EIN: 742361886
UEI: S4ELWK3JEK83
Data as of August 21, 2026
Management decision deadline — for entities that funded this organization
The FAC accepted this audit on June 10, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 10, 2026 (111 days from today).
What is a management decision? →During the audit, it was noted the Organization did not have a procurement process in place as required by the procurement standards set forth in 2 CFR Part 200 Subpart D for subcontractors. Cause: The Organization had not received funding in the previous years that adhered to strict compliance requirements as outlined in 2 CFR Part 200. Management is aware of the compliance requirement set forth in 2 CFR Part 200 and has implemented internal controls to comply with compliance requirements. Effect or potential effect: The Organization is not in compliance with the Subrecipient Obligations clause of the agreement and within the procurement standards set forth in 2 CFR Part 200 Subpart D.
Show full finding ▾Hide full finding ▴Criteria: NAMI Greater San Antonio, Inc. (the “Organization”) and Bexar County had an agreement dated September 4, 2024. Section 4.04 of the agreement stated the Organization must comply with 2 CFR Part 200 Subpart D, Procurement when expending federal funds. Condition: During the audit, it was noted the Organization did not have a procurement process in place as required by the procurement standards set forth in 2 CFR Part 200 Subpart D for subcontractors. Cause: The Organization had not received funding in the previous years that adhered to strict compliance requirements as outlined in 2 CFR Part 200. Management is aware of the compliance requirement set forth in 2 CFR Part 200 and has implemented internal controls to comply with compliance requirements. Effect or potential effect: The Organization is not in compliance with the Subrecipient Obligations clause of the agreement and within the procurement standards set forth in 2 CFR Part 200 Subpart D.
The Organization will implement an official procurement policy and set forth internal controls to follow the procedures set forth in 2 CFR Part 200 Subpart D.
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and compliance status.