Victory Housing, Inc.

EIN: 822891865

UEI: CBCFAJKGTMD6

Data as of August 22, 2026

Victory Housing, Inc.6 audit years2 findings
6
Audit Years
2
Total Findings
0
Repeat Findings

FY 2021-09-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on January 16, 2022. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by July 16, 2022 (1498 days ago).

What is a management decision? →
2021-001
Reporting / Special Tests & Provisions

Required monthly deposits to the replacement reserve are deficient in the amount of $2,748. Cause: Procedures in place to ensure that deposits are made were not followed. Effect or Potential Effect: Replacement reserve is deficient. Auditor Non-Compliance Code: N Questioned Costs: There are no questioned costs. The finding does not relate to an undocumented transaction or unreasonable expenditure. Reporting Views of Responsible Officials: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future. Context: Required monthly deposits to the replacement reserve are deficient in the amount of $2,748. Recommendation: Management should compare the required annual amount to the monthly deposits made to determine if the correct amount is deposited. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future. Response Indicator: Agree Completion Date: December 29, 2021 Response: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future.

Show full finding ▾
Full finding narrative

Finding Reference Number: 2021-001 Type of Finding: FA Finding Resolution Status: In Process Information on Universe Population Size: The finding was not a result of a sampling procedure. Sample Size Information: The finding was not a result of a sampling procedure. Identification of Repeat Finding and Finding Reference Number: This is not a repeat finding. Criteria: The regulatory agreement (as amended) requires monthly deposits of $3,334. Statement of Condition: Required monthly deposits to the replacement reserve are deficient in the amount of $2,748. Cause: Procedures in place to ensure that deposits are made were not followed. Effect or Potential Effect: Replacement reserve is deficient. Auditor Non-Compliance Code: N Questioned Costs: There are no questioned costs. The finding does not relate to an undocumented transaction or unreasonable expenditure. Reporting Views of Responsible Officials: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future. Context: Required monthly deposits to the replacement reserve are deficient in the amount of $2,748. Recommendation: Management should compare the required annual amount to the monthly deposits made to determine if the correct amount is deposited. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future. Response Indicator: Agree Completion Date: December 29, 2021 Response: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future.

Corrective Action Plan

Finding Reference Number: 2021-001 Concur or Do Not Concur: Concur Agree or Disagree with Auditor Recommendations: Agree Actions Taken or Planned on the Finding: Management agrees with the finding. The replacement reserve deficiency will be funded in the amount of $2,748. Management will ensure that the replacement reserve deposits are made on a timely basis in the future. Completion Date: December 29, 2021

About Reporting, Special Tests and Provisions →
2021-002
Activities Allowed or Unallowed
QUESTIONED COSTS

When the project was acquired by the current owner in the prior year, it still had outstanding advances payable to the previous owner. HUD approved repayment of the advances in a prior year. The monthly approved payment was $800 and was setup to autopay each month. The remaining balance of the advances was repaid in the current year. However, the monthly auto payments continued for a period of time after the advances were paid in full. As a result, the project has a receivable from the prior owner in the amount of $4,836. Cause: The project did not take the proper steps in calculating the balance owed to ensure that the monthly payments were canceled as soon as the advances were paid in full. Effect or Potential Effect: The project has a receivable from the prior owner in the amount of $4,836. Auditor Non-Compliance Code: G Questioned Costs: $4,836 Reporting Views of Responsible Officials: Management agrees with the finding. Context: The project has a receivable from the prior owner in the amount of $4,836. Recommendation: The project should seek reimbursement from the prior owner. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The prior owner repaid the funds to the project on December 22, 2021 in the amount of $4,836. Response Indicator: Agree Completion Date: December 22, 2021 Response: Management agrees with the finding. The prior owner repaid the funds to the project on December 22, 2021 in the amount of $4,836.

Show full finding ▾
Full finding narrative

Finding Reference Number: 2021-002 Type of Finding: FA Finding Resolution Status: Resolved Information on Universe Population Size: The finding was not a result of a sampling procedure. Sample Size Information: The finding was not a result of a sampling procedure. Identification of Repeat Finding and Finding Reference Number: This is not a repeat finding. Criteria: Project funds may be used only for expenses that are reasonable and necessary to the operation of the project as provided for in the Regulatory Agreement between HUD and the project owner. Statement of Condition: When the project was acquired by the current owner in the prior year, it still had outstanding advances payable to the previous owner. HUD approved repayment of the advances in a prior year. The monthly approved payment was $800 and was setup to autopay each month. The remaining balance of the advances was repaid in the current year. However, the monthly auto payments continued for a period of time after the advances were paid in full. As a result, the project has a receivable from the prior owner in the amount of $4,836. Cause: The project did not take the proper steps in calculating the balance owed to ensure that the monthly payments were canceled as soon as the advances were paid in full. Effect or Potential Effect: The project has a receivable from the prior owner in the amount of $4,836. Auditor Non-Compliance Code: G Questioned Costs: $4,836 Reporting Views of Responsible Officials: Management agrees with the finding. Context: The project has a receivable from the prior owner in the amount of $4,836. Recommendation: The project should seek reimbursement from the prior owner. Auditor's Summary of the Auditee's Comments on the Findings and Recommendations: Management agrees with the finding. The prior owner repaid the funds to the project on December 22, 2021 in the amount of $4,836. Response Indicator: Agree Completion Date: December 22, 2021 Response: Management agrees with the finding. The prior owner repaid the funds to the project on December 22, 2021 in the amount of $4,836.

Corrective Action Plan

Finding Reference Number: 2021-002 Concur or Do Not Concur: Concur Agree or Disagree with Auditor Recommendations: Agree Actions Taken or Planned on the Finding: Management agrees with the finding. The prior owner repaid the funds to the project on December 22, 2021 in the amount of $4,836. Completion Date: December 22, 2021

About Activities Allowed or Unallowed →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →