Montgomery County

EIN: 356000177

UEI: K73MRFRE2TH1

Data as of August 24, 2026

Montgomery County7 audit years10 findings4 repeat
7
Audit Years
10
Total Findings
4
Repeat Findings

FY 2024-12-31

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on September 17, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 17, 2026 (161 days ago).

What is a management decision? →
2024-002
Procurement & Suspension/Debarment
MATERIAL WEAKNESSREPEAT

FINDING 2024-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SWIF 221154-TEMPUR WATER Pass-Through Entity: Indiana Finance Authority Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2023-001. Condition and Context Prior to entering into subawards and covered transactions with federal award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to, contracts for goods or services awarded under a nonprocurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. Verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the U.S. Department of the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Covered transactions in the amount of $3,600,147 were made during the audit period to two vendors. For one of the two vendors, the County did not check the ELPS, collect a certification from the vendor, or add a clause in a contract with the vendor. Although the County established Ordinance 2023-11 dated August 14, 2023, requiring all public works contracts to contain a suspension and debarment clause, the contract with the vendor was entered into prior to the establishment of the ordinance. The contract was not amended nor was one of the other two methods for verification of the suspension and debarment status of the vendor performed. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.214 states: "Recipients and subrecipients are subject to the nonprocurement debarment and suspension regulations implementing Executive Orders 12549 and 12689, as well as 2 CFR part 180. The regulations in 2 CFR part 180 restrict making Federal awards, subawards, and contracts with certain parties that are debarred, suspended, or otherwise excluded from receiving or participating in Federal awards." 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A new policy was adopted to ensure compliance with suspension and debarment requirements after the County's 2023 audit. The new policy was not implemented for all applicable contracts entered into prior to the policy's enactment, and the alternative methods of verification were not performed to ensure compliance with suspension and debarment requirements. Effect Without proper implementation of an effectively designed system of internal controls, the County was unable to verify whether contractors and subrecipients were not suspended, debarred, or excluded. Any program funds the County used to pay contractors that have been suspended or debarred would be unallowable, and the funding agency could potentially recover them. Furthermore, noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls to ensure that the current policy in place was properly implemented for all beneficiaries that are paid $25,000 or more, all or in part with federal funds, to ensure they are not suspended, debarred, or otherwise excluded from participating in federal programs. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2024-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SWIF 221154-TEMPUR WATER Pass-Through Entity: Indiana Finance Authority Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2023-001. Condition and Context Prior to entering into subawards and covered transactions with federal award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to, contracts for goods or services awarded under a nonprocurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. Verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the U.S. Department of the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Covered transactions in the amount of $3,600,147 were made during the audit period to two vendors. For one of the two vendors, the County did not check the ELPS, collect a certification from the vendor, or add a clause in a contract with the vendor. Although the County established Ordinance 2023-11 dated August 14, 2023, requiring all public works contracts to contain a suspension and debarment clause, the contract with the vendor was entered into prior to the establishment of the ordinance. The contract was not amended nor was one of the other two methods for verification of the suspension and debarment status of the vendor performed. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.214 states: "Recipients and subrecipients are subject to the nonprocurement debarment and suspension regulations implementing Executive Orders 12549 and 12689, as well as 2 CFR part 180. The regulations in 2 CFR part 180 restrict making Federal awards, subawards, and contracts with certain parties that are debarred, suspended, or otherwise excluded from receiving or participating in Federal awards." 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A new policy was adopted to ensure compliance with suspension and debarment requirements after the County's 2023 audit. The new policy was not implemented for all applicable contracts entered into prior to the policy's enactment, and the alternative methods of verification were not performed to ensure compliance with suspension and debarment requirements. Effect Without proper implementation of an effectively designed system of internal controls, the County was unable to verify whether contractors and subrecipients were not suspended, debarred, or excluded. Any program funds the County used to pay contractors that have been suspended or debarred would be unallowable, and the funding agency could potentially recover them. Furthermore, noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls to ensure that the current policy in place was properly implemented for all beneficiaries that are paid $25,000 or more, all or in part with federal funds, to ensure they are not suspended, debarred, or otherwise excluded from participating in federal programs. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2024-002 (prior finding audit number 2023-001) Finding Subject: COVID-19 – Coronavirus State and Local Fiscal Recovery Funds – Suspension and Debarment Contact Person Responsible for Corrective Action: Mindy Byers, Auditor Contact Phone Number and Email Address: 765-364-6401 mindy.byers@montgomerycounty.in.gov Views of Responsible Officials: We concur with the finding. Description of Corrective Action Plan: A new policy was adopted after the previous audit to ensure proper language regarding suspension and debarment is included in every contract. Because the contracts are outside of Auditor control, the Auditor is requesting county management to get an amendment for the vendor in question, Indiana American Water. Anticipated Completion Date: 08/31/2025

Prior Finding References

2023-001

About Procurement and Suspension and Debarment →
2024-003
Reporting
MATERIAL WEAKNESSREPEAT

FINDING 2024-003 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Reporting Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2023-002. Condition and Context Recipients are required to submit quarterly or annual Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. The County was classified as a county with a population below 250,000 residents that received an allocation of less than $10 million in COVID-19 - State and Local Fiscal Recovery Funds (SLFRF). As such, the P&E report, covering the period from April 1, 2023 to March 31, 2024, was required to be submitted to the Treasury by April 30, 2024. The County submitted the P&E report by April 30, 2024, as required. Although one employee prepared the P&E report and another reviewed the entries, the system of internal controls was not effective in preventing, or detecting and correcting, errors. The County omitted expenditures that should have been reported and conversely reported expenditures that were erroneously charged to the grant fund but later moved to the correct fund. Additionally, the County reported obligations that were based on amounts budgeted for planned projects. Obligations are defined by a commitment to expend funds based on entering into contracts, subawards, or similar transactions that require payment. An allocation of funds in a budget or an intention to enter into a contract does not constitute an obligation. The errors identified included the following:  Current obligations were understated by $1,723,673.  Current expenditures were overstated by $29,960.  Cumulative obligations were overstated by $1,385,504.  Cumulative expenditures were understated by $12,000. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 35.4(c) states in part: "Reporting and requests for other information. During the period of performance, recipients shall provide to the Secretary or her delegate, as applicable, periodic reports providing detailed accounting of the uses of funds, . . ." Coronavirus State and Local Fiscal Recovery Funds Compliance and Reporting Guidance, page 10, states in part: ". . . 10. Reporting. All recipients of federal funds must complete financial, performance, and compliance reporting as required and outlined in Part 2 of this guidance. Expenditures may be reported on a cash or accrual basis, as long as the methodology is disclosed and consistently applied. Reporting must be consistent with the definition of expenditures pursuant to 2 CFR 200.1. Your organization should appropriately maintain accounting records for compiling and reporting accurate, compliant financial data, in accordance with appropriate accounting standards and principles. . . ." Cause Although a system of internal controls over the P&E report which included segregation of duties was designed by management, it did not ensure that the County provided the Treasury with complete and accurate information related to the SLFRF awards. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the P&E report submitted to the Treasury misstated obligations and expenditures. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. In addition, not meeting the SLFRF reporting requirements increases the likelihood that the public will not have access to transparent and accurate information regarding expenditures of federal awards. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the management of the County establish a system of internal controls and develop policies and procedures over the preparation and review of federal reports to ensure appropriate reviews, approval, and oversight take place. Additionally, management should develop policies and procedures to ensure that the County provides the Treasury with complete and accurate information for all reports. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2024-003 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Reporting Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2023-002. Condition and Context Recipients are required to submit quarterly or annual Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. The County was classified as a county with a population below 250,000 residents that received an allocation of less than $10 million in COVID-19 - State and Local Fiscal Recovery Funds (SLFRF). As such, the P&E report, covering the period from April 1, 2023 to March 31, 2024, was required to be submitted to the Treasury by April 30, 2024. The County submitted the P&E report by April 30, 2024, as required. Although one employee prepared the P&E report and another reviewed the entries, the system of internal controls was not effective in preventing, or detecting and correcting, errors. The County omitted expenditures that should have been reported and conversely reported expenditures that were erroneously charged to the grant fund but later moved to the correct fund. Additionally, the County reported obligations that were based on amounts budgeted for planned projects. Obligations are defined by a commitment to expend funds based on entering into contracts, subawards, or similar transactions that require payment. An allocation of funds in a budget or an intention to enter into a contract does not constitute an obligation. The errors identified included the following:  Current obligations were understated by $1,723,673.  Current expenditures were overstated by $29,960.  Cumulative obligations were overstated by $1,385,504.  Cumulative expenditures were understated by $12,000. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 35.4(c) states in part: "Reporting and requests for other information. During the period of performance, recipients shall provide to the Secretary or her delegate, as applicable, periodic reports providing detailed accounting of the uses of funds, . . ." Coronavirus State and Local Fiscal Recovery Funds Compliance and Reporting Guidance, page 10, states in part: ". . . 10. Reporting. All recipients of federal funds must complete financial, performance, and compliance reporting as required and outlined in Part 2 of this guidance. Expenditures may be reported on a cash or accrual basis, as long as the methodology is disclosed and consistently applied. Reporting must be consistent with the definition of expenditures pursuant to 2 CFR 200.1. Your organization should appropriately maintain accounting records for compiling and reporting accurate, compliant financial data, in accordance with appropriate accounting standards and principles. . . ." Cause Although a system of internal controls over the P&E report which included segregation of duties was designed by management, it did not ensure that the County provided the Treasury with complete and accurate information related to the SLFRF awards. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the P&E report submitted to the Treasury misstated obligations and expenditures. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. In addition, not meeting the SLFRF reporting requirements increases the likelihood that the public will not have access to transparent and accurate information regarding expenditures of federal awards. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the management of the County establish a system of internal controls and develop policies and procedures over the preparation and review of federal reports to ensure appropriate reviews, approval, and oversight take place. Additionally, management should develop policies and procedures to ensure that the County provides the Treasury with complete and accurate information for all reports. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2024-003 (prior finding audit number 2023-002) Finding Subject: COVID-19 – Coronavirus State and Local Fiscal Recovery Funds - Reporting Contact Person Responsible for Corrective Action: Mindy Byers, Auditor Contact Phone Number and Email Address: 765-364-6401 mindy.byers@montgomerycounty.in.gov Views of Responsible Officials: We concur with the finding. Description of Corrective Action Plan: One person will complete the report and another will sign off on a full review. Anticipated Completion Date: April 1, 2026 (based on due date of the next report)

Prior Finding References

2023-002

About Reporting →

FY 2023-12-31

FAC accepted this audit on September 30, 2024 — management decision was due March 30, 2025.

2023-001
Procurement & Suspension/Debarment
MATERIAL WEAKNESSREPEAT

FINDING 2023-001 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Numbers): SLFRP0752, TRSW222154-MACE STORMWATER Pass-Through Entity: Indiana Finance Authority Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion INDIANA STATE BOARD OF ACCOUNTS 13 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2022-004. Condition and Context The County elected to receive the standard revenue loss allowance, allowing the County to claim its total COVID-19 - Coronavirus State and Local Fiscal Recovery Funds (SLFRF) allocation of $7,446,707 as revenue loss to use for government services. As such, all SLFRF program funds were expended under the revenue loss eligible use category. The U.S Department of the Treasury (Treasury) determined that there are no subawards under this eligible use category, and that recipients' use of revenue loss funds would not give rise to subrecipient relationships given that there is no federal program or purpose to carry out in the case of the revenue loss portion of the award. Prior to entering into subawards and covered transactions with SLFRF award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to, contracts for goods and services awarded under a nonprocurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. The verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Upon inquiry of the County in order to review the procedures in place for verifying that an entity with which it plans to enter into a covered transaction is not suspended, debarred, or otherwise excluded, the County divulged that they established Ordinance 2023-11 dated August 14, 2023, indicating that all public works contracts were to include a suspension and debarment clause and were aware of the suspension and debarment requirements related to the SLFRF awards. There was only one covered transaction for goods or services that equaled or exceeded $25,000 paid from SLFRF funds during the audit period in the amount of $679,002. The County did not verify the vendors' suspension and debarment status prior to payment due to the County not having policies or procedures in place prior to entering into the contract with the vendor to verify that contractor was neither suspended nor debarred, or otherwise excluded or disqualified from participating in federal assistance programs or activities. The County reported that verification of suspension and debarment was attempted on the Sam.Gov website, but no results were returned. The lack of internal controls and noncompliance were systematic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." INDIANA STATE BOARD OF ACCOUNTS 14 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, vendors to whom payments equal to or in excess of $25,000 were not verified to be not suspended, debarred, or otherwise excluded. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure contractors and subrecipients, as appropriate, are not suspended, debarred, or otherwise excluded prior to entering into any contracts or subawards. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2023-001 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Numbers): SLFRP0752, TRSW222154-MACE STORMWATER Pass-Through Entity: Indiana Finance Authority Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion INDIANA STATE BOARD OF ACCOUNTS 13 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2022-004. Condition and Context The County elected to receive the standard revenue loss allowance, allowing the County to claim its total COVID-19 - Coronavirus State and Local Fiscal Recovery Funds (SLFRF) allocation of $7,446,707 as revenue loss to use for government services. As such, all SLFRF program funds were expended under the revenue loss eligible use category. The U.S Department of the Treasury (Treasury) determined that there are no subawards under this eligible use category, and that recipients' use of revenue loss funds would not give rise to subrecipient relationships given that there is no federal program or purpose to carry out in the case of the revenue loss portion of the award. Prior to entering into subawards and covered transactions with SLFRF award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to, contracts for goods and services awarded under a nonprocurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. The verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Upon inquiry of the County in order to review the procedures in place for verifying that an entity with which it plans to enter into a covered transaction is not suspended, debarred, or otherwise excluded, the County divulged that they established Ordinance 2023-11 dated August 14, 2023, indicating that all public works contracts were to include a suspension and debarment clause and were aware of the suspension and debarment requirements related to the SLFRF awards. There was only one covered transaction for goods or services that equaled or exceeded $25,000 paid from SLFRF funds during the audit period in the amount of $679,002. The County did not verify the vendors' suspension and debarment status prior to payment due to the County not having policies or procedures in place prior to entering into the contract with the vendor to verify that contractor was neither suspended nor debarred, or otherwise excluded or disqualified from participating in federal assistance programs or activities. The County reported that verification of suspension and debarment was attempted on the Sam.Gov website, but no results were returned. The lack of internal controls and noncompliance were systematic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." INDIANA STATE BOARD OF ACCOUNTS 14 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, vendors to whom payments equal to or in excess of $25,000 were not verified to be not suspended, debarred, or otherwise excluded. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure contractors and subrecipients, as appropriate, are not suspended, debarred, or otherwise excluded prior to entering into any contracts or subawards. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2023-001 Finding Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Suspension and Debarment Summary of Finding: Material Weakness, Modified Opinion Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Contact Email Address: mindy.byers@montgomerycounty.in.gov Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: Because the contracts are outside Auditor control, the Auditor has forwarded to county management to request a policy/internal control be created to be put in place. The County has adopted a Suspension and Debarment Policy in August 2023. A certification will be collected from the vendor in the current audit period. In addition, language regarding obtaining a certification that a vendor is not suspended or debarred has been added to the standard language in the contracts. Anticipated Completion Date: December 31, 2024

Prior Finding References

2022-004

About Procurement and Suspension and Debarment →
2023-002
Reporting
MATERIAL WEAKNESS

FINDING 2023-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Reporting Audit Finding: Material Weakness INDIANA STATE BOARD OF ACCOUNTS 15 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Condition and Context Recipients are required to submit quarterly or annually Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. The County was classified as a county with a population below 250,000 residents that received an allocation of less than $10 million in State and Local Fiscal Recovery Funds. As such, the P&E report, covering the period from April 1, 2022 to March 31, 2023, was required to be submitted to the Treasury by April 30, 2023. The County submitted the P&E report by April 30, 2023, as required; however, there were no internal controls in place that would likely be effective in preventing, or detecting and correcting, noncompliance related to the P&E report. The County Auditor prepared and submitted the report without an oversight or review process. The lack of internal controls was a systemic issue throughout the audit period. 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls over the P&E report was not designed by management of the County, which would include segregation of key functions to ensure the County provided the Treasury with complete and accurate information related to the SLFRF awards. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system may not have prevented or detected material noncompliance. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. In addition, not meeting the SLFRF reporting requirements increases the likelihood that the public will not have access to transparent and accurate information regarding expenditures of federal awards. INDIANA STATE BOARD OF ACCOUNTS 16 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls with review and oversight of the P&E report, including policies and procedures to ensure that the County provides the Treasury with complete and accurate information for the P&E report. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report. INDIANA STATE BOARD OF ACCOUNTS 17

Show full finding ▾
Full finding narrative

FINDING 2023-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Reporting Audit Finding: Material Weakness INDIANA STATE BOARD OF ACCOUNTS 15 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Condition and Context Recipients are required to submit quarterly or annually Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. The County was classified as a county with a population below 250,000 residents that received an allocation of less than $10 million in State and Local Fiscal Recovery Funds. As such, the P&E report, covering the period from April 1, 2022 to March 31, 2023, was required to be submitted to the Treasury by April 30, 2023. The County submitted the P&E report by April 30, 2023, as required; however, there were no internal controls in place that would likely be effective in preventing, or detecting and correcting, noncompliance related to the P&E report. The County Auditor prepared and submitted the report without an oversight or review process. The lack of internal controls was a systemic issue throughout the audit period. 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls over the P&E report was not designed by management of the County, which would include segregation of key functions to ensure the County provided the Treasury with complete and accurate information related to the SLFRF awards. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system may not have prevented or detected material noncompliance. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. In addition, not meeting the SLFRF reporting requirements increases the likelihood that the public will not have access to transparent and accurate information regarding expenditures of federal awards. INDIANA STATE BOARD OF ACCOUNTS 16 MONTGOMERY COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls with review and oversight of the P&E report, including policies and procedures to ensure that the County provides the Treasury with complete and accurate information for the P&E report. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report. INDIANA STATE BOARD OF ACCOUNTS 17

Corrective Action Plan

FINDING 2023-002 Finding Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Audit Finding: Material Weakness, Noncompliance Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Contact Email Address: mindy.byers@montgomerycounty.in.gov Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: The Auditor and her Chief Deputy completed the P&E report together. Moving forward, the Auditor will print the report and have the Chief Deputy sign off on the report prior to submission. Anticipated Completion Date: April 1, 2025. If applicable: Document reason issue will NOT be corrected within six months: The 2024 Project & Expenditure report is not due until April 1, 2025.

About Reporting →

FY 2022-12-31

FAC accepted this audit on August 14, 2023 — management decision was due February 14, 2024.

2022-003
Reporting
MATERIAL WEAKNESS

FINDING 2022-003 Subject: Homeland Security Grant Program - Reporting Federal Agency: Department of Homeland Security Federal Program: Homeland Security Grant Program Assistance Listings Number: 97.067 Federal Award Numbers and Years (or Other Identifying Numbers): 38519SHSP000000, 38521SHSP000000 Pass-Through Entity: Indiana Department of Homeland Security Compliance Requirement: Reporting Audit Finding: Material Weakness Condition and Context The County had not properly designed or implemented a system of internal controls, which would include appropriate segregation of duties, that would likely be effective in preventing, or detecting and correcting, material noncompliance. Recipients are required to complete and submit fiscal reports and reimbursement claims to the Indiana Department of Homeland Security. The County submitted the required reports during the audit period; however, a single employee prepared and submitted the fiscal reports and reimbursement claims without evidence of a review, or oversight, or approval process to prevent, or detect and correct, errors prior to submission. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2022-003 Subject: Homeland Security Grant Program - Reporting Federal Agency: Department of Homeland Security Federal Program: Homeland Security Grant Program Assistance Listings Number: 97.067 Federal Award Numbers and Years (or Other Identifying Numbers): 38519SHSP000000, 38521SHSP000000 Pass-Through Entity: Indiana Department of Homeland Security Compliance Requirement: Reporting Audit Finding: Material Weakness Condition and Context The County had not properly designed or implemented a system of internal controls, which would include appropriate segregation of duties, that would likely be effective in preventing, or detecting and correcting, material noncompliance. Recipients are required to complete and submit fiscal reports and reimbursement claims to the Indiana Department of Homeland Security. The County submitted the required reports during the audit period; however, a single employee prepared and submitted the fiscal reports and reimbursement claims without evidence of a review, or oversight, or approval process to prevent, or detect and correct, errors prior to submission. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2022-003 Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: Grant ended during audit period. Will discuss with departments about need for internal controls. Anticipated Completion Date: 09/2023

About Reporting →
2022-004
Procurement & Suspension/Debarment
MATERIAL WEAKNESSREPEAT

FINDING 2022-004 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Procurement and Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2021-003. Condition and Context The County elected to receive the standard revenue loss allowance, allowing the County to claim its total State and Local Fiscal Recovery Funds (SLFRF) allocation of $7,446,707 as revenue loss to use for government services. As such, all SLFRF program funds were expended under the revenue loss eligible use category. The U.S Department of the Treasury (Treasury) determined that there are no subawards under this eligible use category, and that recipients' use of revenue loss funds would not give rise to subrecipient relationships given that there is no federal program or purpose to carry out in the case of the revenue loss portion of the award. Prior to entering into subawards and covered transactions with SLFRF award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to contracts for goods and services awarded under a non-procurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. The verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Upon inquiry of the County in order to review the procedures in place for verifying that an entity with which it plans to enter into a covered transaction is not suspended, debarred, or otherwise excluded, the County divulged that they were unaware of the suspension and debarment requirements related to the SLFRF awards. There was only one covered transaction for goods or services that equaled or exceeded $25,000 paid from SLFRF funds during the audit period, in the amount of $122,698. The County did not verify the vendors' suspension and debarment status prior to payment due to the County not having any policies or procedures in place to verify that contractor was neither suspended nor debarred, or otherwise excluded or disqualified from participating in federal assistance programs or activities. The lack of internal controls and noncompliance were systematic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, vendors to whom payments equal to or in excess of $25,000 were not verified to be not suspended, debarred, or otherwise excluded. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure contractors and subrecipients, as appropriate, are not suspended, debarred, or otherwise excluded prior to entering into any contracts or subawards. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2022-004 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Procurement and Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Modified Opinion Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2021-003. Condition and Context The County elected to receive the standard revenue loss allowance, allowing the County to claim its total State and Local Fiscal Recovery Funds (SLFRF) allocation of $7,446,707 as revenue loss to use for government services. As such, all SLFRF program funds were expended under the revenue loss eligible use category. The U.S Department of the Treasury (Treasury) determined that there are no subawards under this eligible use category, and that recipients' use of revenue loss funds would not give rise to subrecipient relationships given that there is no federal program or purpose to carry out in the case of the revenue loss portion of the award. Prior to entering into subawards and covered transactions with SLFRF award funds, recipients are required to verify that such contractors and subrecipients are not suspended, debarred, or otherwise excluded. "Covered transactions" include, but are not limited to contracts for goods and services awarded under a non-procurement transaction (i.e., grant agreement) that are expected to equal or exceed $25,000. The verification is to be done by checking the Excluded Parties List System (EPLS), collecting a certification from that person, or adding a clause or condition to the covered transaction with that person. Due to the Treasury's determination that the revenue loss eligible use category does not give rise to subawards, the County was only required to comply with suspension and debarment requirements related to covered transactions. Upon inquiry of the County in order to review the procedures in place for verifying that an entity with which it plans to enter into a covered transaction is not suspended, debarred, or otherwise excluded, the County divulged that they were unaware of the suspension and debarment requirements related to the SLFRF awards. There was only one covered transaction for goods or services that equaled or exceeded $25,000 paid from SLFRF funds during the audit period, in the amount of $122,698. The County did not verify the vendors' suspension and debarment status prior to payment due to the County not having any policies or procedures in place to verify that contractor was neither suspended nor debarred, or otherwise excluded or disqualified from participating in federal assistance programs or activities. The lack of internal controls and noncompliance were systematic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 19.300 states: "When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified. You do this by: (a) Checking the EPLS; or (b) Collecting a certification from that person if allowed by this rule; or (c) Adding a clause or condition to the covered transaction with that person." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, vendors to whom payments equal to or in excess of $25,000 were not verified to be not suspended, debarred, or otherwise excluded. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure contractors and subrecipients, as appropriate, are not suspended, debarred, or otherwise excluded prior to entering into any contracts or subawards. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2022-004 Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: Suspension and Debarment Ordinance being presented to Board of Commissioners at 08/2023 meeting. Clause will be included in all contracts entered into by the County. Commissioners will review contracts to verify clause is included before approving contract. Anticipated Completion Date: 08/2023

Prior Finding References

2021-003

About Procurement and Suspension and Debarment →
2022-005
Reporting
MATERIAL WEAKNESS

FINDING 2022-005 Subject: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response - Reporting Federal Agency: Department of Health and Human Services Federal Program: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response Assistance Listings Number: 93.354 Federal Award Number and Year (or Other Identifying Number): 1NU90TP922179 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Reporting Audit Finding: Material Weakness Condition and Context The County had not properly designed or implemented a system of internal controls, which would include appropriate segregation of duties, that would likely be effective in preventing, or detecting and correcting, material noncompliance. Recipients are required to complete and submit initial and quarterly grant progress reports to the Indiana State Department of Health. The County submitted the required reports during the audit period; however, a single employee prepared and submitted the reports without evidence of a review or oversight, or approval process to prevent, or detect and correct, errors prior to submission. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2022-005 Subject: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response - Reporting Federal Agency: Department of Health and Human Services Federal Program: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response Assistance Listings Number: 93.354 Federal Award Number and Year (or Other Identifying Number): 1NU90TP922179 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Reporting Audit Finding: Material Weakness Condition and Context The County had not properly designed or implemented a system of internal controls, which would include appropriate segregation of duties, that would likely be effective in preventing, or detecting and correcting, material noncompliance. Recipients are required to complete and submit initial and quarterly grant progress reports to the Indiana State Department of Health. The County submitted the required reports during the audit period; however, a single employee prepared and submitted the reports without evidence of a review or oversight, or approval process to prevent, or detect and correct, errors prior to submission. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2022-005 Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: Health Department will continue to prepare required reports with a separate individual reviewing prior to submission. Anticipated Completion Date:12/2023

About Reporting →
2022-006
Period of Performance
MATERIAL WEAKNESSQUESTIONED COSTS

