2023-003
Reporting
MATERIAL WEAKNESS
Condition

FINDING 2023-003 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): CY 2023 Compliance Requirement: Reporting Audit Findings: Material Weakness, Other Matters Condition and Context Recipients are required quarterly or annually to submit Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. The Town was classified as a Non-Entitlement Unit with a population below 250,000 residents that are allocated less than $10 million in COVID-19 - Coronavirus State and Local Fiscal Recovery Funds (SLFRF). As such, the Town's P&E report, covering the period from April 1, 2022 to March 31, 2023, was required to be submitted to the Treasury by April 30, 2023. The Town timely submitted one P&E report during the audit period; however, the report was submitted without a review or oversight process in place to prevent, or detect and correct, errors. As a result, errors in reporting were identified. The cumulative expenditures and current period expenditures reported were both incorrect. The Town did not have any expenditures prior to March 31, 2023; however, the Town reported the full amount received for the grant of $376,654 for both cumulative expenditures and current period expenditures. The lack of internal controls and noncompliance were isolated to the one annual P&E report. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 35.4(c) states in part: "Reporting and requests for other information. During the period of performance, recipients shall provide to the Secretary periodic reports providing detailed accounting of the uses of funds, . . ." Coronavirus State and Local Fiscal Recovery Funds Compliance and Reporting Guidance, page 10, states in part: ". . . 10. Reporting. All recipients of federal funds must complete financial, performance, and compliance reporting as required and outlined in Part 2 of this guidance. Expenditures may be reported on a cash or accrual basis, as long as the methodology is disclosed and consistently applied. Reporting must be consistent with the definition of expenditures pursuant to 2 CFR 200.1. Your organization should appropriately maintain accounting records for compiling and reporting accurate, compliant financial data, in accordance with appropriate accounting standards and principles. . . ." The Indiana State Board of Accounts (SBOA) is required under Indiana Code 5-11-1-27(e) to define the acceptable minimum level of internal control standards. To provide clarifying guidance, the State Examiner compiled the standards contained in the manual, Uniform Internal Control Standards for Indiana Political Subdivisions. All political subdivisions subject to audit by SBOA are expected to adhere to these standards. The standards include adequate control activities. According to this manual: "Control activities are the actions and tools established through policies and procedures that help to detect, prevent, or reduce the identified risks that interfere with the achievement of objectives. Detection activities are designed to identify unfavorable events in a timely manner whereas prevention activities are designed to deter the occurrence of an unfavorable event. Examples of these activities include reconciliations, authorizations, approval processes, performance reviews, and verification processes. An integral part of the control activity component is segregation of duties. . . . There is an expectation of segregation of duties. If compensating controls are necessary, documentation should exist to identify both the areas where segregation of duties are not feasible or practical and the compensating controls implemented to mitigate the risk. . . ." Cause A proper system of internal controls over P&E reports was not implemented by the management of the Town to ensure that complete and accurate information related to the SLFRF awards was provided to the Treasury. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the Town's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. The Town incorrectly reported the correct current and cumulative expenditures due to misunderstanding the line item requirement. Effect Without the proper implementation of an effectively designed system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As such, errors, as identified in the Condition and Context, occurred, and inaccurate information was provided to the Treasury. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the Town. In addition, not meeting the SLFRF reporting requirements increases the likelihood that the public will not have access to transparent and accurate information regarding expenditures of federal awards. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the Town design and implement a proper system of internal controls that would provide for segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place. Additionally, management should develop policies and procedures to ensure that the Town provides the Treasury with complete and accurate information for the P&E report. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2023-003 Finding Subject: COVID-19 – Coronavirus State and Local Fiscal Recovery Funds – Reporting Summary of Finding: The Project and Expenditure (P&E) report covering April 1, 2022, to March 31, 2023, was submitted without a review or oversight process in place to prevent or detect and correct errors. As a result, errors in reporting were identified. Contact Person Responsible for Corrective Action: Jennifer Pickett Contact Person Phone Number: 317-984-3512 jennifer.pickett@arcadia.in.gov Views of Responsible Officials: We concur with the finding. Description of Corrective Action Plan: When the Clerk-Treasurer goes to do the Project and Expenditure report next, she will have the Grant Administrator set with her to complete the form. After the form is completed and has no errors the Clerk Treasurer will print the report off and allow her Deputy Clerk Treasurer to review it. Anticipated Completion Date: This will be corrected in 2025 when the report must be submitted again.

About Reporting →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.