MOUNTAIN AREA REGIONAL TRANSIT AUTHORITY

EIN: 330695718

UEI: ENE9GSYQXMD9

Data as of August 19, 2026

6
Audit Years
7
Total Findings
1
Repeat Findings

FY 2025-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 2, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 2, 2026 (13 days from today).

What is a management decision? →
2025-001
Cost Allowability
Condition

SA 2025-001: Allowable Costs – Non-Payroll Assistance Listing Number: 20.509 Federal Program/Cluster Name: Formula Grants for Rural Areas and Tribal Transit Federal Agency: U.S. Department of Transportation – Federal Transit Administration Federal Award Number: 64BA24-02507/64CA17-02442/64HC22-02180/64RO21-01648/64TO21-01865/64MO21-01910/64HC21-01500 Federal Award Year: July 1, 2024 to June 30, 2025 Compliance Requirement Allowable Costs Criteria Except where otherwise authorized by statute, cost must meet the following general criteria in order to be allowable under federal awards; 1. Be necessary and reasonable for the performance of the federal award and be allocable thereto under the principles in 2 CFR Part 200, Subpart E. 2. Conform to any limitations or exclusions set forth in 2 CFR Part 200, Subpart E or in the federal award as to types or amount of cost items. 3. Be consistent with policies and procedures that apply uniformly to both federally financed and other activities of the non-federal entity. 4. Be accorded consistent treatment. A cost may not be assigned to a federal award as a direct cost if any other cost incurred for the same purpose in like circumstances has been allocated to the federal award as an indirect cost. 5. Be determined in accordance with generally accepted accounting principles (GAAP), except for state and local governments and Indian tribes only as otherwise provided for in 2 CFR Part 200. 6. Not be included as a cost or used to meet cost-sharing or matching requirements of any other federally financed program in either the current or a prior period. 7. Be adequately documented. Condition During the audit of non-payroll expenses charged to the program, an invoice dated May 1, 2025 was approved by the Director of Operations & Maintenance during the General Manager’s absence. The related purchase order was subsequently signed by the General Manager on June 10, 2025, after the invoice had already been received and approved. The procurement policy does not specify the required timing of purchase order approval relative to invoice receipt or approval. Cause The procurement policy lacks clear guidance on the timing of purchase order authorization. The Director of Operations & Maintenance approved the invoice to avoid delays, but the purchase order was not signed until the General Manager’s return. Effect This practice increases the risk of: • Commitments are being made without proper prior authorization. • Noncompliance with federal procurement standards requiring documented procedures that ensure approvals before obligations are incurred. • Potential questioned costs if federal funds were used for expenditures not properly authorized in advance. Questioned Costs None Repeat Findings No Recommendation MARTA should revise the procurement policy to explicitly require purchase order approval prior to invoice receipt or payment. Establish a clear delegation of authority for situations when the General Manager is absent, ensuring that approvals are documented and consistent with federal requirements. Views of Responsible Officials and Planned Corrective Action MARTA recognizes the importance of ensuring all expenses are approved before they are incurred. To address this finding, MARTA is updating its internal procurement rules to clearly state that a purchase order must be signed prior to ordering any items or initiating any services. This measure will prevent the receipt of invoices for costs that have not been officially authorized. Additionally, MARTA is creating a formal backup approval plan. Under this plan, if the General Manager is unavailable, another designated leader will have the documented authority to approve purchases immediately, eliminating the need to wait for the General Manager’s return to complete the necessary paperwork. Finally, MARTA’s finance team will implement a new check-and-balance step in the payment process. Moving forward, the team will verify that the date on the approved purchase order comes before the date on the vendor's invoice. If the dates are out of sequence, the payment will be flagged for review. In addition, MARTA will conduct a training session for all department heads to reinforce that verbal orders are not permitted and that written authorization must always be obtained first. This plan is designed to ensure full compliance with federal grant requirements and prevent any future delays in the approval process. Personnel responsible: Sandra Benson, General Manager Anticipated completion date: October 2026