FINDING 2022-006 Subject: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response - Period of Performance Federal Agency: Department of Health and Human Services Federal Program: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response Assistance Listings Number: 93.354 Federal Award Number and Year (or Other Identifying Number): 1NU90TP922179 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Period of Performance Audit Findings: Material Weakness, Modified Opinion Condition and Context The County had not designed, nor implemented a system of internal controls to ensure grant funds were expended during the grant's period of performance. A grant's period of performance is the time frame during which the grant funds may be expended. The period of performance for the grant was identified in the grant agreement. The County received $220,000 in advance funding for the grant with a period of performance beginning July 1, 2022. The entirety of the grant funds were receipted into the County's Supp PH Workforce GRT 93.354 fund (grant fund); however, the County disbursed $36,150 from the grant fund prior to the start of the grant's period of performance. As the grant did not allow for expenditures prior to the beginning of the period performance and approval from the grantor for the costs was not obtained, the total $36,150 was considered questioned costs. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.1 states in part: ". . . Period of performance means the total estimated time interval between the start of an initial Federal award and the planned end date, which may include one or more funded portions, or budget periods. Identification of the period of performance in the Federal award per ? 200.211(b)(5) does not commit the awarding agency to fund the award beyond the currently approved budget period. . . ." 2 CFR 200.458 states: "Pre-award costs are those incurred prior to the effective date of the Federal award or subaward directly pursuant to the negotiation and in anticipation of the Federal award where such costs are necessary for efficient and timely performance of the scope of work. Such costs are allowable only to the extent that they would have been allowable if incurred after the date of the Federal award and only with the written approval of the Federal awarding agency. If charged to the award, these costs must be charged to the initial budget period of the award, unless otherwise specified by the Federal awarding agency or pass-through entity." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, expenses were paid outside of the period of performance. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs Questioned costs of $36,150 were identified as outlined in the Condition and Context. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure all expenditures are within the period of performance or appropriate approval is obtained for pre-award costs. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2022-006 Subject: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response - Period of Performance Federal Agency: Department of Health and Human Services Federal Program: COVID-19 - Public Health Emergency Response: Cooperative Agreement for Emergency Response: Public Health Crisis Response Assistance Listings Number: 93.354 Federal Award Number and Year (or Other Identifying Number): 1NU90TP922179 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Period of Performance Audit Findings: Material Weakness, Modified Opinion Condition and Context The County had not designed, nor implemented a system of internal controls to ensure grant funds were expended during the grant's period of performance. A grant's period of performance is the time frame during which the grant funds may be expended. The period of performance for the grant was identified in the grant agreement. The County received $220,000 in advance funding for the grant with a period of performance beginning July 1, 2022. The entirety of the grant funds were receipted into the County's Supp PH Workforce GRT 93.354 fund (grant fund); however, the County disbursed $36,150 from the grant fund prior to the start of the grant's period of performance. As the grant did not allow for expenditures prior to the beginning of the period performance and approval from the grantor for the costs was not obtained, the total $36,150 was considered questioned costs. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.1 states in part: ". . . Period of performance means the total estimated time interval between the start of an initial Federal award and the planned end date, which may include one or more funded portions, or budget periods. Identification of the period of performance in the Federal award per ? 200.211(b)(5) does not commit the awarding agency to fund the award beyond the currently approved budget period. . . ." 2 CFR 200.458 states: "Pre-award costs are those incurred prior to the effective date of the Federal award or subaward directly pursuant to the negotiation and in anticipation of the Federal award where such costs are necessary for efficient and timely performance of the scope of work. Such costs are allowable only to the extent that they would have been allowable if incurred after the date of the Federal award and only with the written approval of the Federal awarding agency. If charged to the award, these costs must be charged to the initial budget period of the award, unless otherwise specified by the Federal awarding agency or pass-through entity." Cause A proper system of internal controls was not designed by management of the County. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper implementation of an effectively designed system of internal controls, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As a result, expenses were paid outside of the period of performance. Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of the federal award could result in the loss of future federal funding to the County. Questioned Costs Questioned costs of $36,150 were identified as outlined in the Condition and Context. Recommendation We recommended that management of the County establish a proper system of internal controls and develop policies and procedures to ensure all expenditures are within the period of performance or appropriate approval is obtained for pre-award costs. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2022-006 Contact Person Responsible for Corrective Action: Mindy Byers Contact Phone Number: 765-364-6401 Views of Responsible Official: We concur with the finding. Description of Corrective Action Plan: ALN changed during middle of audit period. Will inquire mid-year with departments managing grants to see if any ALN changes. If so, new grant fund will be created. Anticipated Completion Date: 08/2023

About Period of Performance →

FY 2021-12-31

FAC accepted this audit on October 10, 2022 — management decision was due April 10, 2023.

2021-002
Period of Performance

FINDING 2021-002 Subject: COVID-19 - Coronavirus Relief Fund - Period of Performance Federal Agency: Department of the Treasury Federal Programs: COVID-19 - Coronavirus Relief Fund Assistance Listings Number: 21.019 Federal Award Number and Year (or Other Identifying Number): FY2021 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Period of Performance Audit Findings: Significant Deficiency, Other Matters Condition and Context An effective internal control system, which would include segregation of duties, was not in place at the County to ensure compliance with requirements related to the grant agreement and the Period of Performance compliance requirement. The County received a Coronavirus Relief Fund (Fund) grant through the Indiana State Department of Health to support COVID-19 testing at the local health department clinic. The CARES Act provides that payments from the Fund may only be used to cover costs that were incurred during the period that began March 1, 2020, and ended December 31, 2021 (covered period). In addition, a grant provided from the Fund must be used only to purchase (or reimburse a purchase of) goods or services for which receipt both is needed within the covered period and occurs within the covered period. During 2022, three expenditures were charged to the grant for services that occurred outside the covered period. Furthermore, as of August 31, 2022, the grant had remaining funds not yet expended. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 42 USC 801(d) states in part: ?. . . unit of local government shall use the funds provided under a payment made under this section to cover only those costs of the State, Tribal government, or unit of local government that? . . . (3) were incurred during the period that begins March 1, 2020 and ends on December 31, 2021.? Cause Management did not have an effective system of internal control in place to ensure compliance with the grant agreement and the Period of Performance compliance requirement. Effect The failure to establish an effective internal control system allowed noncompliance with the grant agreement and the Period of Performance compliance requirement. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the County's management establish a system of internal control to ensure compliance and to comply with the grant agreement and the Period of Performance compliance requirement. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2021-002 Subject: COVID-19 - Coronavirus Relief Fund - Period of Performance Federal Agency: Department of the Treasury Federal Programs: COVID-19 - Coronavirus Relief Fund Assistance Listings Number: 21.019 Federal Award Number and Year (or Other Identifying Number): FY2021 Pass-Through Entity: Indiana State Department of Health Compliance Requirement: Period of Performance Audit Findings: Significant Deficiency, Other Matters Condition and Context An effective internal control system, which would include segregation of duties, was not in place at the County to ensure compliance with requirements related to the grant agreement and the Period of Performance compliance requirement. The County received a Coronavirus Relief Fund (Fund) grant through the Indiana State Department of Health to support COVID-19 testing at the local health department clinic. The CARES Act provides that payments from the Fund may only be used to cover costs that were incurred during the period that began March 1, 2020, and ended December 31, 2021 (covered period). In addition, a grant provided from the Fund must be used only to purchase (or reimburse a purchase of) goods or services for which receipt both is needed within the covered period and occurs within the covered period. During 2022, three expenditures were charged to the grant for services that occurred outside the covered period. Furthermore, as of August 31, 2022, the grant had remaining funds not yet expended. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 42 USC 801(d) states in part: ?. . . unit of local government shall use the funds provided under a payment made under this section to cover only those costs of the State, Tribal government, or unit of local government that? . . . (3) were incurred during the period that begins March 1, 2020 and ends on December 31, 2021.? Cause Management did not have an effective system of internal control in place to ensure compliance with the grant agreement and the Period of Performance compliance requirement. Effect The failure to establish an effective internal control system allowed noncompliance with the grant agreement and the Period of Performance compliance requirement. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the County's management establish a system of internal control to ensure compliance and to comply with the grant agreement and the Period of Performance compliance requirement. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

