SOUTHERN GATEWAY PUBLIC GREEN FOUNDATION

EIN: 823991844

UEI: K4U1Z32JUDS5

Data as of August 26, 2026

SOUTHERN GATEWAY PUBLIC GREEN FOUNDATION4 audit years2 findings
4
Audit Years
2
Total Findings
0
Repeat Findings

FY 2025-09-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on June 30, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 30, 2026 (126 days from today).

What is a management decision? →
2025-001
Reporting

During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. Management’s Response: See corrective action plan

Show full finding ▾
Full finding narrative

Finding 2025‐001: Reporting – Significant deficiency in internal controls over compliance and compliance finding. Criteria: Under this grant program, the Foundation is required to complete semi‐annual performance reports in the Disaster Recovery Grant Reporting (DRGR) system. Condition: During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. Management’s Response: See corrective action plan

Corrective Action Plan

In its 2025 Compliance Report, auditors made the following finding: Finding 2025‐001: Reporting – Significant deficiency in internal controls over compliance and compliance finding. Criteria: Under this grant program, the Foundation is required to complete semi‐annual performance reports in the Disaster Recovery Grant Reporting (DRGR) system. Condition: During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. In response, Southern Gateway Public Green Foundation commits to the following Corrective Action Plan:  Remedy: In order to remedy this violation, staff will take immediate action to file missing semiannual reports in cooperation with general contractor.  Responsibility for Implementing Remedy: Reports will be filed by Anne Hagan, VP of Strategic Initiatives.  Verification of Remedy: Reports will be reviewed by April Allen, President and CEO, and filing of reports will also be confirmed by April Allen, President and CEO  Deadline for Remedy: As soon as possible but no later than 7/31/26.  Consequences in the event remedy is not undertaken: Failure to file reports could result in request for reimbursement of grant revenue.  Training to Prevent future violations: Reporting requirements and grant agreements will be reviewed by Anne Hagan.  Statement on Consequences of Repeated Violations: If future reports are late or missed, already reimbursed grant payments may have to be repaid and SGPGF may not be eligible for future grant payments.

About Reporting →
2025-001
Reporting

During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. Management’s Response: See corrective action plan

Show full finding ▾
Full finding narrative

Finding 2025‐001: Reporting – Significant deficiency in internal controls over compliance and compliance finding. Criteria: Under this grant program, the Foundation is required to complete semi‐annual performance reports in the Disaster Recovery Grant Reporting (DRGR) system. Condition: During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. Management’s Response: See corrective action plan

Corrective Action Plan

In its 2025 Compliance Report, auditors made the following finding: Finding 2025‐001: Reporting – Significant deficiency in internal controls over compliance and compliance finding. Criteria: Under this grant program, the Foundation is required to complete semi‐annual performance reports in the Disaster Recovery Grant Reporting (DRGR) system. Condition: During reporting testing, it was noted that the Foundation had not completed or submitted the required performance reports during the year. Cause: The Foundation didn’t implement an effective control for ensuring the required reporting under the grant was completed and submitted timely. Effect: Internal control was not properly designed to identify the required reporting and prevent noncompliance, and the Foundation was not in compliance with the reporting requirement. Recommendation: The Foundation should implement internal controls over the reporting process that ensures the required reporting is submitted in a timely manner. In addition, the Foundation should ensure grant agreements are reviewed in detail so no required reporting is overlooked. In response, Southern Gateway Public Green Foundation commits to the following Corrective Action Plan:  Remedy: In order to remedy this violation, staff will take immediate action to file missing semiannual reports in cooperation with general contractor.  Responsibility for Implementing Remedy: Reports will be filed by Anne Hagan, VP of Strategic Initiatives.  Verification of Remedy: Reports will be reviewed by April Allen, President and CEO, and filing of reports will also be confirmed by April Allen, President and CEO  Deadline for Remedy: As soon as possible but no later than 7/31/26.  Consequences in the event remedy is not undertaken: Failure to file reports could result in request for reimbursement of grant revenue.  Training to Prevent future violations: Reporting requirements and grant agreements will be reviewed by Anne Hagan.  Statement on Consequences of Repeated Violations: If future reports are late or missed, already reimbursed grant payments may have to be repaid and SGPGF may not be eligible for future grant payments.

About Reporting →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →