Town of Wolcott, Vermont

EIN: 036000784

UEI: ULQDEG85G2V5

Data as of August 27, 2026

Town of Wolcott, Vermont2 audit years2 findings
2
Audit Years
2
Total Findings
0
Repeat Findings

FY 2025-06-30

Management decision deadline — for entities that funded this organization

The FAC accepted this audit on March 30, 2026. Under 2 CFR 200.521(d), a pass-through entity that provided federal funds to this organization for this audit period must issue a management decision on these findings by September 30, 2026 (34 days from today).

What is a management decision? →
2025-001
Procurement & Suspension/Debarment
MATERIAL WEAKNESS

During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.

Show full finding ▾
Full finding narrative

2025-001 - Procurement, Debarment and Suspension Federal Program Information: U.S. Department of the Treasury, passed through the Vermont Department of Public Safety CFDA - 21.027 - Coronavirus State and Local Fiscal Recovery Funds Criteria: The following CFRs apply to this finding: 2 CFR 200.214, 2 CFR section 200.317-200.327 Condition: During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.

Corrective Action Plan

Corrective Action Plan Contact Person: Belinda Harris Clegg, Wolcott Town Clerk & Treasurer Corrective Action: The Selectboard will update their Purchasing Policy to include checking Sam.gov to confirm if a contractor has not been debarred or suspended from receiving federal funds and to request a Suspension and Debarment certification from the contractor. Anticipated Completion Date: April 30, 2026

About Procurement and Suspension and Debarment →
2025-001
Procurement & Suspension/Debarment
MATERIAL WEAKNESS

During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.

Show full finding ▾
Full finding narrative

2025-001 - Procurement, Debarment and Suspension Federal Program Information: U.S. Department of the Treasury, passed through the Vermont Department of Public Safety CFDA - 21.027 - Coronavirus State and Local Fiscal Recovery Funds Criteria: The following CFRs apply to this finding: 2 CFR 200.214, 2 CFR section 200.317-200.327 Condition: During audit procedures it was identified that the Town did not check sam.gov to confirm that the contractor was not debarred or suspended from receiving federal funds nor did they request a Suspension and Debarment certification from the contractor. Cause: The Town does not have the necessary internal controls over compliance. Effect: Contracts may be awarded to contractors that are debarred or suspended from working on federally funded projects. Identification of Questioned Costs: None Identified. Context: Two contracts were reviewed out of three. This is not a statistically valid sample. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Town revise its procurement policy to fully incorporate all elements required by 2 CFR §200.317-200.327. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.

Corrective Action Plan

Corrective Action Plan Contact Person: Belinda Harris Clegg, Wolcott Town Clerk & Treasurer Corrective Action: The Selectboard will update their Purchasing Policy to include checking Sam.gov to confirm if a contractor has not been debarred or suspended from receiving federal funds and to request a Suspension and Debarment certification from the contractor. Anticipated Completion Date: April 30, 2026

About Procurement and Suspension and Debarment →

Data source: This information comes from the Federal Audit Clearinghouse, the official repository of Single Audit data. All data is public domain. Verify this organization's audit history at fac.gov.

Are you this organization?

Track your findings and corrective action plans across audit cycles.

Start tracking findings →

Do you fund this organization?

Monitor subrecipient audit findings and compliance status.