Martinsville Community Unit School District C3

EIN: 376002602

UEI: EZFKGWAFMKE9

Data as of August 19, 2026

4
Audit Years
1
Total Findings
0
Repeat Findings

FY 2022-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on June 29, 2023. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by December 29, 2023, which was (965 days ago).

What is a management decision? →
2022-002
Equipment & Real Property
Condition

1. FINDING NUMBER: 2022- 002 2. THIS FINDING IS: X New Repeat from Prior year? Year originally reported? 3. Federal Program Name and Year: COVID 19: Education Stabilization Fund (2021 & 2022) 4. Project No.: 4998-E2 5. CFDA No.: 84.425D-COVID 19 6. Passed Through: Illinois State Board of Education 7. Federal Agency: Department of Education 8. Criteria or specific requirement (including statutory, regulatory, or other citation) Equipment and Real Property Management compliance requirements require that complete property records be maintained that include a description of the property, a serial number or other identification number, the source of funding of the property (including the federal award identification number), who holds title, the acquisition date, cost of the property, percentage of federal participation in the project costs for the federal award under which the property was acquired, the location, use and condition of the property and any ultimate disposition data including the date of disposal and the sales price of the property. (2 CFR section 200.313(d)(1) 9. Condition The District's property records did not include all equipment purchased with federal funds as per 2 CFR section 200.313(d)(1). 10. Questioned Costs None 11. Context The inventory of equipment is material to the program. 12. Effect The District is not in compliance with Equipment and Real Property Management compliance requirements. 13. Cause The District administrative staff does not maintain a complete list of all equipment purchased with federal funds. 14. Recommendation The District should assign an administrative employee with knowledge of applicable federal grant expenditures to maintain a complete list of property records that meets the requirements of 2 CFR section 200.313(d)(1). 15. Management's response Management will implement the auditor's recommendation for the year ended June 30, 2023.

Corrective Action Plan

11-012-003C-26 CORRECTIVE ACTION PLAN FOR CURRENT YEAR AUDIT FINDINGS Year Ending June 30, 2022 Corrective Action Plan Finding No.: 2022-_ 002__ Condition: The District's property records did not include all equipment purchased with federal funds as per 2 CFR section 200.313(d)(1) for equipment purchased with Education Stabilization Funding. Plan: The District will assign an administrative employee with knowledge of applicable federal grant expenditures to maintain a complete list of property records that meets the requirements of 2 CFR section 200.313(d)(1). Anticipated Date of Completion: 06/30/2023 Name of Contact Person: Jill Rogers Management Response: Management will implement the corrective action plan for the year ended June 30, 2023.

About Equipment and Real Property Management →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.