Management decision deadline — for entities that funded this organization
The FAC accepted this audit on March 30, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 30, 2026 (34 days from today).
What is a management decision? →During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.
Show full finding ▾Hide full finding ▴2025-001 - Procurement, Debarment and Suspension Federal Program Information: U.S. Department of the Treasury, passed through the Vermont Department of Public Safety CFDA - 21.027 - Coronavirus State and Local Fiscal Recovery Funds Criteria: The following CFRs apply to this finding: 2 CFR 200.214, 2 CFR section 200.317-200.327 Condition: During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.
Corrective Action Plan Contact Person: Belinda Harris Clegg, Wolcott Town Clerk & Treasurer Corrective Action: The Selectboard will update their Purchasing Policy to include checking Sam.gov to confirm if a contractor has not been debarred or suspended from receiving federal funds and to request a Suspension and Debarment certification from the contractor. Anticipated Completion Date: April 30, 2026
During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.
Show full finding ▾Hide full finding ▴2025-001 - Procurement, Debarment and Suspension Federal Program Information: U.S. Department of the Treasury, passed through the Vermont Department of Public Safety CFDA - 21.027 - Coronavirus State and Local Fiscal Recovery Funds Criteria: The following CFRs apply to this finding: 2 CFR 200.214, 2 CFR section 200.317-200.327 Condition: During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.
Corrective Action Plan Contact Person: Belinda Harris Clegg, Wolcott Town Clerk & Treasurer Corrective Action: The Selectboard will update their Purchasing Policy to include checking Sam.gov to confirm if a contractor has not been debarred or suspended from receiving federal funds and to request a Suspension and Debarment certification from the contractor. Anticipated Completion Date: April 30, 2026
Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.
Track your findings and corrective action plans across audit cycles.
Start tracking findings →Monitor subrecipient audit findings and compliance status.
Start monitoring →© 2026 Single Audit Intelligence. All data is public domain.