Hidalgo County Regional Mobility Authority

EIN: 262731494

UEI: JEPHUCNMTCT5

Data as of August 26, 2026

Hidalgo County Regional Mobility Authority6 audit years1 findings
6
Audit Years
1
Total Findings
0
Repeat Findings

FY 2023-12-31

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on April 26, 2024. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by October 26, 2024 (669 days ago).

What is a management decision? →
2023-001
Special Tests & Provisions

Reference Number 2023-001 Quality Assurance Program Verification Activities Criteria: The provisions of 23 CFR Part 637 require that the quality of the materials be validated by verification sampling and testing. The sampling and testing should be performed by qualified sampling and testing personnel. Condition Found: We selected a sample of 40 sampling and testing activities and verified whether technicians performing testing were certified by Texas Department of Transportation (TxDOT). In the sample tested, we noted one technician, who performed 4 of the 40 tests selected in our sample, was not certified. In November 2023, TxDOT performed a monitoring compliance review and had previously noted the same observation regarding the same technician that was not certified. Management indicated that prompt corrective action was taken to address this issue. None of the testing reports reviewed in our sample by this technician occurred after the findings report was issued TxDOT. Effect: Quality and materials testing performed by technicians who are not certified by TxDOT does not meet the requirements of 23 CFR Part 637. Questioned Costs: $0 Cause: Controls were not enforced to ensure all technicians performing sampling and testing activities were properly certified. Recommendation: We recommend HCRMA strengthen internal controls to ensure all technicians performing testing are properly certified. Repeat Finding from Prior Year(s): N/A Views of Responsible Officials: See management’s corrective action plan.

Show full finding ▾
Full finding narrative

Reference Number 2023-001 Quality Assurance Program Verification Activities Criteria: The provisions of 23 CFR Part 637 require that the quality of the materials be validated by verification sampling and testing. The sampling and testing should be performed by qualified sampling and testing personnel. Condition Found: We selected a sample of 40 sampling and testing activities and verified whether technicians performing testing were certified by Texas Department of Transportation (TxDOT). In the sample tested, we noted one technician, who performed 4 of the 40 tests selected in our sample, was not certified. In November 2023, TxDOT performed a monitoring compliance review and had previously noted the same observation regarding the same technician that was not certified. Management indicated that prompt corrective action was taken to address this issue. None of the testing reports reviewed in our sample by this technician occurred after the findings report was issued TxDOT. Effect: Quality and materials testing performed by technicians who are not certified by TxDOT does not meet the requirements of 23 CFR Part 637. Questioned Costs: $0 Cause: Controls were not enforced to ensure all technicians performing sampling and testing activities were properly certified. Recommendation: We recommend HCRMA strengthen internal controls to ensure all technicians performing testing are properly certified. Repeat Finding from Prior Year(s): N/A Views of Responsible Officials: See management’s corrective action plan.

Corrective Action Plan

Reference Number 2023-001 Quality Assurance Program Verification Activities (ALN 20.205) Corrective Action: Upon notification by TxDOT of the non-compliance on the 365 Tollway Project, the Authority took the following action: 1. Suspended work with consultant on November 10, 2023, and subsequently terminated their contract on December 21, 2023, for non-compliance with quality assurance requirements. 2. Enforced the contract with its Owner’s Independent Assurance Program (IAP) consultant to provide continuous monitoring of all technician certifications/accreditations for the life of the project. 3. Procured services to perform forensic investigation and evaluation of the work performed by the non-compliant technicians to confirm materials meet quality assurance standards. Proposed Completion Date: The IAP is monitoring all technician certifications/accreditation and will continue monitoring for the life of the project. The forensic investigation and evaluation of the work performed by the non-compliant technicians will be completed by December 2024. Name of contact person: Pilar Rodriguez, P.E., Executive Director Contact Information: (956) 402-3762 prodriguez@hcrma.net

About Special Tests and Provisions →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.

Start monitoring →