Corrective Action Plan

Corrective Actions Taken or Planned: MARTA recognizes the importance of ensuring all expenses are approved before they are incurred. To address this finding, MARTA is updating its internal procurement rules to clearly state that a purchase order must be signed prior to ordering any items or initiating any services. This measure will prevent the receipt of invoices for costs that have not been officially authorized. Additionally, MARTA is creating a formal backup approval plan. Under this plan, if the General Manager is unavailable, another designated leader will have the documented authority to approve purchases immediately, eliminating the need to wait for the General Manager’s return to complete the necessary paperwork. Finally, MARTA’s finance team will implement a new check-and-balance step in the payment process. Moving forward, the team will verify that the date on the approved purchase order comes before the date on the vendor's invoice. If the dates are out of sequence, the payment will be flagged for review. In addition, MARTA will conduct a training session for all department heads to reinforce that verbal orders are not permitted and that written authorization must always be obtained first. This plan is designed to ensure full compliance with federal grant requirements and prevent any future delays in the approval process. Personnel responsible: Sandra Benson, General Manager Anticipated completion date: October 2026

About Allowable Costs / Cost Principles →
2025-002
Other
REPEAT
Condition

SA 2025-002: Develop Written Policies and Procedures Assistance Listing Number: 20.509 Federal Program/Cluster Name: Formula Grants for Rural Areas and Tribal Transit Federal Agency: U.S. Department of Transportation – Federal Transit Administration Federal Award Number: 64BA24-02507/64CA17-02442/64HC22-02180/64RO21-01648/64TO21-01865/64MO21-01910/64HC21-01500 Federal Award Year: July 1, 2024 to June 30, 2025 Compliance Requirement Others Criteria 2 CFR 200.303 requires nonfederal entities to establish and maintain effective internal control over federal awards to provide reasonable assurance that organizations who manage the federal award: • Understand and comply with the federal statutes, regulations, and terms and conditions of the award; • Evaluate and monitor compliance; • Take prompt action when instances of noncompliance is identified. These internal controls should be in compliance with guidance in Standards for Internal Control in the Federal Government, issued by the Comptroller General of the United States, or the Internal Control Integrated Framework, issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). Additionally, the Uniform Guidance requires non-federal entities to develop written procedures related to the following areas: 1. Cash Management 2 CFR 200.302(b)(6) states that the financial management system of each non-Federal entity must provide for the written procedures to implement the requirements of 2 CFR 200.305 Federal Payment. 2. Equipment Management Requirements Non-federal entities other than states must follow 2 CFR sections 200.313(c) through (e). Condition MARTA does not have comprehensive written policies and procedures concerning the following key compliance areas which are required by the Uniform Guidance: Cash Management MARTA does not have written procedures to implement the requirements of 2 CFR 200.305 Federal Payment. Equipment and Real Property Management MARTA has an Asset Inventory Policy and Procedures, however, it does not clearly define the policies and procedures that are in place for the use, management and disposition of equipment acquired under a Federal award in accordance with 2 CFR sections 200.313(c) through (e). Cause MARTA’s reliance on informal business practices leads to inconsistencies in its internal controls. Effect The absence of formal policies and procedures in the key compliance areas could result in non-compliance with federal regulations, which may lead to unnecessary sanctions. Additionally, without formal written policies and procedures, it is difficult to ensure consistent practices across the organization. Questioned Costs None Repeat Findings Yes, see the Summary Schedule of Prior Year Audit Findings, SA 2024‑001. The Cash Management and Equipment and Real Property Management policies have not been updated since last year’s audit. Recommendation MARTA should develop and implement formal written policies and procedures for the specific areas required by the Uniform Guidance. These policies and procedures must clearly delineate the requirements of Uniform Guidance. Personnel responsible for these areas should receive adequate training and apply the policies effectively. Regular reviews should be conducted to update the policies and procedures as needed. Views of Responsible Officials and Planned Corrective Action MARTA has grown substantially in the last several years. This progress includes identifying areas that need to be updated or developing new processes and documentation. MARTA has an Asset Inventory Policy and Procedures in which the purpose is to ensure that fixed assets are properly accounted for, identified, and tracked. MARTA also has Cash Handling Policy and Procedures which addresses safeguarding public funds and maximizing the available resources. This is designed to reduce the risks associated with the collection, receipts storage and reporting of cash transactions and to safeguard and maintain the security and integrity of MARTA's fiscal assets. MARTA will review and update these policies and/or create new policies to make sure that they are compliant with the Uniform Guidance. Personnel responsible: Sandy Benson, General Manager Anticipated completion date: October 2026

