VIXEN WATER SYSTEM, INC.

EIN: 721133535

UEI: GSA_MIGRATION

Data as of August 19, 2026

2
Audit Years
1
Total Findings
0
Repeat Findings

FY 2019-12-31

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on August 31, 2020. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 3, 2021, which was (1996 days ago).

What is a management decision? →
2019-003
Procurement & Suspension/Debarment
Condition

2019-003. Noncompliance with Federal Procurement Standards Criteria: Title 2 U. S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) requires that non-federal entities that expend federal funds to meet the general procurement standards in 2 CFR section 200.318. These standards include having written standards of conduct for employees and officials involved in awarding contracts to contractors. In addition, the USDA letter of conditions dated December 06, 2017, requires the water system to have a written conflict of interest policy. Condition: The Board of Directors of the water system did not adopt a written conflict of interest policy as required by the Uniform Guidance and the letter of conditions. Cause: Oversight. Effect: A water system official could have an undisclosed financial interest in a contract funded by a federal award. Recommendation: The Board of Directors of the water system should adopt a written conflict of interest policy that meets the requirements of 2 CFR section 200.318 and the letter of conditions. Management?s Response: The Vixen Board of Directors will approve a conflict of interest policy.

Corrective Action Plan

Finding No. 2019-003 Corrective Action Planned: The Vixen Board of Directors will approve a conflict of interest policy. Person Responsible for Corrective Action: Tommie Chatham, President of Vixen Water Anticipated Completion Date: Not later than the Board of Directors meeting date of September 17, 2020.

About Procurement and Suspension and Debarment →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.