Deficiency Criteria: The Town should have written internal control policies regarding procurement in accordance with Federal guidelines. Condition and Cause: During our testing, we found that the Town does not have a written procurement policy in accordance with Federal guidelines. The cause is undetermined. Effect: Noncompliance Recommendation: We recommend that the Town establish a written procurement policy to ensure compliance with federal guidelines when spending federal funds.

Corrective Action Plan

2025-003: a) I have visited with our lawyer about the procurement policy. b) I am in the process of viewing other towns and writing ours. I plan to have this completed by the end of the month. c) When completed the mayor and council will review and approve or make corrections. The final policy will be approved at the next council meeting. After approval I will submit it to the CPA.

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.