Corrective Action Plan

Corrective Actions Taken or Planned: MARTA has grown substantially in the last several years. This progress includes identifying areas that need to be updated or developing new processes and documentation. MARTA has an Asset Inventory Policy and Procedures in which the purpose is to ensure that fixed assets are properly accounted for, identified, and tracked. MARTA also has Cash Handling Policy and Procedures which addresses safeguarding public funds and maximizing the available resources. This is designed to reduce the risks associated with the collection, receipts storage and reporting of cash transactions and to safeguard and maintain the security and integrity of MARTA's fiscal assets. MARTA will review and update these policies and/or create new policies to make sure that they are compliant with the Uniform Guidance. Personnel responsible: Sandy Benson, General Manager Anticipated completion date: October 2026

Prior Finding References

2024-001

About Other →

FY 2024-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 31, 2025. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 1, 2025, which was (323 days ago).

What is a management decision? →
2024-001
Other
Condition

Develop Written Policies and Procedures Criteria: 2 CFR 200.303 requires nonfederal entities to establish and maintain effective internal control over federal awards to provide reasonable assurance that organizations who manage the federal award: • Understand and comply with the federal statutes, regulations, and terms and conditions of the award; • Evaluate and monitor compliance; • Take prompt action when instances of noncompliance is identified. These internal controls should be in compliance with guidance in Standards for Internal Control in the Federal Government, issued by the Comptroller General of the United States, or the Internal Control Integrated Framework, issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). Additionally, the Uniform Guidance requires non-federal entities to develop written procedures related to the following areas: 1. Cash Management 2 CFR 200.302(b)(6) states that the financial management system of each non-Federal entity must provide for the written procedures to implement the requirements of 2 CFR 200.305 Federal Payment. 2. Equipment Management Requirements Non-federal entities other than states must follow 2 CFR sections 200.313(c) through (e). In addition, the organizations should ensure that existing written procedures are in compliance with: a. General Procurement Standards 2 CFR 200.318 to 200.327 discusses that contracts must be established and managed in accordance with the procurement requirements in 2 CFR Part 200. Grantees must have written procurement policies and procedures that demonstrate a fair and reliable process, with standards of conduct addressing conflicts of interest, for obtaining grant-funded goods and services. Condition MARTA does not have comprehensive written policies and procedures concerning the following key compliance areas which are required by the Uniform Guidance: Equipment and Real Property Management MARTA has an Asset Inventory Policy and Procedures, however, it does not clearly define the policies and procedures that are in place for the use, management and disposition of equipment acquired under a Federal award in accordance with 2 CFR sections 200.313(c) through (e). Cash Management MARTA does not have written procedures to implement the requirements of 2 CFR 200.305 Federal Payment. Procurement, Suspension and Debarment MARTA has a Procurement policy, however, documented procedures are not well-defined regarding the purchase process for different types of procurement, obtaining quotations, bidding, and procedures for verifying that an entity with which it plans to enter into a covered transaction is not debarred, suspended, or otherwise excluded. Cause MARTA’s reliance on informal business practices leads to inconsistencies in its internal controls. Effect The absence of formal policies and procedures in the key compliance areas could result in non-compliance with federal regulations, which may lead to unnecessary sanctions. Additionally, without formal written policies and procedures, it is difficult to ensure consistent practices across the organization. Questioned Costs None Recommendation MARTA should develop and implement formal written policies and procedures for the specific areas required by the Uniform Guidance. These policies and procedures must clearly delineate the requirements of the Uniform Guidance. Personnel responsible for these areas should receive adequate training and apply the policies effectively. Regular reviews should be conducted to update the policies and procedures as needed. Views of Responsible Officials and Planned Corrective Action MARTA has grown substantially in the last several years. This progress includes identifying areas that we need to update or to develop new processes and documentation. MARTA has an Asset Inventory Policy and Procedures in which the purpose is to ensure that fixed assets are properly accounted for, identified, and tracked. MARTA also has Cash Handling Policy and Procedures which addresses safeguarding public funds and maximizing resources available. This is designed to reduce the risks associated with the collection, receipts storage and reporting of cash transactions and to safeguard and maintain the security and integrity of MARTA's fiscal assets. MARTA is in the process of updating the Procurement Policy. MARTA will review and update these policies and/or create new policies to make sure that they are compliant with the Uniform Guidance. The updated or newly created policies will be brought to the October 2025 Board of Directors meeting for Board review or approval. Personnel responsible: Sandy Benson, General Manager Anticipated completion date: October 2025

Corrective Action Plan

Identifying Number: SA 2024-001 Description of Finding: MARTA does not have comprehensive written policies and procedures concerning the following key compliance areas which are required by the Uniform Guidance: Equipment and Real Property Management MARTA has an Asset Inventory Policy and Procedures, however, it does not clearly define the policies and procedures that are in place for the use, management and disposition of equipment acquired under a Federal award in accordance with 2 CFR sections 200.313(c) through (e). Cash Management MARTA does not have written procedures to implement the requirements of 2 CFR 200.305 Federal Payment. Procurement, Suspension and Debarment MARTA has a Procurement policy, however, documented procedures are not well- defined regarding the purchase process for different types of procurement, obtaining quotations, bidding, and procedures for verifying that an entity with which it plans to enter into a covered transaction is not debarred, suspended, or otherwise excluded. Corrective Actions Taken or Planned: We have an Asset Inventory Policy and Procedures in which the purpose is to ensure that fixed assets are properly accounted for, identified, and tracked. We also have Cash Handling Policy and Procedures which addresses safeguarding public funds and maximizing resources available. This is designed to reduce the risks associated with the collection, receipts storage and reporting of cash transactions and to safeguard and maintain the security and integrity of MARTA's fiscal assets. We are in the process of updating our Procurement Policy. We will review and update these policies and/or create new policies to make sure we are compliant with the Uniform Guidance. The updated or newly created policies will be brought to our October 2025 Board of Directors meeting for Board review or approval. Personnel responsible for implementation: Sean Gillingham, Finance Manager Anticipated completion date: October 2025

About Other →
2024-002
Procurement & Suspension/Debarment
Condition

Procurement, Suspension and Debarment Criteria Procurement Non-federal entities other than states, including those operating federal programs as subrecipients of states, must follow specific procurement standards set out in 2 CFR sections 200.317 through 200.327, which includes documenting the procurement methods used for vendor selection. These procedures are designed to ensure fair competition, cost-effectiveness, and federal requirements. These procurement standards require, among other provisions, that a non-federal entity must: 1. Meet the general procurement standards in 2 CFR Section 200.318, which include oversight of contractors’ performance, maintaining written standards of conduct for employees involved in contracting, awarding contracts only to reliable contractors, and maintaining records to document the history of procurement. 2. Conduct all procurement transactions for the acquisition of property or services under a federal award in a manner providing full and open competition consistent with the standards of 2 CFR section 200.320. 3. Use documented procurement procedures, consistent with the standards of 2 CFR 200.317 to 320. 2 CFR 200.320 enumerates below the different procurement methods that a non-federal entity should use: a) The micro-purchase and small purchase methods only for procurements that meet the applicable criteria under 2 CFR sections 200.320(a) (1) and (2). Under the micro-purchase method, the aggregate dollar amount does not exceed $50,000. b) Small purchase procedures are used for purchases that exceed the micro-purchase amount but do not exceed the simplified acquisition threshold. The non-Federal entity is responsible for determining an appropriate simplified acquisition threshold based on internal controls, an evaluation of risk and its documented procurement procedures which must not exceed the threshold established in the FAR. When applicable, a lower simplified acquisition threshold used by the non-Federal entity must be authorized or not prohibited under State, local, or tribal laws or regulations. c) Micro-purchases may be awarded without soliciting competitive quotations if the non-federal entity considers the price to be reasonable (2 CFR section 200.320(a)). If small purchase procedures are used, price or rate quotations must be obtained from an adequate number of qualified sources (2 CFR section 200.320(b)). 4. For acquisitions exceeding the simplified acquisition threshold, the non-federal entity must use one of the following procurement methods: the sealed bid method if the acquisition meets the criteria in 2 CFR section 200.320(b) (1); the competitive proposals method under the conditions specified in 2 CFR section 200.320(b) (2); or the noncompetitive proposals method (i.e., solicit a proposal from only one source) but only when one or more of four circumstances are met, in accordance with 2 CFR section 200.320(c)). 5. Perform a cost or price analysis in connection with every procurement action in excess of the simplified acquisition threshold, including contract modifications (2 CFR section 200.323(a)). The cost plus a percentage of cost and percentage of construction cost methods of contracting must not be used (2 CFR section 200.323(b)). 6. Ensure that every purchase order or other contract includes applicable provisions required by 2 CFR section 200.326. These provisions are described in Appendix II to 2 CFR Part 200, “Contract Provisions for Non-Federal Entity Contracts Under Federal Awards.” Suspension and Debarment Non-federal entities are prohibited from contracting with or making subawards under covered transactions to parties that are suspended or debarred. “Covered transactions” include contracts for goods and services awarded under a non-procurement transaction (e.g., grant or cooperative agreement) that are expected to equal or exceed $25,000 or meet certain other criteria as specified in 2 CFR section 180.220. All non-procurement transactions entered into by a pass-through entity (i.e., subawards to subrecipients), irrespective of award amount, are considered covered transactions, unless they are exempt as provided in 2 CFR section 180.215. When a non-federal entity enters into a covered transaction with an entity at a lower tier, the non-federal entity must verify that the entity, as defined in 2 CFR section 180.995 and agency adopting regulations, is not suspended or debarred or otherwise excluded from participating in the transaction. This verification may be accomplished by (1) checking the System for Award Management (SAM) Exclusions maintained by the General Services Administration (GSA) and available at SAM.gov Home (click on Search Record, then click on Advanced Search-Exclusions) (Note: The OMB guidance at 2 CFR Part 180 and agency implementing regulations still refer to the SAM Exclusions as the Excluded Parties List System (EPLS)), (2) collecting a certification from the entity, or (3) adding a clause or condition to the covered transaction with that entity (2 CFR section 180.300). Condition During our audit, MARTA was unable to provide purchase order documentation or contract for eight samples that are above $500. Per current procurement policy, “Purchases of supplies, services, and equipment costing more than five hundred ($500) shall be made by purchase order, unless authorized by a signed contract or Mountain Transit Board Approval”. During our audit, MARTA was unable to provide supporting documentation to demonstrate that the required price or rate quotations for those purchases or contracts with contract amounts above $10,000 were obtained from an adequate number of qualified sources and maintained the documentation to support its conclusion. These were noted for two samples tested. The expenditure paid ranged from $10,000 to $36,000 in 2024. During our audit, MARTA was unable to provide supporting documentation to demonstrate that the process of verifying if vendors are not suspended or debarred was performed on two vendors tested. The expenditure paid to these vendors ranged from $109,000 to $647,000 in 2024. Cause MARTA did not follow its existing purchasing policy and procedures, and lack of procedures in maintaining appropriate records of vendor selection and compliance with procurement standards. Effect The absence of procurement documentation raises the risk of non-compliance with federal regulations, which could lead to potential disallowances or unnecessary sanctions. Questioned Costs None Recommendation MARTA should strengthen its internal controls over procurement by ensuring that all procurement activities, particularly significant expenditures, are properly documented. This includes retaining evidence that procurement methods required by the Uniform Guidance were followed, such as bids, contracts, or justifications for sole-source vendors. MARTA should also conduct training for staff involved in procurement to ensure awareness and adherence to the policies. Regular internal audits may be implemented to verify compliance with procurement procedures. Views of Responsible Officials and Planned Corrective Action MARTA is in the process of updating the Procurement Policy. MARTA will ensure that updated policies and procedures will be implemented to address compliance and documentation requirements for small and micro-purchases, sole-source, and informal processes. The updated Procurement Policy will be brought to the October 2025 Board of Directors meeting for Board review or approval. Personnel responsible: Sandy Benson, General Manager Anticipated completion date: October 2025

Corrective Action Plan

Identifying Number: SA 2024-002 Description of Finding: During the audit, MARTA was unable to provide purchase order documentation or contract for eight samples that are above $500. Per current procurement policy, "Purchases of supplies, services, and equipment costing more than five hundred ($500) shall be made by purchase order, unless authorized by a signed contract or Mountain Transit Board Approval". During the audit, MARTA was unable to provide supporting documentation to demonstrate that the required price or rate quotations for those purchases or contracts with contract amounts above $10,000 were obtained from an adequate number of qualified sources and maintained the documentation to support its conclusion. These were noted for two samples tested. The expenditure paid ranged from $10,000 to $36,000 in 2024. During the audit, MARTA was unable to provide supporting documentation to demonstrate that the process of verifying if vendors are not suspended or debarred were performed on two vendors tested. The expenditure paid to these vendors ranged from $109,000 to $647,000 in 2024. Corrective Actions Taken or Planned: We are in the process of updating our Procurement Policy. We will ensure that we follow these updated policies and procedures to address compliance and documentation requirements for small and micro-purchases, sole-source, and informal processes. The updated Procurement Policy will be brought to our October 2025 Board of Directors meeting for Board review or approval. Personnel responsible for implementation: Sean Gillingham, Finance Manager Anticipated completion date: October 2025

About Procurement and Suspension and Debarment →
2024-003
Cost Allowability
Condition

Allowable costs – Payroll Criteria Except where otherwise authorized by statute, cost must meet the following general criteria in order to be allowable under federal awards; 1. Be necessary and reasonable for the performance of the federal award and be allocable thereto under the principles in 2 CFR Part 200, Subpart E. 2. Conform to any limitations or exclusions set forth in 2 CFR Part 200, Subpart E or in the federal award as to types or amount of cost items. 3. Be consistent with policies and procedures that apply uniformly to both federally financed and other activities of the non-federal entity. 4. Be accorded consistent treatment. A cost may not be assigned to a federal award as a direct cost if any other cost incurred for the same purpose in like circumstances has been allocated to the federal award as an indirect cost. 5. Be determined in accordance with generally accepted accounting principles (GAAP), except for state and local governments and Indian tribes only as otherwise provided for in 2 CFR Part 200. 6. Not be included as a cost or used to meet cost-sharing or matching requirements of any other federally financed program in either the current or a prior period. 7. Be adequately documented. Condition During the audit of payroll expenses charged to the program, it was noted that four samples have Personnel Action Forms (PAF) without the signature of the General Manager. Per current policies and procedures, for pay rate changes, a PAF should be created by the HR Manager and signed by the General Manager. Additionally, MARTA was unable to provide PAF for four samples. Cause The PAFs without final signature were not submitted to the General Manager. There was also difficulty in finding the missing PAFs which might be due to a lack of proper file management. Effect The absence of approval and adequate documentation raises the risk of non-compliance with federal regulations, which could lead to potential disallowances of costs. Questioned Costs None Recommendation MARTA should strengthen its internal controls over the payroll process by ensuring that all PAFs are reviewed for accuracy and properly approved. MARTA should ensure that PAF and timecards are adequately documented and filed. Views of Responsible Officials and Planned Corrective Action The HR Manager will review the procedures for processing PAF, communicate more effectively to close the loop on paperwork process, and confirm authorized signatures. The HR Manager will review all files for completed PAF forms and practice better diligence going forward in maintaining all documentation in personnel files. Personnel responsible: Jacob Phillips, HR Manager Anticipated completion date: Effective immediately

Corrective Action Plan

Identifying Number: SA 2024-003 Description of Finding: During the audit of payroll expense testing, it was noted that five samples have Personnel Action Forms (PAF) without the signature of the General Manager. In addition, one of those five samples has a variance between the pay rate per PAF and pay rate per payroll register. Per current policies and procedures, for pay rate changes, a PAF should be created by the HR Manager and signed by the General Manager. Additionally, MARTA was unable to provide PAF for four samples. Corrective Actions Taken or Planned: 1. We will review our procedures on processing PAF, communicate more effectively to close loop on paperwork process, and confirm authorized signatures. 2. We will review all files for completed PAF forms and practice better diligence going forward in maintaining all documentation in personnel files. Personnel responsible for implementation: Jacob Phillips, HR Manager Anticipated completion date: Effective immediately

About Allowable Costs / Cost Principles →

FY 2021-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on September 29, 2022. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 29, 2023, which was (1240 days ago).

What is a management decision? →
2021-003
Other
MATERIAL WEAKNESS
Condition

Program: Formula Grants for Rural Areas, Congestion Mitigation and Air Quality Improvement Program Federal Financial Assistance Number: 20.509 Federal Grantor: United States Department of Transportation ? Federal Transit Administration Passed Through: State of California Department of Transportation Award No. and Year: 64HC19-00883 and 2020 Compliance Requirement: Other Material Weakness in Internal Control over Compliance Criteria: Management is responsible for the preparation of a schedule of expenditures of federal awards for the period covered by their financial statements which must include the total federal awards expended as determined in accordance with 2 CFR Section 200.502 Condition: During the audit, it was noted that costs in the amount of $112,752 related to the Formula Grants for Rural Areas, Congestion Mitigation and Air Quality Improvement Program were not included on the schedule of expenditures of federal awards provided by management. Cause: MARTA?s internal controls did not allow for the proper preparation of the schedule of expenditures of federal awards. Effect: The schedule of expenditures of federal awards required a material adjustment to properly reflect total federal assistance. Questioned Costs: No questioned costs were identified as a result of our procedures Context: The condition was noted during our reconciliation procedures of the schedule of expenditures of federal awards Repeat Finding from Prior Years: No. Recommendation: We recommend MARTA review their policies and procedures to ensure that the schedule of expenditures of federal awards properly captures all applicable expenditures. Views of Responsible Official and Planned Corrective Actions: Management agrees. See separately issued Corrective Action Plan.

Corrective Action Plan

Finding 2021-003 Finding Summary: During the audit performed by Eide Bailly LLP, it was noted that costs in the amount of $112,752 related to Formula Grants for Rural Areas, Congestion Mitigation and Air Quality Improvement Program were not included in the schedule of expenditures of federal awards provided by management. Responsible Individuals: Jeremy Myers, Certified Public Accountant Sean Gillingham, Financial Analyst Sandy Benson, General Manager Corrective Action Plan: MARTA will review and update its policies and procedures to ensure all applicable federal expenditures are captured and appropriately presented on the schedule of expenditures of federal awards. Anticipated Completion Date: Effective Immediately

About Other →

FY 2020-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on September 29, 2022. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by March 29, 2023, which was (1240 days ago).

What is a management decision? →
2020-002
Cost Allowability
MATERIAL WEAKNESSQUESTIONED COSTS
Condition

United States Department of Transportation ? Federal Transit Administration passed through the State of California Department of Transportation CFDA # 20.509, Formula Grants for Rural Areas, Section 5311 (f) - Grant 64C019-01007 Compliance Requirement: Allowable Costs and Cost Principles Material Weakness in internal control over compliance; material noncompliance Criteria: Per 2 CFR Section 200.400, management is responsible for the efficient and effective administration of the Federal award through the application of sound management practices. Furthermore, management is responsible for administering Federal funds in a manner consistent with underlying agreements, program objectives, and the terms and conditions of the Federal award. Further, per 2 CFR Section 200.302, MARTA?s financial management systems, including records documenting compliance with Federal statutes, regulations, and terms and conditions of the Federal award, must be sufficient to allow for tracing of funds to a level of expenditures adequate to establish that funds have been used according to the terms and conditions of the award. Condition: During the audit we noted that the cost pool used for the preparation of the request for reimbursement for grant 64CO19-01007 could not be determined by management of MARTA. Cause: MARTA?s federal award management and internal control structure did not allow for the proper data retention necessary to accurately determine the applicable cost pool. As a result, we were unable to validate that such costs were used in accordance with the terms and conditions of the aware. Effect: As management was unable to determine the cost pool used during the preparation of the request for reimbursement for grant 64CO19-01007, the costs allocated to the grant could not be tested. Questioned Costs: Grant expenditures totaled $214,772 as identified on the SEFA. Context/Sampling: The grant award total was reported on the SEFA, and claimed for reimbursement by MARTA ($214,772). However, as described above, management was unable to identify the cost pool used for the reimbursement, and as a result, we were unable to complete our sample and testing. Repeat Finding from Prior Year(s): No Recommendation: We recommend that MARTA reviews and updates policies and procedures over the administration of federal funds to ensure that all applicable expenditures are properly tracked, compiled, and allocated to the correct grant. Views of Responsible Official and Planned Corrective Actions: Management agrees. See separately issued Corrective Action Plan.

Corrective Action Plan

Finding 2020-002 Finding Summary: During the audit performed by Eide Bailly LLP, it was noted that the cost pool used for the preparation of the request for reimbursement for grant 64CO19-01007 could not be determined by management of MARTA. Responsible Individuals: Jeremy Myers, Certified Public Accountant Sean Gillingham, Financial Analyst Sandy Benson, General Manager Corrective Action Plan: MARTA will review and modify its policies and practices to clearly identify expenditures that qualify for capital/operating expense reimbursement for the period in which the expenditure was incurred. This will ensure that the appropriate costs are being reimbursed by the granting agencies. Anticipated Completion Date: Effective Immediately

About Allowable Costs / Cost Principles →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →

Single Audit Intelligence is an independent tool powered by Federal Audit Clearinghouse data. Not affiliated with GSA, OMB, or any federal agency.