Corrective Action Plan

FINDING 2021-002 (Auditor Assigned Reference Number) Contact Person Responsible for Corrective Action: Jennifer Andel Contact Phone Number: 765-364-6403 Views of Responsible Official: We concur with the finding ? there are unspent monies in this fund. Description of Corrective Action Plan: We will work with the Health Department to make sure all is claimed out of this fund as soon as possible. Anticipated Completion Date: 12/31/2022

About Period of Performance →
2021-003
Procurement & Suspension/Debarment
MATERIAL WEAKNESS

FINDING 2021-003 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds ? Procurement and Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Qualified Opinion Condition and Context The County had not designed nor implemented an effective internal control system over suspension and debarment procedures to ensure compliance with requirements related to the grant agreement and the Procurement and Suspension and Debarment compliance requirement. ? The County did not have procedures in place to verify vendors were not suspended, debarred, or otherwise excluded from or ineligible for participation in federal assistance programs or activities. The County did not ensure the one vendor contract entered into during the audit period contained a suspension and debarment clause or included a certification from the vendor, nor did the County check the EPLS. The lack of internal controls and noncompliance were isolated to the one contract. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 19.300 states: ?When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified.? You do this by: ? (a)??Checking the EPLS; or ? (b)??Collecting a certification from that person if allowed by this rule; or ? (c)??Adding a clause or condition to the covered transaction with that person.? Cause Management did not have an effective system of internal control in place to ensure compliance with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Effect The failure to establish an effective system of internal control allowed noncompliance with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the County's management establish a system of internal control to ensure compliance and to compy with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan which is part of this report.

Show full finding ▾
Full finding narrative

FINDING 2021-003 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds ? Procurement and Suspension and Debarment Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): SLFRP0752 Compliance Requirement: Procurement and Suspension and Debarment Audit Findings: Material Weakness, Qualified Opinion Condition and Context The County had not designed nor implemented an effective internal control system over suspension and debarment procedures to ensure compliance with requirements related to the grant agreement and the Procurement and Suspension and Debarment compliance requirement. ? The County did not have procedures in place to verify vendors were not suspended, debarred, or otherwise excluded from or ineligible for participation in federal assistance programs or activities. The County did not ensure the one vendor contract entered into during the audit period contained a suspension and debarment clause or included a certification from the vendor, nor did the County check the EPLS. The lack of internal controls and noncompliance were isolated to the one contract. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 31 CFR 19.300 states: ?When you enter into a covered transaction with another person at the next lower tier, you must verify that the person with whom you intend to do business is not excluded or disqualified.? You do this by: ? (a)??Checking the EPLS; or ? (b)??Collecting a certification from that person if allowed by this rule; or ? (c)??Adding a clause or condition to the covered transaction with that person.? Cause Management did not have an effective system of internal control in place to ensure compliance with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Effect The failure to establish an effective system of internal control allowed noncompliance with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the County's management establish a system of internal control to ensure compliance and to compy with the grant agreement and the Procurement and Suspension and Debarment compliance requirement. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan which is part of this report.

Corrective Action Plan

FINDING 2021-003 (Auditor Assigned Reference Number) Contact Person Responsible for Corrective Action: Jennifer Andel Contact Phone Number: 765-364-6403 Views of Responsible Official: We concur with the finding ? I do not have documentation that verifies that vendors using SLFR funds were not suspended, debarred or otherwise excluded or ineligible from federal programs. Jennifer Andel Montgomery County Auditor 1580 Constitution Row, Suite A Crawfordsville, Indiana 47933 Phone: 765-364-6400 Fax: 765-364-6404 Email: auditor@montgomerycounty.in.gov Description of Corrective Action Plan: We will work with attorneys and vendors to gather that information. Anticipated Completion Date: 12/31/2023

About Procurement and Suspension and Debarment →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →