EIN: 814300335
UEI: S74FFWGDRZZ3
Data as of August 26, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on September 24, 2023. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 24, 2024 (885 days ago).
What is a management decision? →CRITERIA Per CFR 200.405 (a)(1) A cost is allocable to a particular Federal award or other cost objective if the goods or services involved are chargeable or assignable to that Federal award or cost objective in accordance with relative benefits received. This standard is met if the cost: (1) Is incurred specifically for the Federal award; (2) Benefits both the Federal award and other work of the non-Federal entity and can be distributed in proportions that may be approximated using reasonable methods; and (3) Is necessary to the overall operation of the non-Federal entity and is assignable in part to the Federal award in accordance with the principles in this subpart. CONDITION During our control and compliance test work over cash management, as well as reconciliation of the Schedule of Federal Expenditures (SEFA), we noted the following: - In testing two of the monthly requests for reimbursement by examining all the invoices related to the reimbursements, we found that there were amounts overbilled that totaled $25,186. - In reconciling the total expenditures on the SEFA, we found that total reimbursement requests exceeded actual expenses incurred by $186,089 (this total includes the $25,186). CAUSE Proper internal control procedures are not maintained to ensure federal reimbursement requests include only actual costs incurred vs budgeted amounts. EFFECT The Organization billed the federal government for amounts of costs that had not yet been incurred and is at-risk for noncompliance with allowable activities and allowable costs, as well as cash management requirements. QUESTIONED COSTS $186,089 CONTEXT Management?s monthly reimbursement requests for the communications and grants technical manager position was based on budgeted amounts and not actual costs incurred. RECOMMENDATION We recommend that management contact the grantor with regard to the overbilled amounts. For future reimbursement requests, only requests funds that are for direct costs incurred and for the approved 10% indirect rate. MANAGEMENT VIEW AND CORRECTIVE ACTION PLAN Corrective action has been taken. FHI has discussed this finding with grantor (USDA Department of Agriculture) as has Auditor. To date, there has been no action taken by the USDA. As of July 2023, FHI has been billing only reimbursable amounts for direct costs incurred and for the approved 10% indirect rate.
Show full finding ▾Hide full finding ▴CRITERIA Per CFR 200.405 (a)(1) A cost is allocable to a particular Federal award or other cost objective if the goods or services involved are chargeable or assignable to that Federal award or cost objective in accordance with relative benefits received. This standard is met if the cost: (1) Is incurred specifically for the Federal award; (2) Benefits both the Federal award and other work of the non-Federal entity and can be distributed in proportions that may be approximated using reasonable methods; and (3) Is necessary to the overall operation of the non-Federal entity and is assignable in part to the Federal award in accordance with the principles in this subpart. CONDITION During our control and compliance test work over cash management, as well as reconciliation of the Schedule of Federal Expenditures (SEFA), we noted the following: - In testing two of the monthly requests for reimbursement by examining all the invoices related to the reimbursements, we found that there were amounts overbilled that totaled $25,186. - In reconciling the total expenditures on the SEFA, we found that total reimbursement requests exceeded actual expenses incurred by $186,089 (this total includes the $25,186). CAUSE Proper internal control procedures are not maintained to ensure federal reimbursement requests include only actual costs incurred vs budgeted amounts. EFFECT The Organization billed the federal government for amounts of costs that had not yet been incurred and is at-risk for noncompliance with allowable activities and allowable costs, as well as cash management requirements. QUESTIONED COSTS $186,089 CONTEXT Management?s monthly reimbursement requests for the communications and grants technical manager position was based on budgeted amounts and not actual costs incurred. RECOMMENDATION We recommend that management contact the grantor with regard to the overbilled amounts. For future reimbursement requests, only requests funds that are for direct costs incurred and for the approved 10% indirect rate. MANAGEMENT VIEW AND CORRECTIVE ACTION PLAN Corrective action has been taken. FHI has discussed this finding with grantor (USDA Department of Agriculture) as has Auditor. To date, there has been no action taken by the USDA. As of July 2023, FHI has been billing only reimbursable amounts for direct costs incurred and for the approved 10% indirect rate.
The Organization billed the federal government for amounts of costs that had not yet been incurred and is at-risk for noncompliance with allowable activities and allowable costs, as well as cash management requirements. Statement of Concurrence or Nonconcurrence: Flower Hill has been billing the US Department of Agriculture 100% of its annual expenses in equal monthly amounts whether the total amount billed was expensed or not. According to audit, this is not allowable under a cost reimbursable contract. The organization agrees with, understands this finding and has already implemented corrective action to this finding. Questioned Costs $186,089 Corrective Action: Corrective action has been taken. FHI has discussed this finding with grantor (USDA Department of Agriculture) as has Auditor. To date, there has been no action taken by the USDA. As of July 2023, FHI has been billing only reimbursable amounts for direct costs incurred and for the approved 10% indirect rate. Name of Contact Person: Person responsible for completing the corrective action plan is Nicole Mast, Director of Operations, nmast@flowerhill.institute. Projected Completion Date: July 2023 Oversight: Billings will be monitored on a monthly basis to ensure full implementation through the end of the current contract (currently March 2026).
CRITERIA Per 2 CFR 200.318(a), the auditee must establish and maintain effective internal control over the federal award the provides assurance that the entity is managing the federal award in compliance with federal statutes, regulations and conditions of the federal award. 2 CFR 200.318(c)(1) provides that the auditee must maintain written standards of conduct covering conflicts of interest and governing the actions of its employees engaged in the selection, award, and administration of contracts. 2 CFR 200.319(c) establishes that the auditee must have written procedures for procurement transactions. According to ? 180.300 of Subpart C ? Responsibilities of Participants Regarding Transactions Doing Business, when you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified. You do this by: (a) Checking System for Award Management (SAM.gov) Exclusions; (b)Collecting a certification from that person; (c) Adding a clause or condition to the covered transaction with that person. CONDITION During our control and compliance test work over procurement we noted the following: 1- In testing three of the consultants used, all three had contracts that exceeded $25,000 but were not tested for suspension and debarment. 2- In testing three of the consultants, used, all three had contracts that exceed the Simplified Acquisition Threshold (SAT) of $250,000, but no sealed bids, proposals, or documentation of sole source was performed. (a) Through further inquiry, the written micropurchase policy of $50,000 was not self-certified. (b) Through further inquiry, small purchases that exceed micropurchase policy but are less than SAT ($250,000) did not obtain quotations. CAUSE Proper internal control procedures are not maintained to ensure federal procurement requirements are met. EFFECT The Organization is not in compliance with federal requirements when entering into procurement contracts as well as not meeting suspension and debarment requirements by potentially contracting with a suspended or debarred vendor. QUESTIONED COSTS None CONTEXT The Organization?s written procurement policy does not address suspension and debarment. In addition, the Organization did not perform a self-certification to lower its micropurchase threshold. The Organization did not maintain proper documentation for selected vendors that were over thresholds. RECOMMENDATION We recommend that the Organization update its procurement policy and adhere to the following: 1 For all vendors with purchases of $25,000 or more, check SAM.gov website for suspension and debarment. 2. Perform an annual self-certification that includes a justification, clear identification of the threshold, and supporting documentation to allow for $50,000 as the micropurchase limit 3. For all vendors/contractors with procurements for goods or services over the micropurchase limit, but under the SAT limit, obtain a number of reasonable quotations. 4. For all vendors/contractors with procurements for goods or services over the SAT limit provide: o Sealed bids o Proposals o Documentation of single source o Express authorization from grantor MANAGEMENT VIEW AND CORRECTIVE ACTION PLAN 1. FHI will search SAM.gov for suspension and debarment of contractors and keep those records on file. FHI will perform this search annually as the contractors registration expires and is renewed. 2. FHI will perform an annual self-certification that includes a justification, clear identification of the threshold, and supporting documentation to allow for $50,000 as the micropurchase limit.
Show full finding ▾Hide full finding ▴CRITERIA Per 2 CFR 200.318(a), the auditee must establish and maintain effective internal control over the federal award the provides assurance that the entity is managing the federal award in compliance with federal statutes, regulations and conditions of the federal award. 2 CFR 200.318(c)(1) provides that the auditee must maintain written standards of conduct covering conflicts of interest and governing the actions of its employees engaged in the selection, award, and administration of contracts. 2 CFR 200.319(c) establishes that the auditee must have written procedures for procurement transactions. According to ? 180.300 of Subpart C ? Responsibilities of Participants Regarding Transactions Doing Business, when you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified. You do this by: (a) Checking System for Award Management (SAM.gov) Exclusions; (b)Collecting a certification from that person; (c) Adding a clause or condition to the covered transaction with that person. CONDITION During our control and compliance test work over procurement we noted the following: 1- In testing three of the consultants used, all three had contracts that exceeded $25,000 but were not tested for suspension and debarment. 2- In testing three of the consultants, used, all three had contracts that exceed the Simplified Acquisition Threshold (SAT) of $250,000, but no sealed bids, proposals, or documentation of sole source was performed. (a) Through further inquiry, the written micropurchase policy of $50,000 was not self-certified. (b) Through further inquiry, small purchases that exceed micropurchase policy but are less than SAT ($250,000) did not obtain quotations. CAUSE Proper internal control procedures are not maintained to ensure federal procurement requirements are met. EFFECT The Organization is not in compliance with federal requirements when entering into procurement contracts as well as not meeting suspension and debarment requirements by potentially contracting with a suspended or debarred vendor. QUESTIONED COSTS None CONTEXT The Organization?s written procurement policy does not address suspension and debarment. In addition, the Organization did not perform a self-certification to lower its micropurchase threshold. The Organization did not maintain proper documentation for selected vendors that were over thresholds. RECOMMENDATION We recommend that the Organization update its procurement policy and adhere to the following: 1 For all vendors with purchases of $25,000 or more, check SAM.gov website for suspension and debarment. 2. Perform an annual self-certification that includes a justification, clear identification of the threshold, and supporting documentation to allow for $50,000 as the micropurchase limit 3. For all vendors/contractors with procurements for goods or services over the micropurchase limit, but under the SAT limit, obtain a number of reasonable quotations. 4. For all vendors/contractors with procurements for goods or services over the SAT limit provide: o Sealed bids o Proposals o Documentation of single source o Express authorization from grantor MANAGEMENT VIEW AND CORRECTIVE ACTION PLAN 1. FHI will search SAM.gov for suspension and debarment of contractors and keep those records on file. FHI will perform this search annually as the contractors registration expires and is renewed. 2. FHI will perform an annual self-certification that includes a justification, clear identification of the threshold, and supporting documentation to allow for $50,000 as the micropurchase limit.
Description of Finding: During the Auditor?s control and compliance test work the following was noted: o In testing three of the consultants used, all three had contracts that exceeded $25,000 but were not tested for suspension and debarment. o In testing three of the consultants, used, all three had contracts that exceed the Simplified Acquisition Threshold (SAT) of $250,000, but no sealed bids, proposals, or documentation of sole source was performed. o Through further inquiry, the written ?micropurchase? policy of $50,000 was not self-certified. o Through further inquiry, small purchases that exceed micropurchase policy but are less than SAT did not obtain quotations. As a result, FHI is not in compliance with federal requirements when entering into procurement contracts as well as not meeting suspension and debarment requirements by potentially contracting with a suspended or debarred vendor. Statement of Concurrence or Nonconcurrence: A resume of every contractor and their budgeted compensation was provided to the Department of Agriculture with our competitive application as well as with the service agreement contract signed by both representatives of USDA and FHI. Because of timing on the grantor?s end, FHI has less than 10 business days to review and ratify contract and no one at USDA questioned use of consultants, consultants by name/resume or compensation amounts. However, we acknowledge Federal regulations cited by the Auditor. Questioned Costs: None Corrective Action: ? FHI will search SAM.gov for suspension and debarment of contractors and keep those records on file. FHI will perform this search annually as the contractors registration expires and is renewed. ? FHI will perform an annual self-certification that includes a justification, clear identification of the threshold, and supporting documentation to allow for $50,000 as the micropurchase limit. Name of Contact Person: Person responsible for completing the corrective action plan is Nicole Mast, Director of Operations, nmast@flowerhill.institute. Projected Completion Date: December 31, 2023 Oversight: Contractor documentation will monitored annually to ensure compliance through the end of the current contract (currently March 2026).
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and compliance status.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.